Answer (i) TRUE
Explanation:
Arithmetical increase method predicts a lower estimate than the actual population. Thus the Arithmetical increase method is suitable for older cities, whereas a geometrical increase method is suitable for new cities. Geometric increase method predicts a greater population than the aithmetic increase method.
Reference:
"Handbook of Engineering Hydrology: Environmental Hydrology and Water Management".
Answer (ii) WRONG
Explanation:
In gravity method, water flows under the influence of gravity only. Therefore this method can be used to transport water from higher to lower elevation only.
Reference:
"Gravity Flow Water Supply" by Santiago Arnalich
Answer (iii) TRUE
Explanation:
Self cleansing velocity is necessary to reduce the risk of accumulation of deposits.
Reference:
"Urban and Highway Stormwater Pollution: Concepts and Engineering" by Thorkild Hvitved-Jacobsen, Jes Vollertsen, Asbjorn Haaning Nielsen
Answer (iv) WRONG
Explanation:
Pumps can be arranged in parallel to achieve higher flow rate wheras the pumps in series has higher pumping head. Long distance transport of water requires higher pumping head. Thus the best arrangement is series arrangement. Thus the given statement is wrong.
Reference:
"Fluid Mechanics - Fundamentals and applications" by Yunus A Cengel and John M Cimbala
QUESTION 2 Check whether the following statements are true or wrong. i. The geometric increase method...
10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...