Question

44) Find the project is $45,00o. Initial cost of the peoject is $76.000 B087 C177 D)159 45) When you by ldentiftyoa plot t t
0 0
Add a comment Improve this question Transcribed image text
Answer #1

44). PI = 1 + (NPV/Initial Investment) = 1 + (45,000/76,000) = 1 + 0.59 = 1.59

Hence, Option "D" is correct.

45). As IRR is the rate at which NPV is zero. Hence the statement is True.

46). NPV. When facing such a situation, the project with a higher NPV should be chosen because there is an inherent reinvestment assumption.

47). Option Ä is correct.

As the sign change happens twice. Hence, there will be two IRRs.

48). \betaP = \sum_{i=1}^{n} [Wi x \betai]

= [(2/10) x 1.5] + [(7/10) x 0.4] + [(1/10) x (-0.5)] = 0.3 + 0.28 - 0.05 = 0.53

Hence, Option "D" is correct.

Add a comment
Know the answer?
Add Answer to:
44) Find the project is $45,00o. Initial cost of the peoject is $76.000 B087 C177 D)159...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • HW help please with explanations Which project will you choose? Use the information to answer the...

    HW help please with explanations Which project will you choose? Use the information to answer the following questions. A company is analyzing two mutually exclusive projects, S and L, whose cash flows are shown below: Year o Year 1 Year 2 Year 3 Year 4 Cashflow for S -100 40 50 30 30 Cashflow for L -100 10 10 50 90 Assume the company can get an unlimited amount of capital at that cost. WACC NPV (S) NPV (L) 5%...

  • eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected...

    eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years, Mutually exclusive Project L requires an initial outlay at t = 0 of $48,000, and its expected cash flows would be $9,550 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer a. Project L, since the NPV > NPV- b. Both...

  • You are considering undertaking a project that has beta of 1.2, an initial cost of $100...

    You are considering undertaking a project that has beta of 1.2, an initial cost of $100 million and annual after-tax inflows of $10 million for 20 years starting at the beginning of next year. The risk-free rate is 2% and the market is expected to yield 5% over the next year. a) Assuming that the CAPM holds, what is the appropriate discount rate for this project? b) What is the NPV of the project? c) What is the IRR of...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...

  • Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,500, and its expected cash flows would be $13,100 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVs > NPVĻ. b. Project L,...

  • Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85.000 and expected free cash flows of ​$20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT