Given details are:
Activity |
Predecessor |
A |
---- |
B C D E |
A |
F |
B |
G |
C |
K |
B D G |
H |
D |
J |
E H |
I |
E |
N |
I |
L |
F K |
M |
K J I |
O |
L M N |
Hope it is fine.
Case-2 Consider that you have an interview in a construction firm and they asked you to...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence diagram is shown in Figure 1 Figure 2 Figure 3 Figure 1 Figure 2 Figure 3 In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence...
Problems 3.4.3.14 relate to Project Management Techniques • 3.4 Using the project information listed in the table below: a) Draw the AON network for the construction activity. b) Draw the AOA for the construction activity. ACTIVITY IMMEDIATE PREDECESSOR(S) DURATION (DAYS) A 4 B - 2 с 2 D A 2. E B 3 B 4 F G 2 H с D, E F, G 5 3 -
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity Immediate Predecessor(s) Time (weeks) = C, E WLUI WNVN = n a a) Choose the correct network to represent this situation. OA. OB b) The critical path is B-E-F-H c) The length of the critical path is . weeks.
(30%Juana Pueblo is the owner ofJPPR Construction, a Activity Description company that specializes in the construction of single-family residences and small office buildings. She wants to apply project scheduling techniques to one of the homebuilding project she will be undertaking in the near future, Juana hasRough plur identified each of the major activities required for this projectD Frame and has estimated how much time each activity will require Finis The table at the right summarizes this information along withInstall HVAC...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 5 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E, F 7 Carl's team should be able to complete the project in nothing days. Critical path activities for Carl's project are .
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 55 B A 44 C A 66 D B 66 E B 44 F C 44 G D 66 H E, F 99 Carl's team should be able to complete the project in ? days.
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) - ITMO OWNono Ana E, F D GH a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-
Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...
project are listed for a In the following table the activities with their precedence sequence and expected time (days) Immediate Predecessor(s) Time (days) Activity 7 A 2 A B 4 C 4 5 5 E C F 2 G E, F 3 H G, H a) The activities on the critical path are b) The project length is days.