Performance Report Based on Budgeted and Actual Levels of Production
Bowling Company budgeted the following amounts:
Variable costs of production: | |
Direct materials | 3 pounds @ $0.60 per pound |
Direct labor | 0.5 hr. @ $16.00 per hour |
VOH | 0.5 hr. @ $2.20 |
FOH: | |
Materials handling | $6,200 |
Depreciation | $2,600 |
At the end of the year, Bowling had the following actual costs for production of 3,800 units:
Direct materials | $6,800 |
Direct labor | 30,500 |
VOH | 4,200 |
FOH: | |
Materials handling | 6,300 |
Depreciation | $2,600 |
Required:
1. Calculate the budgeted amounts for each cost category listed
above for the 4,000 budgeted units.
$
2. Prepare a performance report using a budget based on expected production of 4,000 units. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number and if there is no entries enter "0" then select for "Not applicable".
Bowling Company | ||||
Performance Report | ||||
Actual | Budgeted | Variance | ||
Units produced | Unfavorable | |||
Direct materials | $ | $ | $ | Favorable |
Direct labor | Favorable | |||
Variable overhead | Favorable | |||
Fixed overhead: | ||||
Materials handling | Unfavorable | |||
Depreciation | Not applicable | |||
Total | $ | $ | $ | Favorable |
3. Prepare a performance report using a budget based on the actual level of production of 3,800 units. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number and if there is no entries enter "0" then select for "Not applicable".
Bowling Company | ||||
Performance Report | ||||
Actual | Budgeted | Variance | ||
Units produced | Not applicable | |||
Direct materials | $ | $ | $ | Favorable |
Direct labor | Unfavorable | |||
Variable overhead | Unfavorable | |||
Fixed overhead: | ||||
Materials handling | Unfavorable | |||
Depreciation | Not applicable | |||
Total | $ | $ | $ | Unfavorable |
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...
Performance Report Scafidi Company provided the following information for last year. Master Budget Actual Data Budgeted production 4,400 4,200 units Direct materials: 8 kilograms @ 0.6 per kilogram $6,800 Direct labour: 0.4 hr. @ $15.50 per hour 30,500 VOH: 0.4 hr. @ $2.70 4,200 FOH: Materials handling, $6,600 6,300 Depreciation, $2,700 2,700 Required: 1. Calculate the budgeted amounts for each cost category listed above for the 4,400 budgeted units, then give the total below. Direct materials $ Direct labour $...
Performance Report Based on Actual Production Palladium Inc. produces a variety of household cleaning products. Palladium's controller has developed standard costs for the following four overhead items: Variable Rate per Direct Overhead Item Total Fixed Cost Labor Hour Maintenance $ 86,000 $0.20 Power 0.45 Indirect labor 140,000 2.10 Rent 35,000 Assume that actual production required 93,000 direct labor hours at standard. The actual overhead costs incurred were as follows: Maintenance $107,000 Power 41,200 Indirect labor 336,000 Rent 35,000 Required: Prepare...
Performance Report Based on Actual Production Palladium Inc. produces a variety of household cleaning products. Palladium's controller has developed standard costs for the following four overhead items: Overhead Item Total Fixed Cost Variable Rate per Direct Labor Hour Maintenance $ 86,000 $0.20 Power 0.45 Indirect labor 140,000 2.10 Rent 35,000 Next year, Palladium expects production to require 90,000 direct labor hours. Assume that actual production required 98,000 direct labor hours at standard. The actual overhead costs incurred were as follows:...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...
Goldman Company manufactures shirts. During June, Goldman made 1,500 shirls but had budgeted production at 1,575 shirts. Goldman gathered the following additional dala: :: (Click on the icon to view the data.) Read the requirements i Data Table 13. Calculate the variable overhead cost variance. Select the formula, then enter the amounts and compute the cost variance for variable overhead (VOH) and identify whether the variance is favorable (F) or unfavorable (U) = VOH Cost Variance Variable overhead cost standard...
Goldman Company manufactures shirts. During June, Goldman made 1.500 shirts but had budgeted production at 1,575 shirts. Goldman gathered the following additional data: (Click on the icon to view the data.) Read the requirements. i Data Table 13. Calculate the variable overtiead cost variarice. Select the formula, then enter the amounts and compute the cost variance for variable overhead (VOH) and identify whether the variance is favorable (F) or unfavorable (U) = VOH Cost Variance Actual Cost 14. Actual Quantity...
The following data are given for Stringer Company: Budgeted production 909 units Actual production 1,036 units Materials: Standard price per ounce $1.82 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,805 Actual price paid for materials $26,250 Labor: Standard hourly labor rate $14.95 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,335.4 Actual total labor costs $81,365 Overhead: Actual and budgeted fixed overhead $1,110,000 Standard variable overhead rate $28.00 per...
The following data are given for Harry Company: Budgeted production 1,054 units Actual production 937 units Materials: Standard price per ounce $1.919 Standard ounces per completed unit 11 Actual ounces purchased and used in production 10,616 Actual price paid for materials $21,763 Labor: Standard hourly labor rate $14.76 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,826 Actual total labor costs $78,423 Overhead: Actual and budgeted fixed overhead $1,025,000 Standard variable overhead rate $24.00 per...
Flexible Budget for Various Levels of Production Budgeted amounts for the year: Materials 2 leather strips @ $7.00 Labor 1.5 hr. @ $18.00 VOH 1.5 hr. @ $1.20 $6,800 FOH Required: 1. Prepare a flexible budget for 3,500, 4,000, and 4,500 units. Flexible Budget Variable Cost per Unit 3,500 units 4,000 units 4,500 units Direct materials Direct labor Variable overhead Fixed overhead Total 2. CONCEPTUAL CONNECTION Calculate the unit cost at 3,500, 4,000, and 4,500 units. (Note: Round unit costs...
erformance Report Based on Actual Production Palladium Inc. produces a variety of household cleaning products. Palladium's controller has developed standard costs for the following four overhead items: Overhead Item Total Fixed Cost Variable Rate per Direct Labor Hour Maintenance $ 86,000 $0.20 Power 0.45 Indirect labor 140,000 2.10 Rent 35,000 Next year, Palladium expects production to require 90,000 direct labor hours. Assume that actual production required 106,000 direct labor hours at standard. The actual overhead costs incurred were as follows:...