Using precedence diagramming method, activity B must not start until activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. What is the correct description of the type of the relationship that exists between activites A and B
This relationship is an example of the rare but occasionally necessary Start-Finish relationship, SF-3d. |
||
This relationship is a standard Finish-Start relationship, FS, but the successor of B will have a 3 day lead. |
||
This relationship is a Finish-Start relationship, FS + 3d. |
||
This relationship mandates a dummy activity with a three-day duration following A. |
c)This relationship is a Finish-Start relationship, FS + 3d.
FS + 3d or FS + 3ed
Response: Refer to section 8.4, precedence diagramming. The amount
of lag could be indicated as +3d to reference work periods or as
+3ed to reference calendar time that includes both work periods and
nonwork period
if you think this helped do give a thumbs up else share your queries in the comment section.
Using precedence diagramming method, activity B must not start until activity A has been completed. Moreover,...
post the answers for the following Mcq's. NOTE: FYI - 17th question has 4 option in the pic option A and B is there. option C ) Environmental D ) Mandatory. 2. If you are compressing the project schedule by using a technique that generally does not increase project costs, which of the following techniques are you using? A. Fast tracking B. Crashing C. Resource optimization D. Resource leveling 3. The amount of time a successor activity must wait after...