Question
post the answers for the following Mcq's.

NOTE: FYI - 17th question has 4 option in the pic option A and B is there. option C ) Environmental D ) Mandatory.
2. If you are compressing the project schedule by using a technique that generally does not increase project costs, which of
0 0
Add a comment Improve this question Transcribed image text
Answer #1

2) C

It is the resource optimization scenario so as to compress the schedule

3) D

It is also called as Slack

14) A

The milestone list is the part of project schedule and not included in activity list

15) D

Finish to Start is the common relationship as it is used in case of dependencies

Add a comment
Know the answer?
Add Answer to:
post the answers for the following Mcq's. NOTE: FYI - 17th question has 4 option in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • Case-2 Consider that you have an interview in a construction firm and they asked you to...

    Case-2 Consider that you have an interview in a construction firm and they asked you to develop an (AOA) network for a construction project has the following activities along with their relationships. Draw your suggested network. (15 Marks) (The project was started in activity A and it is the precedence of activities B,C,D &E, the activity B is followed by activity F, while the activity C was followed by activity G, the activity K was not start until the activities...

  • 26.According to the DISC acronym, _____ relates to control, power, and assertiveness. independence steadiness influence dominance...

    26.According to the DISC acronym, _____ relates to control, power, and assertiveness. independence steadiness influence dominance competence 28.Which of the following is an example of asynchronous communications? Texting Mail and package delivery Instant messaging Computer-assisted conference Audio conference 33.Which of the following is an example of synchronous communications? Web log Fax Computer-assisted conference Mail and package delivery Electronic mail 36.A table reflecting Communication Escalation will contain information about all of the following EXCEPT: Priority Definitions Decision Authority Timeframe for Notification...

  • QUESTION 1 Your company is planning to implement a construction project in a nearby town. You...

    QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activities and their relationship to be carried out in order to complete the project. Table 1 and Figure 1 below show the relationship and the critical path diagram for the project. The duration to complete each activity (days) is stated below the activity. The relationship between activities is 'finish-start with no lag except for the following activities. Table 1: Relationship...

  • 17. The types of float in a CPM schedule are a. free Float b. negative Float...

    17. The types of float in a CPM schedule are a. free Float b. negative Float c. total Float d. independent Float e. all of the above 18. A loop in the schedule means a. circular logic between two activities b. two paths with the same logic c. duplicate activities d. negative float e. a and d 19. Constraints can be define as a. imposed restrictions applied to activities to reflect project requirements that cannot be built into the logic....

  • QUESTION 1 Please use the information below to draw and solve the network on a piece...

    QUESTION 1 Please use the information below to draw and solve the network on a piece of paper by: Complete the forward and backward pass Identify the critical path Fill in the requested information (Example: ESA Early Start of Activity A; LFA Late Finish of Activity A, etc) Relationship Activity Contract sign Predecessor Activity ID Duration 3 А Survey В 2 А Target market C Data В,С D 7 collection Presentation 2 FS Lag 3 E В Analyze F 2...

  • hi need answers for this urgently thanks Question 2 (20 Marks) a) Given the following project...

    hi need answers for this urgently thanks Question 2 (20 Marks) a) Given the following project details, identify the project's critical path; Activity Predecessor A B Duration (Man Days) 5 10 12 8 6 15 D Ε F B, C GE CD G H 20 18 30 5 I,J к F, L M (10 Marks) Continued... b) Given the information below, identify how much it would cost for each day you crash the schedule. Determine the total cost for crashing...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT