Standard DATA for | 2000 | test | |
Quantity (SQ) | Rate (SR) | Standard Cost | |
[A] | [B] | [A x B] | |
Direct Material | ( 3 Pound x 2000 test)=6000 Pound | $ 0.75 | $ 4,500.00 |
Direct labor | ( 0.4hr x 2000 test)=800hr | $ 12.00 | $ 9,600.00 |
Variable Overhead | ( 0.4hr x 2000 test)=800hr | $ 4.00 | $ 3,200.00 |
Actual DATA for | 2000 | test | |
Quantity (AQ) | Rate (AR) | Actual Cost | |
Direct Material | 7200 | $ 0.85 | $ 6,120.00 |
Direct labor | 840 | $ 10.25 | $ 8,610.00 |
Variable Overhead | 840 | $ 3.81 | $ 3,200.00 |
Variable Overhead Rate Variance | ||||||
( | Standard Rate | - | Actual Rate | ) | x | Actual Labor Hours |
( | $ 4.00 | - | $ 3.81 | ) | x | 840 |
160 | ||||||
Variance | $ 160.00 | Favourable-F | ||||
Variable Overhead Efficiency Variance | ||||||
( | Standard Hours | - | Actual Hours | ) | x | Standard Rate |
( | 800 | - | 840 | ) | x | $ 4.00 |
-160 | ||||||
Variance | $ 160.00 | Unfavourable-U |
Note no. | Explanation |
1 | Standard data is calculated by considering budgeted data and using actual data. |
2 | Variance refers to the difference between Standard cost and Actual cost. |
3 | If Actual cost is MORE than Standard Cost, the Variance is said to be UNFAVOURABLE. |
4 | If Actual cost is LESS than Standard Cost, the Variance is said to be FAVOURABLE. |
QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests...
Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed based on planned activity of 1,800 core tests: Standard Hours or Quantity Standard Price or Rate Price Per Unit Direct materials ........................................ 3 pounds $0.75 per pound $2.25 Direct labor............................................... 0.4 hours $12 per hour $4.80 Variable manufacturing overhead ............ 0.4 hours $9 per hour $3.60 Fixed manufacturing overhead............. $6,800 During...
I know you can only answer the first four
but if you could include the formulas for the other 2 I would
appreciate it. Thanks
30. The labor rate variance for March is: A) $4,578 unfavorable. B) $1,470 unfavorable. C) $4,578 favorable. D) $1,470 favorable. QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: 31. The labor efficiency variance...
Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Vaughn, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH 0.50 DLH 5.00 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $27.50 At...
Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Carson, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH .5 DLH 5.00 Variable overhead $9 per DLH .5 DLH 4.50 Fixed overhead $16 per DLH .5 DLH 8.00 Total standard cost per test $19.50 At...
Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Sunland, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $11 per DLH 0.50 DLH 5.50 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $28.00 At...
Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. month. he following standard costs for the tests have bean developed by the company's controller, Landon Vaughn, based on performing 2,100 care tests Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds 2.00 Direct labar $10 per DLH a.50 DLH 5.00 ead ived cuechead 16 $27.50 Total standard cost per test March, London reported the following operational results At the end The company actually performed...
Use the following information for the next three questions. Oak Company uses a standard costing system. Manufacturing overhead costs are applied to products on the basis of direct labor hours. The standard cost card shows that 5 direct labor hours at the hourly rate of $25 per hour are required per unit of product. Oak Company had the following data for March: Actual Budgeted Units produced 22,000 20,000 Direct labor hours 105,000 100,000 Variable overhead costs $91,000 $80,000 Fixed overhead...
this is a multi-part
question
Required information The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows Direct materials: 5 pounds at $7 per pound Direct labor: 3 hours at $16 per hour 48 Variable overhead: 3 hours at $4 12 per hour $ 95 Total standard cost per unit The planning budget for...
Required information [The following information applies to the questions displayed below.) The Platter Valley factory of Bybee Industries manufactures field boots. The cost of each boot includes direct materials, direct labor, and manufacturing (factory) overhead. The firm traces all direct costs to products, and it assigns overhead cost to products based on direct labor hours. The company budgeted $15,000 variable factory overhead cost and 2,500 direct labor hours to manufacture 5,000 pairs of boots in March. The factory used 2,700...
Answer the next the questions using the following information: re was planning to product 900 tablets in March, but they ended up producing 920 tablets Company produces a lightweigh tablet that is page with college students. Filmore was standard costing. It standards of production March Master (sistic planning) budget, and a March Master Actual costs Standards incurred Direct Materials $5.40 per yard 24 100 $23,050 Direct Labor 7 per DLHS $ 20.250 $21,500 Variable MOH 52.00 per DLH S 2,700...