Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wide basis to its two products (The Wall and The Wig) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows:
Activity | Cost Driver | Estimated Overhead | Expected Activity |
Material handling | Number of moves | $250,000 | 50,000 |
Purchase orders | Number of orders | $200,000 | 4,000 |
Product testing | Number of tests | $450,000 | 10,000 |
Machine set-up | Number of set-ups | $600,000 | 6,000 |
Machining | Machine hrs | $1500,000 | 100,000 hrs |
Wall | Wig | |
Direct materials costs | $125 | $220 |
Direct labour costs | $110 | $150 |
Purchase orders | 2 | 3 |
Machine set-up | 5 | 10 |
Product testing | 3 | 4 |
Machining | 50 | 50 |
Materials handing | 5 | 10 |
a. Under traditional product costing using machine hours, calculate the total manufacturing cost per unit of both products.
b.Under ABC, prepare a schedule showing the calculation of the activity-based overhead rates (per cost driver).
c. Calculate the total manufacturing cost per unit for both products under ABC.
(That's the whole question and no further information.)
TRADITIONAL COSTING SYSTEM | ||||||
ALLOCATED OVERHEAD RATE = (TOTAL OVERHEAD/ TOTAL MACHINE HOUR) | ||||||
($3000000/100000) =$30/ HOUR | ||||||
WALL | WIG | |||||
DIRECT MATERIAL COST | $ 125.00 | $ 220.00 | ||||
DIRECT LABOR COST | $ 110.00 | $ 150.00 | ||||
OVERHEAD COST | $ 1,500.00 | $ 1,500.00 | ||||
(MACHINE HOUR X OVERHEAD RATE) | (50 X $30) | (50 X $30) | ||||
TOTAL COST PER UNIT | $ 1,735.00 | $ 1,870.00 | ||||
ABC RATE CALCULATION | ||||||
COST ITEM | COST | TOTAL COST DRIVER | ABC RATE | |||
MATERIAL HANDLING | $ 250,000.00 | 50,000.00 | $ 5.00 | PER MOVES | ||
PURCHASE ORDER | $ 200,000.00 | 4,000.00 | $ 50.00 | PER ORDER | ||
PRODUCT TESTING | $ 450,000.00 | 10,000.00 | $ 45.00 | PER TEST | ||
MACHINE SET-UP | $ 600,000.00 | 6,000.00 | $ 100.00 | PER SETUP | ||
MACHINING | $ 1,500,000.00 | 100,000.00 | $ 15.00 | PER MACHINE HOUR | ||
OVERHEAD COST AS PER ABC METHOD | ||||||
WALL | WIG | |||||
COST ITEM | COST RATE | NO/HOUR OF ACTIVITY | COST | COST RATE | NO/HOUR OF ACTIVITY | COST |
MATERIAL HANDLING COST | $ 5.00 | 5 | $ 25.00 | $ 5.00 | 10 | $ 50.00 |
PURCHASE ORDER | $ 50.00 | 2 | $ 100.00 | $ 50.00 | 3 | $ 150.00 |
PRODUCT TESTING | $ 45.00 | 3 | $ 135.00 | $ 45.00 | 4 | $ 180.00 |
MACHINE SET UP | $ 100.00 | 5 | $ 500.00 | $ 100.00 | 10 | $ 1,000.00 |
MACHINING | $ 15.00 | 50 | $ 750.00 | $ 15.00 | 50 | $ 750.00 |
$ 1,510.00 | $ 2,130.00 | |||||
PRODUCT COST ABC SYSTEM | WALL | WIG | ||||
MATERIAL COST | $ 125.00 | $ 220.00 | ||||
LABOUR COST | $ 110.00 | $ 150.00 | ||||
OTHER OVERHEAD | $ 1,510.00 | $ 2,130.00 | ||||
TOTAL COST PER UNIT | $ 1,745.00 | $ 2,500.00 | ||||
Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wid...
Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...
Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...
International Steel Company has budgeted manufacturing overhead costs of $1,971,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Material handling Purchase orders Product testing Machine set-up Machining Cost Driver Estimated Activity Number of...
Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,925,000. It has allocated overhead on alatide to the products and hand are estimated to be 100.000 for the current year. The company has decided to experiment with activity-based costing and has created the city cost pools and related t o Activity Centre made heurs, which drives as Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining Number of moves Number of orders Number of...
EcoFabrics has budgeted overhead costs of $1,115,100. It has
allocated overhead on a plantwide basis to its two products (wool
and cotton) using direct labor hours which are estimated to be
531,000 for the current year. The company has decided to experiment
with activity-based costing and has created two activity cost pools
and related activity cost drivers. These two cost pools are cutting
(cost driver is machine hours) and design (cost driver is number of
setups). Overhead allocated to the...
EcoFabrics has budgeted overhead costs of $1,152,900. It has
allocated overhead on a plantwide basis to its two products (wool
and cotton) using direct labor hours which are estimated to be
549,000 for the current year. The company has decided to experiment
with activity-based costing and has created two activity cost pools
and related activity cost drivers. These two cost pools are cutting
(cost driver is machine hours) and design (cost driver is number of
setups). Overhead allocated to the...
EcoFabrics has budgeted overhead costs of $1,039,500. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 495,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...
EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 517,500 for the current year. The company ha decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups) Overhead alocated to the...
EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 517,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...
Oriole has budgeted overhead costs of $1,067,850. It has
allocated overhead on a plantwide basis to its two products (wool
and cotton) using direct labor hours which are estimated to be
508,500 for the current year. The company has decided to experiment
with activity-based costing and has created two activity cost pools
and related activity cost drivers. These two cost pools are cutting
(cost driver is machine hours) and design (cost driver is number of
setups). Overhead allocated to the...