Answer |
option A is correct. : 53,241 unfavorable |
Working |
Standard fixed overhead rate per unit = $1,092,000 / 1005 = $1086.5671 |
Fixed factory overhead volume variance = fixed overhead applied - Budgeted fixed overhead |
(956 * $1086.5671 - $1,092,000) |
$53,241 unfavorable |
Hence option A is correct. |
Please like |
1,005 units 956 units $1.90 11 10,201 $20,912 The following data are given for Bahia Company:...
The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production 906 units Materials: Standard price per pound $1.866 Standard pounds per completed unit 11 Actual pounds purchased and used in production 9,667 Actual price paid for materials $19,817 Labor: Standard hourly labor rate $14.62 per hour Standard hours allowed per completed unit 4.0 Actual labor hours worked 4,665.9 Actual total labor costs $71,155 Overhead: Actual and budgeted fixed overhead $1,181,000 Standard variable overhead rate $26.00...
The following data is given for the Bahia Company: Budgeted production (at 100% of normal capacity) 1,077 units Actual production 917 units Materials: Standard price per pound $1.76 Standard pounds per completed unit 12 Actual pounds purchased and used in production 10,674 Actual price paid for materials $21,882 Labor: Standard hourly labor rate $14.01 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,722.55 Actual total labor costs $72,019 Overhead: Actual and budgeted fixed overhead $1,035,000...
The following data are given for Harry Company: Budgeted production 1,054 units Actual production 937 units Materials: Standard price per ounce $1.919 Standard ounces per completed unit 11 Actual ounces purchased and used in production 10,616 Actual price paid for materials $21,763 Labor: Standard hourly labor rate $14.76 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,826 Actual total labor costs $78,423 Overhead: Actual and budgeted fixed overhead $1,025,000 Standard variable overhead rate $24.00 per...
The following data are given for Stringer Company: Budgeted production 909 units Actual production 1,036 units Materials: Standard price per ounce $1.82 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,805 Actual price paid for materials $26,250 Labor: Standard hourly labor rate $14.95 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,335.4 Actual total labor costs $81,365 Overhead: Actual and budgeted fixed overhead $1,110,000 Standard variable overhead rate $28.00 per...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 920 units Actual production 1,021 units Materials: Standard price per ounce $1.81 Standard ounces per completed unit 11 Actual ounces purchased and used in production 11,568 Actual price paid for materials $23,714 Labor: Standard hourly labor rate $14.51 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,258.15 Actual total labor costs $80,187 Overhead:...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...
Use this information to answer the question that follow. The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.03 Standard yards per unit: standard, 4.62 yards; actual, 5.06 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$8,128.12 favorable b.$7,927.92 unfavorable c.$7,927.92 favorable d.$8,128.12 unfavorable Myers Corporation has the following data related to direct materials costs for November: actual costs for 4,600 pounds of material, $5.00 and standard costs for...
22. The following data is given for the Stringer Company: Budgeted production 917 units Actual production 1,002 units Materials: Standard price per ounce $1.75 Standard ounces per completed unit 11 Actual ounces purchased and used in production 11,353 Actual price paid for materials $23,274 Labor: Standard hourly labor rate $14.38 per hour Standard hours allowed per completed unit 5.0 Actual labor hours worked 5,160.3 Actual total labor costs $78,695 Overhead: Actual and budgeted fixed overhead $1,124,000 Standard variable overhead rate...
The following information is for the standard and actual costs for the Happy Corporation: Enter favorable variances as negative numbers. Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on...
1)
2)
3)
4)
5)
A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...