Takt time = Available time / Rate of Customer demand
Available time = 5 days per week * 8 hours per day
= 40 hours
Demand for A = 80 units
Demand for B = 100 units
Total demand = 180 units
Takt time = 40 / 180 = 0.22 hours/unit
A process makes two products. A and B. and operates 5 days per week. 8 hours...