Question

Use the following information to answer questions 5 through 8: Actual results Budget data 20,000 units produced and sold 19,0
me 10. Which of the following statements regarding fixed overhead is correct? a. Production volume variance is the difference
0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per HOMEWORKLIB RULES we can answer only 4 sub questions in a single question i am answering the first 4 questions. Student may re upload the remaining questions.

Calculation of basic data to answer the questions 5 to 8,

  1. Standard price of material = 30 per unit
  2. Actual price of material = 29 per unit
  3. Actual consumption of material = 62,300 units,
  4. Standard units required = 20,000 x 3 = 60,000,
  5. Standard rate of labour = 20 per hour,
  6. Actual rate of labour = 21.5 per hour
  7. Actual hours worked = 51500 hours,
  8. Standard hours required = 20000 x 2.5 hours = 50000 hours.

5. Material price varience = (Standard price - actual price) x Actual consumption = (30 - 29) x 62,300 = 62,300 Favourable.

6. Material cost varience = (standard price x standard consumption) - (actual price x Actual consumption) = (30 x 60,000) - (29 x 62,300) = 6,700 Unfavourable.

7. Labour price varience = (standard rate - actual rate) x Actual hours worked = (20 - 21.5) x 51500 = 77,250 Unfavourable.

8. Labour efficiency varience = (standard hours - actual hours) x standard rate = (50000 - 51500) x 20 = 30,000 Unfavourable.

Add a comment
Know the answer?
Add Answer to:
Use the following information to answer questions 5 through 8: Actual results Budget data 20,000 units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units...

    The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units Materials:     Standard price per ounce $1.82     Standard ounces per completed unit 12     Actual ounces purchased and used in production 12,805     Actual price paid for materials $26,250 Labor:     Standard hourly labor rate $14.95 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,335.4     Actual total labor costs $81,365 Overhead:     Actual and budgeted fixed overhead $1,110,000     Standard variable overhead rate $28.00 per...

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...

  • The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units...

    The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units Materials:     Standard price per ounce $1.919     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,616     Actual price paid for materials $21,763 Labor:     Standard hourly labor rate $14.76 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,826     Actual total labor costs $78,423 Overhead:     Actual and budgeted fixed overhead $1,025,000     Standard variable overhead rate $24.00 per...

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production   1,021 units Materials:     Standard price per ounce $1.81     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,568     Actual price paid for materials $23,714 Labor:     Standard hourly labor rate $14.51 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,258.15     Actual total labor costs $80,187 Overhead:...

  • The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906...

    The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906 units Materials:     Standard price per pound $1.866     Standard pounds per completed unit 11      Actual pounds purchased and used in production 9,667     Actual price paid for materials $19,817 Labor:     Standard hourly labor rate $14.62 per hour     Standard hours allowed per completed unit 4.0      Actual labor hours worked 4,665.9     Actual total labor costs $71,155 Overhead:     Actual and budgeted fixed overhead $1,181,000     Standard variable overhead rate $26.00...

  • The following information is for the standard and actual costs for the Happy Corporation: Enter favorable...

    The following information is for the standard and actual costs for the Happy Corporation: Enter favorable variances as negative numbers. Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on...

  • Use this information to answer the question that follow. The following data relate to direct materials...

    Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.03 Standard yards per unit: standard, 4.62 yards; actual, 5.06 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$8,128.12 favorable b.$7,927.92 unfavorable c.$7,927.92 favorable d.$8,128.12 unfavorable Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.00 and standard costs for...

  • Acme Company's production budget for August is 18,000 units and includes the following component unit costs:...

    Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials. 58.0 direct labor, 510.5, variable overhead, $6.4. Budgeted fixed overhead is $37,000. Actual production in August was 19.950 units. Actual unit component costs incurred during August include direct materials, $8.70; direct labor, $9.90: variable overhead, 5730. Actual fixed overhead was $39.000. The standard variable overhead rate per unit consists of $6.4 per machine hour and each unit is allowed a standard of...

  • 1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...

    1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...

  • A company's flexible budget for the range of 30,000 units to 36,000 units of production showed...

    A company's flexible budget for the range of 30,000 units to 36,000 units of production showed variable overhead costs of $3.60 per unit and fixed overhead costs of $70,000. The company incurred total overhead costs of $180,100 while operating at a volume of 40,000 units. The total controllable cost variance is Multiple Choice $2,100 unfavorable. $2100 favorable. 33.900 favorable. $6,000 favorable $33.900 unfavorable Hassock Corp. produces woven wall hangings. It takes 4 hours of direct labor to produce a single...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT