TOTAL NO PRODUCTION REUN 10+190= 200
TOTAL SETUP COST $250000
SETUPCOST PER PRODUCTION RUN $250000/200 =1250
B) MACHINE COST PER MACHINE HOUR
TOTAL MACHINE HOUR 15000+85000=100000
MCHINE COST $1250000
MACHONE COST PER HOUR 1250000/100000 = 12.5
C) RECEIVING COST PER RECEIVING ORDER
TOTAL ORDER 450+40 = 490
RECEIVING COST $2000000
PER ORDER RATE 2000000/490= 4081.63
D) ENGINEERING COST PER HOUR
TOTAL ENGINEERING HOUR 90000+10000=100000
TOTAL ENGINEERING COST $1000000
PER HOUR RATE 1000000/100000= 10
E) MATERIAL HANDLING COST PER MOVE
TOTAL MOVE 60+40=100
TOTAL HANDLING COST $500000
PER MOVE RATE 500000/100= 5000
OVERHEAD COST AS PER ABC METHOD | ||||||
TINY BOBBLEHEADS | HUGE BOBBLEHEADS | |||||
COST ITEM | COST RATE | NO/HOUR OF ACTIVITY | COST | COST RATE | NO/HOUR OF ACTIVITY | COST |
SETUP COST | 1250 | 190 | 237500 | 1250 | 10 | 12500 |
MACHINE COSTS | 12.5 | 85000 | 1062500 | 12.5 | 15000 | 187500 |
RECEVING COST | 4081.63 | 450 | 1836734 | 4081.63 | 40 | 163266 |
ENGINEERING | 10 | 90000 | 900000 | 10 | 10000 | 100000 |
MATERIAL HANDLING COST | 5000 | 60 | 300000 | 5000 | 40 | 200000 |
4,336,734.00 | 663,266.00 | |||||
PRODUCT COST ABC SYSTEM | TINY BOBBLEHEADS | HUGE BOBBLEHEADS | ||||
MATERIAL COST | 900000*3 | 2700000 | +100000*100 | 10000000 | ||
LABOUR COST | 5*900000 | 4500000 | 100000*150 | 15000000 | ||
OTHER OVERHEAD | 4,336,734.00 | 663,266.00 | ||||
TOTAL COST | 11,536,734.00 | 25,663,266.00 | ||||
CONRTRUBUTION | ||||||
SALES | 900000*50 | 45000000 | 100000*500 | 50000000 | ||
TOTAL COST | 11,536,734.00 | 25,663,266.00 | ||||
CONTRIBUTION TOTAL | 33,463,266.00 | 24,336,734.00 | ||||
CONTRIBUTION PER UNIT | 37.18 | 243.37 | ||||
Name Section Alphabetical Number Week #5- Chapter 4 Homework Assignment Problem 1 (Supplemental Problem #1 )-Tradition...
CMA5-5 Chapter 5 Activity-Based Costing are given below Product AProductB CMAS-S. Atmel Inc. manufactures and sells two products. Data with regard to these products are given be 30,000 12,000 Units produced and sold Machine hours required per unit.. Receiving orders per product line . Production orders per product line......... Production runs 2 50 12 8 20 150 18 12 30 Total budgeted machine hours are 100,000. The budgeted overhead costs are shown below .. $ 450,00 Receiving costs Engineering costs....
Pro blem 2 (Supplemental Problem #2)-Activity-based costing versus traditional costing sunglasses. The company uses a normal cos based on direct labor hours Lovelace Company produces only two products: reading glasses and sung system and overhead costs are currently allocated using a plant-wide overhead rate products. Itants have recommended that the company use activity-based costing to charge overhead to he company expects to produce 4,000 reading glasses and 8,000 sunglasses this year. Each pair of reading glasses requires two direct labor...
Please show your work Use the following information to answer Questions #5 and #6 12 30 Product A Units produced and sold Product B 30,000 Machine hours required per unit 12.000 23 Receiving orders per product line 50 150 Production orders per product line 12 18 Production runs 8 Inspections 20 Total budgeted machine hours are 100,000. The budgeted overhead costs are as shown below. 96.000 Machine hat Receiving costs $450,000 used Engineering costs 300,000 Machine setup costs 25,000 Inspection...
4: Homework Question 8 of 13 0.75/1 Perdon Corporation manufactures safes-large mobile safes, and large walk-in stationary bank safes. As part of its annual budgeting process, Perdon is analyzing the profitability of its two products. Part of this analysis involves estimating the amount of overhead to be allocated to each product line. The information shown below relates to overhead. Units planned for production Material moves per product line Purchase orders per product line Direct labor hours per product line Mobile...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 ------ Prime costs $9,800,000 $44,520,000 $54,320,000 Machine hours 140,000 700,000 840,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours ...
ACCT 210 Chapter 5 Supplemental in Class Assignment Numbers Text Model A Product Data Model B 100,000 110,000 10,000 Units produced per year Direct Labor hours Production Set-ups Inspection hours Machine hours Maintenance hours 50,000 40 800 20,000 10,000 350,000 60 1,200 180,000 90,000 400,000 100 2,000 200,000 100,000 Total Activity Rate Overhead costs: Set-up Costs Inspection costs Machining Costs Maintenance Costs 300,000 250,000 240,000 210,000 1,000,000 Activity Driver Pr00015 Inspection hours Machine hog Maintenance hours nu 1. Compute the...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 Prime costs $12,600,000 $45,000,000 $57,600,000 900,000 Machine hours 150,000 750,000 500 4,500 5,000 Engineering hours Receiving orders Inspection hours 200 600 800 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 2,100,000 320,000 Receiving Inspecting products 480,000 Required: 1. Calculate...
Activity Based Costing 1 Chapter 3: Applying Excel Fra formulato each of the cols marked when Review Problem. Activity Based Couting 6 Data Annual sales in units 9 Direct materials per unit 10 Direct labor hours per unit 2000 Tourist 10 000 $25 517 12 Direct labor rate 512 per DUH Overhead Expected Activity 16 Activities and Activity Measures 17 Labor-related (direct labor hours) 19 Machine setups (setups) 19 Production orders (orders) 20 General factory (machine hours) $ 80.000 150.000...
Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wide basis to its two products (The Wall and The Wig) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Cost Driver Estimated Overhead Expected Activity Material handling Number of moves $250,000 50,000 Purchase orders Number...
Problem 2 (Supplemental Problem #2) – Activity-based costing versus traditional costing Lovelace Company produces only two products: reading glasses and sunglasses. The company uses a normal cost system and overhead costs are currently allocated using a plant-wide overhead rate based on direct labor hours. Outside cost consultants have recommended that the company use activity-based costing to charge overhead to products. The company expects to produce 4,000 reading glasses and 8,000 sunglasses this year. Each pair of reading glasses requires two...