Question

Kumar, Inc., evaluates managers of producing departments on their ability to control costs. In addition to the costs directly traceable to their departments, each production manager is held responsible for a share of the costs of a support center, the Human Resources (HR) Department. The total costs of HR are allocated on the basis of actual direct labor hours used. The total costs of HR and the actual direct labor hours worked by each producing department are as follows:


Year 1Year 2
Direct labor hours worked:

    Department A24,00025,000
    Department B38,00025,000
Total hours62,00050,000
Actual HR cost$117,400$117,400
Budgeted HR cost112,400*110,000*

*$0.20 per direct labor hour plus $100,000.

When the capacity of the HR Department was originally established, the normal usage expected for each department was 15,000 direct labor hours. This usage is also the amount of activity planned for the two departments in Year 1 and Year 2.

Required:

1. Allocate the costs of the HR Department using the direct method and assuming that the purpose is product costing.


Department ADepartment B
Variable costs$$
Fixed costs
Total cost$$

2. Allocate the costs of the HR Department using the direct method and assuming that the purpose is to evaluate performance.


Year 1
Year 2

Department ADepartment B
Department ADepartment B
Variable costs$$
$$
Fixed costs
Total cost$$
$$

Please I need an answer ASAP!!

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Kumar INC, evaluates managers of producing departments on their ability to control costs.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Kumar, Inc., evaluates managers of producing departments on their ability to control costs. In addition to...

    Kumar, Inc., evaluates managers of producing departments on their ability to control costs. In addition to the costs directly traceable to their departments, each production manager is held responsible for a share of the costs of a support center, the Human Resources (HR) Department. The total costs of HR are allocated on the basis of actual direct labor hours used. The total costs of HR and the actual direct labor hours worked by each producing department are as follows: Year...

  • Actual versus Budgeted Costs Kumar, Inc., evaluates managers of producing departments on their ability to control...

    Actual versus Budgeted Costs Kumar, Inc., evaluates managers of producing departments on their ability to control costs. In addition to the costs directly traceable to their departments, each production manager is held responsible for a share of the costs of a support center, the Human Resources (HR) Department. The total costs of HR are allocated on the basis of actual direct labor hours used. The total costs of HR and the actual direct labor hours worked by each producing department...

  • 17. Albemarle, Inc., has two producing departments (X and Y). Each producing department is held responsible for a share...

    17. Albemarle, Inc., has two producing departments (X and Y). Each producing department is held responsible for a share of the costs of a support department. Actual and budgeted data are as follows: 2018 Actual Support department hours used: Department 8,000 Department Y Total hours 16,000 24,000 Support department costs: Actual support department costs Budgeted fixed support dept. costs $72,000 $24,000 Budgeted variable rate per hour $ 3.00 Normal, budgeted support department usage is 12,000 hours each for Department X...

  • 2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery...

    2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery and Assembly). Additional information is given below: Kilowatt Maintenance Cost Hours Hours Machinery 450,000 39,000 1,600 Assembly 210.000 15,000 2,400 Power 135,000 5,500 1,000 Maintenance 90,000 6,000 600 Costs of Power department are allocated on the basis of Kilowatt Hours. The Costs of Maintenance department are allocated on the basis of Maintenance Hours. Total machine hours worked in Machinery Department is 2,500 and total...

  • 2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery...

    2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery and Assembly). Additional information is given below: Kilowatt Maintenance Cost Hours Hours Machinery 450,000 39,000 1,600 Assembly 210.000 15,000 2,400 Power 135,000 5,500 1,000 Maintenance 90,000 6,000 600 Costs of Power department are allocated on the basis of Kilowatt Hours. The Costs of Maintenance department are allocated on the basis of Maintenance Hours. Total machine hours worked in Machinery Department is 2,500 and total...

  • Venetian Company has two production departments, Fabricating and Assembling. At a department managers’ meeting, the controller...

    Venetian Company has two production departments, Fabricating and Assembling. At a department managers’ meeting, the controller uses flexible budget graphs to explain total budgeted costs. Separate graphs based on direct labor hours are used for each department. The graphs show the following. 1. At zero direct labor hours, the total budgeted cost line and the fixed cost line intersect the vertical axis at $49,000 in the Fabricating Department and $41,000 in the Assembling Department. 2. At normal capacity of 47,800...

  • Venetian Company has two production departments, Fabricating and Assembling. At a department managers’ meeting, the controller...

    Venetian Company has two production departments, Fabricating and Assembling. At a department managers’ meeting, the controller uses flexible budget graphs to explain total budgeted costs. Separate graphs based on direct labor hours are used for each department. The graphs show the following. 1. At zero direct labor hours, the total budgeted cost line and the fixed cost line intersect the vertical axis at $51,000 in the Fabricating Department and $43,000 in the Assembling Department. 2. At normal capacity of 45,900...

  • Sequential Method Eilers Company has two producing departments and two support departments. The following budgeted data...

    Sequential Method Eilers Company has two producing departments and two support departments. The following budgeted data pertain to these four departments: Support Departments Producing Departments General Factory Receiving Assembly Finishing Direct overhead $400,000 $160,000 $43,000 $74,000 Square footage — 2,700 5,400 5,400 Number of receiving orders 300 — 1,680 1,020 Direct labor hours — — 25,000 40,000 The support departments are ranked in order of highest cost to lowest cost. Required: 1. Allocate the costs of the support departments using...

  • Exercise 23-12 a-b Venetian Company has two production departments, Fabricating and Assembling. At a department managers'...

    Exercise 23-12 a-b Venetian Company has two production departments, Fabricating and Assembling. At a department managers' meeting, the controller uses flexible budget graphs to explain total budgeted costs. Separate graphs based on direct labor hours are used for each department. The graphs show the following. 1. At zero direct labor hours, the total budgeted cost line and the fixed cost line intersect the vertical axis at $50,000 in the Fabricating Department and 543,000 in the Assembling Department. 2. At normal...

  • The Wallaby Company has two support departments and two producing departments. Information for each department for...

    The Wallaby Company has two support departments and two producing departments. Information for each department for the year is as follows:                                          Support Departments         Producing    Departments                                                 Administration  Maintenance    Molding     Assembly       Budgeted overhead         $80,000       $120,000              $460,000     $540,000       Direct labor hours                 500          2,000                      25,000       32,000       Square meter occupied         200            300                        2,500      10,000       Machine hours                        —              500                          9,600     14,400 The company does not divide costs into fixed and variable components. Plant administration costs are allocated based on square meter occupied, and factory maintenance costs are allocated based on machine hours. Predetermined overhead rates for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT