Question 2 (20 Marks) a) Given the following project details, identify the projects critical path; Activity Predecessor A B
b) Given the information below, identify how much it would cost for each day you crash the schedule. Determine the total cost
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

5

0

5

0

5

0

B

10

5

15

54

64

49

C

12

5

17

52

64

47

D

8

5

13

5

13

0

E

6

17

23

64

70

47

F

15

23

38

70

85

47

G

4

17

21

66

70

49

H

20

13

33

13

33

0

I

18

33

51

33

51

0

J

2

33

35

49

51

16

K

4

51

55

51

55

0

L

30

55

85

55

85

0

M

5

85

90

85

90

0


FORWARD PASS

We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.

BACKWARD PASS

We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.

SLACK

Slack is the value which is determined by subtracting EF from the LF or ES from the LS.

CRITICAL PATH

Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.

CRITICAL PATH & DURATION

A + D + H + I + K + L + M = 90


2. CRASHING



ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

12

0

12

0

12

0

B

8

12

20

13

21

1

C

9

12

21

12

21

0

D

6

21

27

21

27

0



FORWARD PASS

We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.

BACKWARD PASS

We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.

SLACK

Slack is the value which is determined by subtracting EF from the LF or ES from the LS.

CRITICAL PATH

Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.

CRITICAL PATH & DURATION

A + C + D = 27


EXPLANATION

1. We calculate crash cost per period by using the formula:

CPP = (CRASH COST - NORMAL COST) / (NORMAL TIME - CRASH TIME)

2. If we have 1 critical path, we crash an activity from it with the least crash cost per day and can still be crashed.

3. We recalculate the critical path after the crash to see if the critical path is still the critical path, if there’s still 1 critical path, we repeat step 2, else we crash 1 activity from each chain, till we get the desired crashed period.



ACTIVITY

NORMAL TIME

CRASH TIME

NORMAL COST

CRASH COST

CRASH COST PER PERID

CRASH TIMES

CRASH #

COST

A

12

12

200

350

0

0

B

8

8

300

300

0

0

C

9

7

250

450

100

1

1

100

D

6

5

400

600

200

1

2

200

TOTAL POSSIBLE CRASHES = 2

TOTAL CRASH COST = 300



Add a comment
Know the answer?
Add Answer to:
hi need answers for this urgently thanks Question 2 (20 Marks) a) Given the following project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 2. (30%) The following table provides the information necessary to construct project network and calculate...

    Question 2. (30%) The following table provides the information necessary to construct project network and calculate a total project cost. In case of activity crash, the information includes crash cost for each activity. Activity Immediate predecessor(s) Activity time (weeks) Normal cost (x1000$) Additional cost for crashing one week (x1000$) Normal After maximum crash A - 16 12 2,000 300 B - 14 9 1,000 160 C A 8 6 500 100 D A 5 4 600 700 E B 4...

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • 1) Based on the given information regarding the activities for the project, the project length= ___...

    1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...

  • Project Cycle

    The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14.(a) What is the shortest time duration for this project regardless of cost?(30 marks) (b) What is the total cost and time of the minimum-cost schedule?(10 marks)Table 1:...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to S150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. Normal Time Crash Time Crash Cost Immediate Normal Cost ($) Activity (S) (days) (days) Predecessor(s) 6 800 1,200 A 4 6 1,000 2,200 C 600 1...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given $150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. the following table. Indirect project costs amount to Normal Time Crash Time Crash Cost Immediate Normal Cost (S) Activity Predecessor(s) (S) (days) (days) 1.200 A 6 800 4 6 1,000 2 2,200 600 900 C...

  • Question 1: I)-What is the normal cost of this project? II)-What is the cost of the...

    Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 da...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Please show work and calculations. NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300 400 C 4 3 500 600 5 3 900 1,200 A 5 1,000 1,600 C LO LO C Ln LLI NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT