The welding department supplies parts to the final assembly line. Management decides to implement a kanban...

The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data.
  • The daily demand is 2000 units
  • The production lead time is 4 days (this includes processing time, transport time, and waiting time)
  • Management has decide to have a 1 day safety stock
  •  One container fits 400 units
 
How many kanban containers will be needed to support this system?
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Compute the number of kanban containers in the system as below,

Number of \(\mathrm{K}\) anban \(=\frac{\mathrm{L}_{\mathrm{d}}+\mathrm{SS}}{\mathrm{n}}\)

Here.

Lead time demand, \(L_{\mathrm{d}}=4\) days \(\times 2000\) units per day \(=8,000\) units Container size, \(\mathrm{n}=400\) units Safety stock, \(\mathrm{SS}=1\) day \(\times 2,000\) units per day \(=2,000\) units

$$ \begin{aligned} \text { Number of Kanban } &=\frac{\mathrm{L}_{\mathrm{d}}+\mathrm{SS}}{\mathrm{n}} \\ &=\frac{8000+2000}{400} \\ &=25 \text { containers } \end{aligned} $$

Add a comment
Know the answer?
Add Answer to:
The welding department supplies parts to the final assembly line. Management decides to implement a kanban...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT