Question

The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906...

The following data is given for the Bahia Company:

Budgeted production 1,040 units
Actual production   906 units
Materials:
    Standard price per pound $1.866
    Standard pounds per completed unit 11
     Actual pounds purchased and used in production 9,667
    Actual price paid for materials $19,817
Labor:
    Standard hourly labor rate $14.62 per hour
    Standard hours allowed per completed unit 4.0
     Actual labor hours worked 4,665.9
    Actual total labor costs $71,155
Overhead:
    Actual and budgeted fixed overhead $1,181,000
    Standard variable overhead rate $26.00 per standard labor hour
     Actual variable overhead costs $130,645
Overhead is applied on standard labor hours.

The variable factory overhead controllable variance is

a.$152,167.31 unfavorable

b.$152,167.31 favorable

c.$36,421.00 unfavorable

d.$36,421.00 favorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Variable Factory Overhead Controllable Variance = (Std VOH Cost - Actual VOH Cost)

Actual Variable OH Cost = $130,645

Standard Variable OH Cost = Std hrs*Std rate per hour

= (906 units*4 hrs per unit)*$26 per hour

= 3,624 hrs*$26 per hour = $94,224

Variable Factory OH Controllable Variance = Std Variable OH - Actual Variable OH

= $94,224 - $130,645 = $36,421 Unfavorable

Therefore the variable overhead controllable variance is $36,421 Unfavorable. Hence the correct option is C) $36,421 Unfavorable.

Add a comment
Know the answer?
Add Answer to:
The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production   906...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity)...

    The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity) 1,077 units Actual production   917 units Materials:     Standard price per pound $1.76     Standard pounds per completed unit 12     Actual pounds purchased and used in production 10,674     Actual price paid for materials $21,882 Labor:     Standard hourly labor rate $14.01 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,722.55     Actual total labor costs $72,019 Overhead:     Actual and budgeted fixed overhead $1,035,000...

  • The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units...

    The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units Materials:     Standard price per ounce $1.82     Standard ounces per completed unit 12     Actual ounces purchased and used in production 12,805     Actual price paid for materials $26,250 Labor:     Standard hourly labor rate $14.95 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,335.4     Actual total labor costs $81,365 Overhead:     Actual and budgeted fixed overhead $1,110,000     Standard variable overhead rate $28.00 per...

  • The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units...

    The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units Materials:     Standard price per ounce $1.919     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,616     Actual price paid for materials $21,763 Labor:     Standard hourly labor rate $14.76 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,826     Actual total labor costs $78,423 Overhead:     Actual and budgeted fixed overhead $1,025,000     Standard variable overhead rate $24.00 per...

  • 1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company:...

    1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company: Budgeted production (at 100% of normal capacity) Actual production Materials: Standard price per pound Standard pounds per completed unit Actual pounds purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs...

  • 22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production...

    22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production   1,002 units Materials:     Standard price per ounce $1.75     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,353     Actual price paid for materials $23,274 Labor:     Standard hourly labor rate $14.38 per hour     Standard hours allowed per completed unit 5.0     Actual labor hours worked 5,160.3     Actual total labor costs $78,695 Overhead:     Actual and budgeted fixed overhead $1,124,000     Standard variable overhead rate...

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production   1,021 units Materials:     Standard price per ounce $1.81     Standard ounces per completed unit 11     Actual ounces purchased and used in production 11,568     Actual price paid for materials $23,714 Labor:     Standard hourly labor rate $14.51 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,258.15     Actual total labor costs $80,187 Overhead:...

  • The following information is for the standard and actual costs for the Happy Corporation: Enter favorable...

    The following information is for the standard and actual costs for the Happy Corporation: Enter favorable variances as negative numbers. Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on...

  • Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...

    Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH:      Materials handling 6,300      Depreciation $2,600 Required: 1....

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...

  • A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual...

    A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT