Question

Water Movers, Inc. is known throughout the world for its H2O-X high-capacity water pump, used in irrigation systems. The pump’s standard cost is as follows. The company’s predetermined fixed overhead rate is based on an expected capacity of 100,000 direct labor hours per month.

Direct materials Direct labor Variable overhead Fixed overhead Standard Price Standard Quantity Standard Cost $96 40 36 20 $192 $6 per pound $10 per DLH $9 per DLH $5 per DLH 16 pounds 4 DLH 4 DLH 4 DLH During the month of September, the company produced 22,210 of the 25,000 pumps that had been scheduled for production in the budget. The company used 406,600 pounds of material during September. The direct labor payroll for the month was $1,012,000 for 92,000 direct labor hours. Variable overhead costs were $813,000; fixed overhead costs were $537,700. The companys purchasing agent signed a new supply contract that resulted in purchases of 526,300 pounds of direct materials at a total price of $2,894,650 Calculate Water Movers direct materials, direct labor, and overhead variances for September. (Round per unit values to 2 decimal places, e.g. 15.25 & final answers to 0 decimal places, e.g. 5,725. If variance is zero, select Not Applicable and enter o for the amounts.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Standard Actual
SQ / SH SR Total AQ / AH AR Total
Direct Material    355,360.00           6.00      2,132,160.00    406,600.00           5.50    2,236,300.00
Direct Labor      88,840.00         10.00          888,400.00      92,000.00         11.00    1,012,000.00
Variable Overhead      88,840.00           9.00          799,560.00      92,000.00           8.84        813,000.00
Actual Production = 22,210 Pumps
Direct Material Price Variance = (SR - AR) X AQ Purchased
Direct Material Price Variance = ($6 - $5.50) X 526,300 pounds
Direct Material Price Variance = $263,150 (F)
Direct Materials Quantity Variance = (SQ - AQ) X SR
Direct Materials Quantity Variance = (355,360 pounds - 406,600 pounds) X $6
Direct Materials Quantity Variance = $307,440 (U)
Direct Labor Rate Variance = (SR - AR) X AH
Direct Labor Rate Variance = ($10 - $11) x 92,000 Hrs
Direct Labor Rate Variance = $92,000 (U)
Direct Labor Efficiency Variance = (SH - AH) X SR
Direct Labor Efficiency Variance = (88,840 hrs - 92,000 hrs) X $10
Direct Labor Efficiency Variance = $31,600 (U)
Variable Overhead Spending Variance = (SR - AR) X AH
Variable Overhead Spending Variance = ($9 -$8.84) X 92,000 hrs
Variable Overhead Spending Variance = $15,000 (F)
Variable Overhead Efficiency Variance = (SH - AH) X SR
Variable Overhead Efficiency Variance = (88,840 hrs - 92,000 hrs) X $9
Variable Overhead Efficiency Variance = $28,440 (U)
Fixed Overhead Spending Variance = Budgeted Overhead - Actual Overhead
Fixed Overhead Spending Variance = $500,000 - $537,700
Fixed Overhead Spending Variance = $37,700 (U)
Add a comment
Know the answer?
Add Answer to:
Water Movers, Inc. is known throughout the world for its H2O-X high-capacity water pump, used in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem T4-11 Water Movers, Inc. is known throughout the world for its H2O-X high-capacity water pump,...

    Problem T4-11 Water Movers, Inc. is known throughout the world for its H2O-X high-capacity water pump, used in irrigation systems. The company uses a standard costing system, and the pump’s standard cost is as follows. The company’s predetermined fixed overhead rate is based on an expected capacity of 100,000 direct labor hours per month. Problem T1-11 Your answer is partially correct. Try again. Water Movers, Inc. is known throughout the world tor its H20O-X high-capacity water pump, used in irrigation...

  • Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Sunland, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $11 per DLH 0.50 DLH 5.50 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $28.00 At...

  • Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Vaughn, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH 0.50 DLH 5.00 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $27.50 At...

  • Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Carson, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH .5 DLH 5.00 Variable overhead $9 per DLH .5 DLH 4.50 Fixed overhead $16 per DLH .5 DLH 8.00 Total standard cost per test $19.50 At...

  • World Company expects to operate at 60% of its productive capacity of 28,000 units per month....

    World Company expects to operate at 60% of its productive capacity of 28,000 units per month. At this planned level, the company expects to use 7,560 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.450 direct labor hour per unit. At the 60% capacity level, the total budgeted cost includes $22,680 fixed overhead cost and $60,480 variable overhead cost. In the current month, the company incurred $63,920 actual overhead and 7,130 actual...

  • World Company expects to operate at 80% of its productive capacity of 68,750 units per month....

    World Company expects to operate at 80% of its productive capacity of 68,750 units per month. At this planned level, the company expects to use 30,800 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.560 direct labor hours per unit. At the 80% capacity level, the total budgeted cost includes $73,920 fixed overhead cost and $397,320 variable overhead cost. In the current month, the company incurred $487,000 actual overhead and 27,800 actual...

  • World Company expects to operate at 80 % of its productive capacity of 55,000 units per...

    World Company expects to operate at 80 % of its productive capacity of 55,000 units per month. At this planned level, the company expects to use 23,100 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.525 direct labor hours per unit At the 80% capacity level, the total budgeted cost includes $60.060 fixed overhead cost and $267,960 variable overhead cost. In the current month, the company incurred $342,000 actual overhead and 20100...

  • World Company expects to operate at 80% of its productive capacity of 70,000 units per month....

    World Company expects to operate at 80% of its productive capacity of 70,000 units per month. At this planned level, the company expects to use 25,200 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.450 direct labor hours per unit. At the 80% capacity level, the total budgeted cost includes $57,960 fixed overhead cost and $322,560 variable overhead cost. In the current month, the company incurred $386,000 actual overhead and 22,200 actual...

  • World Company expects to operate at 90% of its productive capacity of 30,000 units per month....

    World Company expects to operate at 90% of its productive capacity of 30,000 units per month. At this planned level, the company expects to use 10,800 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.400 direct labor hours per unit. At the 90% capacity level, the total budgeted cost includes $21,600 fixed overhead cost and $194,400 variable overhead cost. In the current month, the company incurred $120,700 actual overhead and 6,380 actual...

  • World Company expects to operate at 60% of its productive capacity of 32,000 units per month....

    World Company expects to operate at 60% of its productive capacity of 32,000 units per month. At this planned level, the company expects to use 12,000 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.625 direct labor hours per unit. At the 60% capacity level, the total budgeted cost includes $36,000 fixed overhead cost and $120,000 variable overhead cost. In the current month, the company incurred $116,000 actual overhead and 5,760 actual...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT