Question

Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wid...

Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wide basis to its two products (The Wall and The Wig) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows:

Activity Cost Driver Estimated Overhead Expected Activity
Material handling Number of moves $250,000 50,000
Purchase orders Number of orders $200,000 4,000
Product testing Number of tests $450,000 10,000
Machine set-up Number of set-ups $600,000 6,000
Machining Machine hrs $1500,000 100,000 hrs
Wall Wig
Direct materials costs $125 $220
Direct labour costs $110 $150
Purchase orders 2 3
Machine set-up 5 10
Product testing 3 4
Machining 50 50
Materials handing 5 10

a. Under traditional product costing using machine hours, calculate the total manufacturing cost per unit of both products.

b.Under ABC, prepare a schedule showing the calculation of the activity-based overhead rates (per cost driver).

c. Calculate the total manufacturing cost per unit for both products under ABC.

(That's the whole question and no further information.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
TRADITIONAL COSTING SYSTEM
ALLOCATED OVERHEAD RATE = (TOTAL OVERHEAD/ TOTAL MACHINE HOUR)
($3000000/100000) =$30/ HOUR
WALL WIG
DIRECT MATERIAL COST $                               125.00 $              220.00
DIRECT LABOR COST $                               110.00 $              150.00
OVERHEAD COST $                            1,500.00 $           1,500.00
(MACHINE HOUR X OVERHEAD RATE) (50 X $30) (50 X $30)
TOTAL COST PER UNIT $                            1,735.00 $           1,870.00
ABC RATE CALCULATION
COST ITEM COST TOTAL COST DRIVER ABC RATE
MATERIAL HANDLING $     250,000.00                              50,000.00 $                   5.00 PER MOVES
PURCHASE ORDER $     200,000.00                                4,000.00 $                50.00 PER ORDER
PRODUCT TESTING $     450,000.00                              10,000.00 $                45.00 PER TEST
MACHINE SET-UP $     600,000.00                                6,000.00 $              100.00 PER SETUP
MACHINING $ 1,500,000.00                           100,000.00 $                15.00 PER MACHINE HOUR
OVERHEAD COST AS PER ABC METHOD
WALL WIG
COST ITEM COST RATE NO/HOUR OF ACTIVITY COST COST RATE NO/HOUR OF ACTIVITY COST
MATERIAL HANDLING COST $                  5.00 5 $                25.00 $                            5.00 10 $                   50.00
PURCHASE ORDER $                50.00 2 $              100.00 $                         50.00 3 $                 150.00
PRODUCT TESTING $                45.00 3 $              135.00 $                         45.00 4 $                 180.00
MACHINE SET UP $             100.00 5 $              500.00 $                       100.00 10 $             1,000.00
MACHINING $                15.00 50 $              750.00 $                         15.00 50 $                 750.00
$         1,510.00 $           2,130.00
PRODUCT COST ABC SYSTEM WALL WIG
MATERIAL COST $                               125.00 $                 220.00
LABOUR COST $                               110.00 $                 150.00
OTHER OVERHEAD $                            1,510.00 $             2,130.00
TOTAL COST PER UNIT $                          1,745.00 $           2,500.00
Add a comment
Know the answer?
Add Answer to:
Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wid...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead...

    Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...

  • Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead...

    Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...

  • International Steel Company has budgeted manufacturing overhead costs of $1,971,000. It has allocated overhead on a...

    International Steel Company has budgeted manufacturing overhead costs of $1,971,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Material handling Purchase orders Product testing Machine set-up Machining Cost Driver Estimated Activity Number of...

  • Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,925,000. It has allocated overhead...

    Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,925,000. It has allocated overhead on alatide to the products and hand are estimated to be 100.000 for the current year. The company has decided to experiment with activity-based costing and has created the city cost pools and related t o Activity Centre made heurs, which drives as Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining Number of moves Number of orders Number of...

  • EcoFabrics has budgeted overhead costs of $1,115,100. It has allocated overhead on a plantwide basis to...

    EcoFabrics has budgeted overhead costs of $1,115,100. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 531,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...

  • EcoFabrics has budgeted overhead costs of $1,152,900. It has allocated overhead on a plantwide basis to...

    EcoFabrics has budgeted overhead costs of $1,152,900. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 549,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...

  • EcoFabrics has budgeted overhead costs of $1,039,500. It has allocated overhead on a plantwide basis to...

    EcoFabrics has budgeted overhead costs of $1,039,500. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 495,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...

  • EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to...

    EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 517,500 for the current year. The company ha decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups) Overhead alocated to the...

  • EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to...

    EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 517,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...

  • Oriole has budgeted overhead costs of $1,067,850. It has allocated overhead on a plantwide basis to...

    Oriole has budgeted overhead costs of $1,067,850. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 508,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT