The following data is given for the Bahia Company:
Budgeted production | 1,040 units |
Actual production | 906 units |
Materials: | |
Standard price per pound | $1.866 |
Standard pounds per completed unit | 11 |
Actual pounds purchased and used in production | 9,667 |
Actual price paid for materials | $19,817 |
Labor: | |
Standard hourly labor rate | $14.62 per hour |
Standard hours allowed per completed unit | 4.0 |
Actual labor hours worked | 4,665.9 |
Actual total labor costs | $71,155 |
Overhead: | |
Actual and budgeted fixed overhead | $1,181,000 |
Standard variable overhead rate | $26.00 per standard labor hour |
Actual variable overhead costs | $130,645 |
Overhead is applied on standard labor hours. |
The variable factory overhead controllable variance is
a.$152,167.31 unfavorable
b.$152,167.31 favorable
c.$36,421.00 unfavorable
d.$36,421.00 favorable
Variable Factory Overhead Controllable Variance = (Std VOH Cost - Actual VOH Cost)
Actual Variable OH Cost = $130,645
Standard Variable OH Cost = Std hrs*Std rate per hour
= (906 units*4 hrs per unit)*$26 per hour
= 3,624 hrs*$26 per hour = $94,224
Variable Factory OH Controllable Variance = Std Variable OH - Actual Variable OH
= $94,224 - $130,645 = $36,421 Unfavorable
Therefore the variable overhead controllable variance is $36,421 Unfavorable. Hence the correct option is C) $36,421 Unfavorable.
The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production 906...
The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity) 1,077 units Actual production 917 units Materials: Standard price per pound $1.76 Standard pounds per completed unit 12 Actual pounds purchased and used in production 10,674 Actual price paid for materials $21,882 Labor: Standard hourly labor rate $14.01 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,722.55 Actual total labor costs $72,019 Overhead: Actual and budgeted fixed overhead $1,035,000...
The following data are given for Stringer Company: Budgeted production 909 units Actual production 1,036 units Materials: Standard price per ounce $1.82 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,805 Actual price paid for materials $26,250 Labor: Standard hourly labor rate $14.95 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,335.4 Actual total labor costs $81,365 Overhead: Actual and budgeted fixed overhead $1,110,000 Standard variable overhead rate $28.00 per...
The following data are given for Harry Company: Budgeted production 1,054 units Actual production 937 units Materials: Standard price per ounce $1.919 Standard ounces per completed unit 11 Actual ounces purchased and used in production 10,616 Actual price paid for materials $21,763 Labor: Standard hourly labor rate $14.76 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,826 Actual total labor costs $78,423 Overhead: Actual and budgeted fixed overhead $1,025,000 Standard variable overhead rate $24.00 per...
1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity) Actual production Materials: Standard price per pound Standard pounds per completed unit Actual pounds purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs...
22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production 1,002 units Materials: Standard price per ounce $1.75 Standard ounces per completed unit 11 Actual ounces purchased and used in production 11,353 Actual price paid for materials $23,274 Labor: Standard hourly labor rate $14.38 per hour Standard hours allowed per completed unit 5.0 Actual labor hours worked 5,160.3 Actual total labor costs $78,695 Overhead: Actual and budgeted fixed overhead $1,124,000 Standard variable overhead rate...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production 1,021 units Materials: Standard price per ounce $1.81 Standard ounces per completed unit 11 Actual ounces purchased and used in production 11,568 Actual price paid for materials $23,714 Labor: Standard hourly labor rate $14.51 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,258.15 Actual total labor costs $80,187 Overhead:...
The following information is for the standard and actual costs for the Happy Corporation: Enter favorable variances as negative numbers. Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on...
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production: Direct materials 3 pounds @ $0.60 per pound Direct labor 0.5 hr. @ $16.00 per hour VOH 0.5 hr. @ $2.20 FOH: Materials handling $6,200 Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH: Materials handling 6,300 Depreciation $2,600 Required: 1....
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...
A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...