Question

30. The labor rate variance for March is: A) $4,578 unfavorable. B) $1,470 unfavorable. C) $4,578 favorable. D) $1,470 favoraI know you can only answer the first four but if you could include the formulas for the other 2 I would appreciate it. Thanks

0 0
Add a comment Improve this question Transcribed image text
Answer #1

28) Materials Price Variance – The correct option is A) $860 Unfavorable

Material Price Variance is the variance arises in the material cost due to difference in actual material purchase price from standard material price. Mathematically, it is calculated as below:

Material Price Variance = Actual Quantity (Standard Price – Actual Price)

Note --- Here actual quantity means actual quantity of material PURCHASED. If the question does not provide the information about material purchase, it is taken as equal to material consumed.

Direct Material Price Variance

Actual Price

(Actual Cost $7,310 / Actual quantity purchased 8,600 pounds)

$0.85

per pound

Standard Price

$0.75

per pound

Variance or Difference in Price

$0.10

per pound

x Actual Quantity PURCHASED

8,600

pounds

Direct Material Price Variance

$860

Unfavorable

29) Material Quantity/Efficiency/Usage Variance – The correct option is D) $900 Unfavorable

Material Efficiency (Usage) Variance measures variance in material cost due to usage/consumption of materials. It is calculated as below:

Material Quantity Variance = Standard Price (Standard Quantity for Actual Production – Actual Quantity USED)

Note --- Here actual quantity means actual quantity of material CONSUMED/USED

Direct Material Quantity/Efficiency/Usage Variance

Standard Quantity Allowed for actual production:

Actual Production/Activity

2000

tests

x Allowed Standard Quantity Per Unit

3

Pounds

Total Standard Quantity Allowed for actual production (SQAP)

6,000

Pounds

Actual Quantity USED

7,200

pounds

Variance or Difference in Quantity

1,200

pounds

x Standard Price (SP)

$0.75

per pound

Material Quantity/Efficiency Variance

$900

Unfavorable

30) Labor Rate/Price Variance – The correct option is D) $1,470 Favorable

Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:

Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)

Here, actual time means time for which wage has been paid.

Labor Rate Variance

Actual Hourly Rate (Actual Cost $8,610 / Actual Labor Hours 840)

$10.25

Per Hour

Standard Hourly Rate

$12.00

Per Hour

Variance or Difference in Rate

$1.75

Per Hour

x Actual Labor Hours worked

840

Hours

Labor Rate Variance

$1,470

Favorable

31) Labor Quantity Variance – The correct option is B) $480 Unfavorable

Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.

Labor Quantity / Efficiency Variance

Standard Hours Allowed for actual production:

Actual Production

2000

Tests

x Allowed Standard Hours Per Unit

0.4

hours

Total Standard Hours Allowed for actual production (SHAP)

800

hours

Actual Labor Hours Worked

840

hours

Variance or Difference in Hours

40

hours

x Standard Hourly Rate (SHR)

$12

per hour

Labor Efficiency Variance

$480

Unfavorable

32) Variable Overhead Rate Variance – the correct option is D) $160 favorable

Variable Overhead Rate Variance

Actual Hourly Variable Overhead Rate ($3,200 Actual / 840 Actual Labor Hours)

3.81

Per Hour

Standard Hourly Variable Overhead Rate

4.00

Per Hour

Variance or Difference in Rate

0.19

Per Hour

x Actual Hours Worked

840

Hours

Variable Overhead Rate Variance

$160

Favorable

33) Variable Overhead Efficiency Variance – The correct option is C) $160 Unfavorable

Variable Overhead Efficiency/Quantity Variance

Standard Hours Allowed for actual production:

Actual Production

2,000

Pools

x Allowed Standard Hours Per Unit

0.4

Hours

Total Standard Hours Allowed for actual production (SHAP)

800

Hours

Actual Hours Worked (AH)

840

Hours

Variance or Difference in Hours

40

hours

x Standard Hourly Variable Overhead Rate

$4.00

per hour

Variable Overhead Efficiency Variance

$160

Unfavorable

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Add a comment
Know the answer?
Add Answer to:
I know you can only answer the first four but if you could include the formulas...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in...

    Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed based on planned activity of 1,800 core tests: Standard Hours or Quantity Standard Price or Rate Price Per Unit Direct materials ........................................ 3 pounds $0.75 per pound $2.25 Direct labor............................................... 0.4 hours $12 per hour $4.80 Variable manufacturing overhead ............ 0.4 hours $9 per hour $3.60 Fixed manufacturing overhead............. $6,800 During...

  • QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests...

    QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: SP Direct materials, 3 pounds @ $0.75 per pound. Direct labor, 0.4 hours @ $12.00 per hour.se Variable factory overhead, 0.4 hours @ $4.00 per hour. Fixed factory overhead, 0.4 hours @ $10.00 per hour. Manufacturing overhead is assigned to core tests on the basis of direct labor hours. Budgeted...

  • 5. If Preble had purchased 182,000 pounds of materials at $7.40 per pound and used 160,000...

    5. If Preble had purchased 182,000 pounds of materials at $7.40 per pound and used 160,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.) 6. If Preble had purchased 182,000 pounds of materials at $7.40 per pound and used 160,000 pounds in production, what would be the materials...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard cost per unit $ 40.00 28.00 10.00 $78.00 The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually...

  • Revise the data in your worksheet to reflect the results for the subsequent period as shown...

    Revise the data in your worksheet to reflect the results for the subsequent period as shown below: A B C D E 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Chapter 09: Applying Excel Data Exhibit 9-8: Standard Cost Card Inputs Standard Quantity Standard Price Direct materials 3.0 pounds $4.00 per pound Direct labor 0.50 hours $22.00 per hour Variable manufacturing overhead 0.50 hours $6.00 per hour Actual results: Actual output 2,040 units...

  • 1. What raw materials cost would be included in the company's planning budget for March? 2....

    1. What raw materials cost would be included in the company's planning budget for March? 2. What raw materials cost would be included in the company's flexible budget for March? 3. What is the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.) 4. What is the materials quantity variance for March? (Indicate the effect of...

  • ACCOUNTING 2

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $10.00 per pound$50.00Direct labor: 3 hours at $17 per hour51.00Variable overhead: 3 hours at $7 per hour21.00Total standard variable cost per unit$122.00 The company also established the following cost formulas for its selling expenses: Fixed Cost per MonthVariable Cost per Unit SoldAdvertising$330,000Sales salaries and commissions$360,000$25.00Shipping expenses$16.00 The planning budget for March was...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $10.00 per pound $ 50.00 Direct labor:

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $10.00 per pound$50.00Direct labor: 3 hours at $17 per hour51.00Variable overhead: 3 hours at $7 per hour21.00Total standard variable cost per unit$122.00 The company also established the following cost formulas for its selling expenses: Fixed Cost per MonthVariable Cost per Unit SoldAdvertising$330,000Sales salaries and commissions$360,000$25.00Shipping expenses$16.00 The planning budget for March was...

  • I'm only missing these two questions , thank you for your help! Complete this question by...

    I'm only missing these two questions , thank you for your help! Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Required 5 GLAR Required 6 Required 7 Required 8 What was the labor rate variance for March? The labor efficiency variance? (Do not rond your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance)....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT