26.According to the DISC acronym, _____ relates to control, power, and assertiveness.
independence |
||
steadiness |
||
influence |
||
dominance |
||
competence |
28.Which of the following is an example of asynchronous communications?
Texting |
||
Mail and package delivery |
||
Instant messaging |
||
Computer-assisted conference |
||
Audio conference |
33.Which of the following is an example of synchronous communications?
Web log |
||
Fax |
||
Computer-assisted conference |
||
Mail and package delivery |
||
Electronic mail |
36.A table reflecting Communication Escalation will contain information about all of the following EXCEPT:
Priority |
||
Definitions |
||
Decision Authority |
||
Timeframe for Notification |
||
Communication Type |
37.The _____ schedule is a summary level schedule that encompasses the entire project scope.
original |
||
milestone |
||
procurement |
||
master |
||
conceptual |
39.Work performed on the project that consumes project resources, including cost and time are called _____.
sequences |
||
attributes |
||
activities |
||
decompositions |
||
milestones |
40.A(n) _____ has no duration or resources, and is simply an indicator of an important point in the project.
node |
||
milestone |
||
inference |
||
hierarchy |
||
attribute |
41. is the difference between the finish date of the last activity on the critical path and the project completion date.
Lag time |
||
Control limit |
||
Total float |
||
Contingency time |
||
Forward pass |
44.The time an activity that is not on the critical path can be delayed without delaying the start of a successor activity is called _____.
free float |
||
assignable cause |
||
forward pass |
||
contingency time |
||
scope creep |
46.The _____ is a technique for graphically displaying the logic of the scheduled activities using boxes and arrows.
responsibility matrix |
||
precedence diagram method |
||
arrow diagramming method |
||
critical path method |
||
project evaluation and review technique |
47.The Gantt chart:
is usually difficult to read and analyze. |
||
is also called a PERT chart. |
||
is used to indicate duration and relationships between project activities. |
||
illustrates complex relationships well. |
||
is a time-scaled graphic that represents each activity with connected straight line segments |
26 d) dominance
28 e) Audio conference
33 c) Computer-assisted conference
36 c) Decision Authority
We are asked to perform only 4 subparts of a single question if you think this helped do give a thumbs up else share your queries in comment section.
26.According to the DISC acronym, _____ relates to control, power, and assertiveness. independence steadiness influence dominance...
Q#1) True or False statements: Circle (T) for True or (F) l) The cost of installing surveillance cameras is a non-recurring expense 2) The salary of the project manager is a recurring expense 3) Risk and uncertainty increase with time TİF Cost of making changes increase with time 5) Ideas generated during brainstorming are ranked in order of their 6) In focus group interviews, people from different segments and viewpoints TF 7) Duration is the number of workdays or work...
ISOM319 Operations Management Instructions: For each topic (with bullet point) please use one or two sentences to describe or define the topic , can be as simple as a definition. You may use the book to help you with concepts you may not remember. Process Analysis · Process Flow Diagram · Little’s Law: Flow Unit, Flow Rate, Flow Time · Inventory Turns, Direct Labor Cost, Productivity, Yield Capacity Management and Analysis · Capacity Management · Capacity Analysis: Theoretical vs Actual Capacities, Utilization, Process Capacity, Process Flow...
Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...
First, read the article on "The Delphi Method for Graduate Research." ------ Article is posted below Include each of the following in your answer (if applicable – explain in a paragraph) Research problem: what do you want to solve using Delphi? Sample: who will participate and why? (answer in 5 -10 sentences) Round one questionnaire: include 5 hypothetical questions you would like to ask Discuss: what are possible outcomes of the findings from your study? Hint: this is the conclusion....
Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
Discussion questions 1. What is the link between internal marketing and service quality in the airline industry? 2. What internal marketing programmes could British Airways put into place to avoid further internal unrest? What potential is there to extend auch programmes to external partners? 3. What challenges may BA face in implementing an internal marketing programme to deliver value to its customers? (1981)ǐn the context ofbank marketing ths theme has bon pururd by other, nashri oriented towards the identification of...
Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...