Question

Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Sunland, based on performing 2,100 core tests per month.

Standard Price Standard Quantity Standard Cost
Direct materials $0.50 per pound 4 pounds $2.00
Direct labor $11 per DLH 0.50 DLH 5.50
Variable overhead $9 per DLH 0.50 DLH 4.50
Fixed overhead $16 per DLH 1 DLH 16.00
Total standard cost per test $28.00
At the end of March, London reported the following operational results:
The company actually performed 2,300 core tests during the month.
8,600 pounds of direct materials were purchased during the month at a total cost of $5,800.
6,300 pounds of direct materials were used to conduct the core tests.
860 direct labor hours were worked at a total cost of $9,830.
Actual variable overhead was $8,000.
Actual fixed overhead was $15,900.


(b) Calculate the direct materials quantity variance for March. (Round answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter 0 for the amounts.)

(c) Calculate the direct labor rate variance for March. (Round per unit value to 2 decimal places, e.g. 52.75 and final answer to 0 decimal places, e.g. 5,275. If variance is zero, select "Not Applicable" and enter 0 for the amounts.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Material Quantity Variance (MQV) = ( SQ-AQ) SP >>MQV = 1 9200 - 6300 ) * 0.5 >>MQV - 1450,00 Favorable Note-1 SQ = Standard QParticulars Direct Labour SH 1150 SR 11 AHP 860 AR 11.43 Labour Rate Variance (LV) = ( SR - ARAHP >>LRV = ( 11 - 11.43) * 860

Add a comment
Know the answer?
Add Answer to:
Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. month. he following standard costs...

    Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. month. he following standard costs for the tests have bean developed by the company's controller, Landon Vaughn, based on performing 2,100 care tests Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds 2.00 Direct labar $10 per DLH a.50 DLH 5.00 ead ived cuechead 16 $27.50 Total standard cost per test March, London reported the following operational results At the end The company actually performed...

  • Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Vaughn, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH 0.50 DLH 5.00 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $27.50 At...

  • Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Carson, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH .5 DLH 5.00 Variable overhead $9 per DLH .5 DLH 4.50 Fixed overhead $16 per DLH .5 DLH 8.00 Total standard cost per test $19.50 At...

  • QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests...

    QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: SP Direct materials, 3 pounds @ $0.75 per pound. Direct labor, 0.4 hours @ $12.00 per hour.se Variable factory overhead, 0.4 hours @ $4.00 per hour. Fixed factory overhead, 0.4 hours @ $10.00 per hour. Manufacturing overhead is assigned to core tests on the basis of direct labor hours. Budgeted...

  • Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in...

    Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed based on planned activity of 1,800 core tests: Standard Hours or Quantity Standard Price or Rate Price Per Unit Direct materials ........................................ 3 pounds $0.75 per pound $2.25 Direct labor............................................... 0.4 hours $12 per hour $4.80 Variable manufacturing overhead ............ 0.4 hours $9 per hour $3.60 Fixed manufacturing overhead............. $6,800 During...

  • Water Movers, Inc. is known throughout the world for its H2O-X high-capacity water pump, used in...

    Water Movers, Inc. is known throughout the world for its H2O-X high-capacity water pump, used in irrigation systems. The pump’s standard cost is as follows. The company’s predetermined fixed overhead rate is based on an expected capacity of 100,000 direct labor hours per month. Direct materials Direct labor Variable overhead Fixed overhead Standard Price Standard Quantity Standard Cost $96 40 36 20 $192 $6 per pound $10 per DLH $9 per DLH $5 per DLH 16 pounds 4 DLH 4...

  • Sunland Sports has determined the following unit costs for each of its products: Pants Jerseys Jackets...

    Sunland Sports has determined the following unit costs for each of its products: Pants Jerseys Jackets Direct materials $7.00 $10.00 $58.00 Direct labor 4.00 3.60 22.00 Manufacturing overhead 5.00 4.00 34.00 Total unit cost $16.00 $17.60 $114.00 Sales price per unit $21.00 $22.40 $179.00 On May 31, Sunland Sports’ Work in Process Inventory consisted of the following items: Job Units Accumulated Cost PA-1247—Pants 100 $1,150 JE-1397—Jerseys 200 2,800 JA 426—Jackets 50 4,350 $8,300 During June, a total of $267,900 in...

  • Bramble, Ltd. manufactures shirts, which it sells to customers for embroidering with various slogans and emblems....

    Bramble, Ltd. manufactures shirts, which it sells to customers for embroidering with various slogans and emblems. The standard cost card for the shirts is as follows. Bramble, Ltd. manufactures shirts, which it sells to customers for embroidering with various slogans and emblems. The standard cost card for the shirts is as follows. Direct materials Direct labor Variable overhead Fixed overhead Standard Price Standard Quantity Standard Cost $4 per yard 1.50 yards $6.00 $12 per DLH 0.50 DLH 6.00 $4 per...

  • Waterways Corporation uses very stringent standard costs in evaluating its manufacturing efficiency. These standards are not...

    Waterways Corporation uses very stringent standard costs in evaluating its manufacturing efficiency. These standards are not “ideal” at this point, but the management is working toward that as a goal. At present, the company uses the following standards. Materials Item Per unit Cost Metal 1 lb. 63¢ per lb. Plastic 12 oz. $1.00 per lb. Rubber 4 oz. 88¢ per lb. Direct labor Item Per unit Cost Labor 15 min. $8.00 per hr. Predetermined overhead rate based on direct labor...

  • Waterways Corporation uses very stringent standard costs in evaluating its manufacturing efficiency. These standards are not...

    Waterways Corporation uses very stringent standard costs in evaluating its manufacturing efficiency. These standards are not "ideal" at this point, but the management is working toward that as a goal. At present, the company uses the following standards Materials Item Per unit Cost 63 per lb. $100 per lb. Metal 1lb. Plastic 12 oz Rubber 4 oz 884 per lb. Direct labor Item Per unit Cost $8.00 per hr Labor 15 min Predetermined overhead rate based on direct labor hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT