Question

Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in...

Use the following data for questions 25 thru 31:

Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test

performed based on planned activity of 1,800 core tests:

Standard Hours or

Quantity

Standard Price or

Rate

Price Per

Unit

Direct materials ........................................

3 pounds

$0.75 per pound

$2.25

Direct labor...............................................

0.4 hours

$12 per hour

$4.80

Variable manufacturing overhead ............

0.4 hours

$9 per hour

$3.60

Fixed manufacturing overhead.............

$6,800

During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable

manufacturing overhead is assigned to core tests on the basis of standard direct labor-hours. The following events

occurred during March:

• 7,200 pounds of sand were purchased at a cost of $6,120.

• 7,200 pounds of sand were used for core tests.

• 840 actual direct labor-hours were worked at a cost of $8,610.

• Actual variable manufacturing overhead incurred was $7,240.

• Actual fixed manufacturing overhead incurred was $6,500.

25.

The materials price variance for March is:

A. $720 unfavorable

B. $720 favorable

C. $281 unfavorable

D. $281 favorable

26.

The materials quantity variance for March is:

A. $900 favorable

B. $1,950 favorable

C. $1,950 unfavorable D. $900 unfavorable

27.

The labor rate variance for March is:

A. $4,578 unfavorable B. $1,470 unfavorable C. $4,578 favorable D. $1,470 favorable

28.

The labor efficiency variance for March is:

A. $480 favorable

B. $480 unfavorable C. $192 favorable

D. $192 unfavorable

29.

The variable manufacturing overhead price variance for March is:

A. $320 unfavorable

B. $320 favorable

C. $40 unfavorable

D. $40 favorable

30.

The variable manufacturing overhead efficiency variance for March is:

A. $360 unfavorable

B. $360 favorable

C. $40 unfavorable

D. $40 favorable

31.

The total fixed manufacturing overhead variance for March is:

A. $300 unfavorable

B. $300 favorable

C. $40 unfavorable

D. $40 favorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Material Labour Variable O/H Fixed O/H
Standard Standard Standard Standard
Qty Price Total p.u Hours Rate Total p.u Hours Rate Total p.u
3 0.75 2.25 0.4 12 4.8 0.4 9 3.6 6800
Standard (1800 Tests) Standard (1800 Tests) Standard (1800 Tests) Standard (1800 Tests)
Qty Price Total p.u Hours Rate Total p.u Hours Rate Total p.u
5400 0.75 4050 720 12 8640 720 9 6480 6800
Actual (2000 Tests) Actual (2000 Tests) Actual (2000 Tests) Actual (2000 Tests)
Qty Price Total p.u Hours Rate Total p.u Hours Rate Total p.u
7200 0.85 6120 840 10.25 8610 840 8.62 7240 6500
Material Price Variance =(S.P-A.P)*AQ Labour Rate Variance =(S.R-A.R)*AH V O/H Price Variance =(S.R-A.R)*AH Total fixed manufacturing overhead variance
=(0.75-0.85)*7200 -720 =(12-10.25)*840 1470 =(9-8.62)*840 319.2 =Standard Fixed O/H-Actual Fixed O/H
=6800-6500
Material Qty Variance =(S.Q-A.Q)*SP Labour Efficiency Variance =(S.H-A.H)*SR V O/H Efficiency Variance =(S.H-A.H)*SR 300
=(3*2000-7200)*0.75 -900 =(0.4*2000-840)*12 -480 =(0.4*2000-840)*9 -360

25.  The materials price variance for March is: A. $720 unfavorable

26.  The materials quantity variance for March is:   D. $900 unfavorable

27.  The labor rate variance for March is: D. $1,470 favorable

28.  The labor efficiency variance for March is: B. $480 unfavorable

29.  The variable manufacturing overhead price variance for March is: B. $320 favorable

30.  The variable manufacturing overhead efficiency variance for March is: A. $360 unfavorable

31.  The total fixed manufacturing overhead variance for March is:  B. $300 favorable

(Kindly Rate Positively, if found helpful.)

Add a comment
Know the answer?
Add Answer to:
Use the following data for questions 25 thru 31: Cox Engineering performs cement core tests in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests...

    QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: SP Direct materials, 3 pounds @ $0.75 per pound. Direct labor, 0.4 hours @ $12.00 per hour.se Variable factory overhead, 0.4 hours @ $4.00 per hour. Fixed factory overhead, 0.4 hours @ $10.00 per hour. Manufacturing overhead is assigned to core tests on the basis of direct labor hours. Budgeted...

  • I know you can only answer the first four but if you could include the formulas...

    I know you can only answer the first four but if you could include the formulas for the other 2 I would appreciate it. Thanks 30. The labor rate variance for March is: A) $4,578 unfavorable. B) $1,470 unfavorable. C) $4,578 favorable. D) $1,470 favorable. QUESTIONS 28 THROUGH 33 ARE BASED ON THE FOLLOWING INFORMATION: Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: 31. The labor efficiency variance...

  • Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Sunland Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Sunland, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $11 per DLH 0.50 DLH 5.50 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $28.00 At...

  • Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Vaughn, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH 0.50 DLH 5.00 Variable overhead $9 per DLH 0.50 DLH 4.50 Fixed overhead $16 per DLH 1 DLH 16.00 Total standard cost per test $27.50 At...

  • Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for...

    Carson Construction Consultants performs cement core tests in its Greenville laboratory. The following standard costs for the tests have been developed by the company’s controller, Landon Carson, based on performing 2,100 core tests per month. Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds $2.00 Direct labor $10 per DLH .5 DLH 5.00 Variable overhead $9 per DLH .5 DLH 4.50 Fixed overhead $16 per DLH .5 DLH 8.00 Total standard cost per test $19.50 At...

  • Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. month. he following standard costs...

    Vaughn Construction Consultants performs cement core tests in its Greenville laboratory. month. he following standard costs for the tests have bean developed by the company's controller, Landon Vaughn, based on performing 2,100 care tests Standard Price Standard Quantity Standard Cost Direct materials $0.50 per pound 4 pounds 2.00 Direct labar $10 per DLH a.50 DLH 5.00 ead ived cuechead 16 $27.50 Total standard cost per test March, London reported the following operational results At the end The company actually performed...

  • Use the following information to answer questions 5 through 8: Actual results Budget data 20,000 units...

    Use the following information to answer questions 5 through 8: Actual results Budget data 20,000 units produced and sold 19,000 units planned $1,806,700 $90 Direct materials: 62,300 units of input purchased and used @ $29 per input unit - 2.575 Direct labor: 51,500 hours used per output unit @ $21.50 per hour Direct materials: 3 units of input allowed per output unit @ $30 per input unit 47,500 Direct labor: 2.5 hours of input allowed per output unit @ $20...

  • Use the following information for the next three questions. Oak Company uses a standard costing system....

    Use the following information for the next three questions. Oak Company uses a standard costing system. Manufacturing overhead costs are applied to products on the basis of direct labor hours. The standard cost card shows that 5 direct labor hours at the hourly rate of $25 per hour are required per unit of product. Oak Company had the following data for March: Actual Budgeted Units produced 22,000 20,000 Direct labor hours 105,000 100,000 Variable overhead costs $91,000 $80,000 Fixed overhead...

  • 1. Colina Production Company uses a standard costing system. The following information pertains to the current...

    1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...

  • Revise the data in your worksheet to reflect the results for the subsequent period as shown...

    Revise the data in your worksheet to reflect the results for the subsequent period as shown below: A B C D E 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Chapter 09: Applying Excel Data Exhibit 9-8: Standard Cost Card Inputs Standard Quantity Standard Price Direct materials 3.0 pounds $4.00 per pound Direct labor 0.50 hours $22.00 per hour Variable manufacturing overhead 0.50 hours $6.00 per hour Actual results: Actual output 2,040 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT