Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly...

Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.

Based on the required safety stock of zero and the number of containers computed in Question 33, what would be the new required round-trip time, all else being constant?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

CHuen, 200 P er hr 10 CC) Containor Size Ce 2 leadl time CL) hr (25P 200 X5 -> Lead time clemand 0 2 (ss) 201 Stock 2 Lead ti

Add a comment
Know the answer?
Add Answer to:
Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area,...

    Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area, the demand is 100 parts per eight-hour day. It uses a container that holds eight parts. It typically takes about six hours to round-trip a container from one work center to the next and back again. It also desires to hold 15% safety stock of this part in the system. If it reduced the number of containers by one, how would this impact the...

  • A manufacturing assembly line has a demand for specific part of 1,200 parts per eight-hour day....

    A manufacturing assembly line has a demand for specific part of 1,200 parts per eight-hour day. It wants to design a lean system using containers. It takes about four hours to round-trip a container from one work center to the next and back again. It also wants to hold 10% safety stock of this part in its system. a) Design a container system. State each container's size and how many are needed. b) Calculate the maximum system inventory for this...

  • Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day,...

    Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day, they use 1,500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the subassembly line that is currently rated at a 15% safety factor. If the required safety stock was changed to zero and 3 containers were being used in the system, calculate the maximum inventory....

  • The welding department supplies parts to the final assembly line. Management decides to implement a kanban...

    The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data. The daily demand is 2,600 units. The production lead time is 6 days (this includes processing time, transport time, and waiting time). Management has decided to have 2 day(s) of safety stock One container fits 350 units How many kanban containers will be needed to support this system? (Round up to next whole number). containers

  • Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of...

    Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed Setup cost Annual holding cost $400 per mainshaft $20 320 mainshafts/day Daily production Annual usage 20,000 (50 weeks x5 days each x daily usage of 80 mainshafts) 3 days Lead time 1.00 days' production Safety stock Kanban container size = 52 mainshafts (round your response to the nearest whole number) Number of...

  • Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of...

    Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost $200 per mainshaft Daily production 360 mainshafts/day Annual usage 25,000 (50 weeks x 5 days each x daily usage of 100 mainshafts) Lead time 3 days Safety stock 1.00 days' production Kanban container size = mainshafts (round your response to the nearest whole number).

  • Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of...

    Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost $220 per mainshaft Daily production 320 mainshafts/day Annual usage 20,000 (50 weeks 5 days each x daily usage of 80 mainshafts) Lead time 4 days Safety stock 0.50 days' production Kanban container size = 60mainshafts (round your response to the nearest whole number). Number of kanbans...

  • A. Issues [1] In addition to damages for one year's notice period, can a trial judge...

    A. Issues [1] In addition to damages for one year's notice period, can a trial judge award significant damages for the mere fact of an employee's dismissal, or for the stigma that that dismissal brings? Or for the employer thereafter competing with the ex-employee for the clients, before the ex-employee has got a new job? B. Basic Facts [2] This is an appeal from 2009 ABQB 591 (CanLII), 473 A.R. 254. [3] Usually a judgment recites facts before law. But...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT