Question

C&A operates three eight-hour shifts to produce 600 gallons of a chemical per day. It requires...

C&A operates three eight-hour shifts to produce 600 gallons of a chemical per day. It requires 12 minutes of labor to produce a gallon of the chemical. What is C&A’s takt time in minutes per gallon and target manpower?

0.3, 40

0.8, 15

0.04, 5

2.4, 5

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

3 eight hour shifts produce 600 gallons. So, 1 eight hour shift will produce 600\div3 = 200 gallons.

So, as 8 hrs produce 200 gallons, 1 hour or 60 mins produce 200\div8 = 25 gallons.

12 minutes of labour is required to produce 1 gallon, so in 1 hour 1 labour can produce 60\div12 = 5 gallons of chemical.

So, to produce 25 gallons, we need 25\div5 = 5 labours.

Again as we already know in 1 hour we can produce 25 gallons, the time taken for producing 1 gallon overall (not per labour) is 60\div25= 2.4. This is the takt time (time taken per unit of material).

So, the answer is option d i.e. 2.4,5

Add a comment
Know the answer?
Add Answer to:
C&A operates three eight-hour shifts to produce 600 gallons of a chemical per day. It requires...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT