Answer:
Total Budgeted Overhead = $1,925,000
Total Labour Hours = 100000 hours
Predetermined Overhead rate = Total Overhead/Labour Hours
Predetermined Overhead rate = 1,925,000 100000
Predetermined Overhead rate = $19.25
Particulars | Soft Steel | Hard Steel |
Direct Materaial Cost | $300 | $200 |
Direct Labor Cost | 120 | 60 |
Overhead: | ||
($19.25 60); ($19.25 60) | 1150 | 1150 |
Total manufacturing Cost per Unit | $1,570 | $1,410 |
Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,925,000. It has allocated overhead...
Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...
International Steel Company has budgeted manufacturing overhead costs of $1,971,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Material handling Purchase orders Product testing Machine set-up Machining Cost Driver Estimated Activity Number of...
Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...
Donald Trump’s Company has budgeted manufacturing overhead costs of $3,000,000. It has allocated overhead on a plant-wide basis to its two products (The Wall and The Wig) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Cost Driver Estimated Overhead Expected Activity Material handling Number of moves $250,000 50,000 Purchase orders Number...
EcoFabrics has budgeted overhead costs of $1,115,100. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 531,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...
EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 517,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...
Oriole has budgeted overhead costs of $1,067,850. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 508,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...
EcoFabrics has budgeted overhead costs of $1,086,750. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 517,500 for the current year. The company ha decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups) Overhead alocated to the...
using EcoFabrics has budgeted overhead costs of $1,181,250, It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 562,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cuttino (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to...
Exercise 17-03 al-a2, bl-b2 EcoFabrics has budgeted overhead costs of $973,350. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct la bor hours which are estimated to be 463,500 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of...