The mean for the above set of data points is,
The standard deviation for the above set of data points is,
The upper control limits (UCL) and lower control limits (LCL) for a 100(1-) % control are given by,
For the given problem, and
Therefore, the control limits are UCL=4.226 and LCL = 1.487.
The following plot depicts the control chart for this:
The numbers 0 to 6 on the x-axis correspond to the days Sunday, Monday, and so on till Saturday. Clearly, the chart was not in control on Monday and Saturday since the errors fell below the LCL. Also, the chart was also not in control on Tuesday and Thursday since the errors were higher than UCL.
A recent Living at Southeast post suggested that the vending machines on campus are error-prone (i.e.,...
Risk management in Information Security today Everyday information security professionals are bombarded with marketing messages around risk and threat management, fostering an environment in which objectives seem clear: manage risk, manage threat, stop attacks, identify attackers. These objectives aren't wrong, but they are fundamentally misleading.In this session we'll examine the state of the information security industry in order to understand how the current climate fails to address the true needs of the business. We'll use those lessons as a foundation...