I know you can only answer the first four but if you could include the formulas for the other 2 I would appreciate it. Thanks
28) Materials Price Variance – The correct option is A) $860 Unfavorable
Material Price Variance is the variance arises in the material cost due to difference in actual material purchase price from standard material price. Mathematically, it is calculated as below:
Material Price Variance = Actual Quantity (Standard Price – Actual Price)
Note --- Here actual quantity means actual quantity of material PURCHASED. If the question does not provide the information about material purchase, it is taken as equal to material consumed.
Direct Material Price Variance |
||
Actual Price (Actual Cost $7,310 / Actual quantity purchased 8,600 pounds) |
$0.85 |
per pound |
Standard Price |
$0.75 |
per pound |
Variance or Difference in Price |
$0.10 |
per pound |
x Actual Quantity PURCHASED |
8,600 |
pounds |
Direct Material Price Variance |
$860 |
Unfavorable |
29) Material Quantity/Efficiency/Usage Variance – The correct option is D) $900 Unfavorable
Material Efficiency (Usage) Variance measures variance in material cost due to usage/consumption of materials. It is calculated as below:
Material Quantity Variance = Standard Price (Standard Quantity for Actual Production – Actual Quantity USED)
Note --- Here actual quantity means actual quantity of material CONSUMED/USED
Direct Material Quantity/Efficiency/Usage Variance |
||
Standard Quantity Allowed for actual production: |
||
Actual Production/Activity |
2000 |
tests |
x Allowed Standard Quantity Per Unit |
3 |
Pounds |
Total Standard Quantity Allowed for actual production (SQAP) |
6,000 |
Pounds |
Actual Quantity USED |
7,200 |
pounds |
Variance or Difference in Quantity |
1,200 |
pounds |
x Standard Price (SP) |
$0.75 |
per pound |
Material Quantity/Efficiency Variance |
$900 |
Unfavorable |
30) Labor Rate/Price Variance – The correct option is D) $1,470 Favorable
Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:
Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)
Here, actual time means time for which wage has been paid.
Labor Rate Variance |
||
Actual Hourly Rate (Actual Cost $8,610 / Actual Labor Hours 840) |
$10.25 |
Per Hour |
Standard Hourly Rate |
$12.00 |
Per Hour |
Variance or Difference in Rate |
$1.75 |
Per Hour |
x Actual Labor Hours worked |
840 |
Hours |
Labor Rate Variance |
$1,470 |
Favorable |
31) Labor Quantity Variance – The correct option is B) $480 Unfavorable
Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.
Labor Quantity / Efficiency Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
2000 |
Tests |
x Allowed Standard Hours Per Unit |
0.4 |
hours |
Total Standard Hours Allowed for actual production (SHAP) |
800 |
hours |
Actual Labor Hours Worked |
840 |
hours |
Variance or Difference in Hours |
40 |
hours |
x Standard Hourly Rate (SHR) |
$12 |
per hour |
Labor Efficiency Variance |
$480 |
Unfavorable |
32) Variable Overhead Rate Variance – the correct option is D) $160 favorable
Variable Overhead Rate Variance |
||
Actual Hourly Variable Overhead Rate ($3,200 Actual / 840 Actual Labor Hours) |
3.81 |
Per Hour |
Standard Hourly Variable Overhead Rate |
4.00 |
Per Hour |
Variance or Difference in Rate |
0.19 |
Per Hour |
x Actual Hours Worked |
840 |
Hours |
Variable Overhead Rate Variance |
$160 |
Favorable |
33) Variable Overhead Efficiency Variance – The correct option is C) $160 Unfavorable
Variable Overhead Efficiency/Quantity Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
2,000 |
Pools |
x Allowed Standard Hours Per Unit |
0.4 |
Hours |
Total Standard Hours Allowed for actual production (SHAP) |
800 |
Hours |
Actual Hours Worked (AH) |
840 |
Hours |
Variance or Difference in Hours |
40 |
hours |
x Standard Hourly Variable Overhead Rate |
$4.00 |
per hour |
Variable Overhead Efficiency Variance |
$160 |
Unfavorable |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
I know you can only answer the first four but if you could include the formulas...
Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed based on planned activity of 1,800 core tests: Standard Hours or Quantity Standard Price or Rate Price Per Unit Direct materials ........................................ 3 pounds $0.75 per pound $2.25 Direct labor............................................... 0.4 hours $12 per hour $4.80 Variable manufacturing overhead ............ 0.4 hours $9 per hour $3.60 Fixed manufacturing overhead............. $6,800 During...
QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: SP Direct materials, 3 pounds @ $0.75 per pound. Direct labor, 0.4 hours @ $12.00 per hour.se Variable factory overhead, 0.4 hours @ $4.00 per hour. Fixed factory overhead, 0.4 hours @ $10.00 per hour. Manufacturing overhead is assigned to core tests on the basis of direct labor hours. Budgeted...
5. If Preble had purchased 182,000 pounds of materials at $7.40 per pound and used 160,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.) 6. If Preble had purchased 182,000 pounds of materials at $7.40 per pound and used 160,000 pounds in production, what would be the materials...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard cost per unit $ 40.00 28.00 10.00 $78.00 The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually...
Revise the data in your worksheet to reflect the results for the subsequent period as shown below: A B C D E 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Chapter 09: Applying Excel Data Exhibit 9-8: Standard Cost Card Inputs Standard Quantity Standard Price Direct materials 3.0 pounds $4.00 per pound Direct labor 0.50 hours $22.00 per hour Variable manufacturing overhead 0.50 hours $6.00 per hour Actual results: Actual output 2,040 units...
1. What raw materials cost would be included in the company's planning budget for March? 2. What raw materials cost would be included in the company's flexible budget for March? 3. What is the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.) 4. What is the materials quantity variance for March? (Indicate the effect of...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $10.00 per pound$50.00Direct labor: 3 hours at $17 per hour51.00Variable overhead: 3 hours at $7 per hour21.00Total standard variable cost per unit$122.00 The company also established the following cost formulas for its selling expenses: Fixed Cost per MonthVariable Cost per Unit SoldAdvertising$330,000Sales salaries and commissions$360,000$25.00Shipping expenses$16.00 The planning budget for March was...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $10.00 per pound$50.00Direct labor: 3 hours at $17 per hour51.00Variable overhead: 3 hours at $7 per hour21.00Total standard variable cost per unit$122.00 The company also established the following cost formulas for its selling expenses: Fixed Cost per MonthVariable Cost per Unit SoldAdvertising$330,000Sales salaries and commissions$360,000$25.00Shipping expenses$16.00 The planning budget for March was...
I'm only missing these two questions , thank you for your help! Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Required 5 GLAR Required 6 Required 7 Required 8 What was the labor rate variance for March? The labor efficiency variance? (Do not rond your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance)....