Question

We have the opportunity to building a new manufacturing facility which will reduce our annual cost...

We have the opportunity to building a new manufacturing facility which will reduce our annual cost of production for 50 million pounds of fertilizer from $1.00/lb. to $.70/lb. The life of the new plant will be 20 years. The engineering firm we have hired estimates the cost to build the plant at $80 million, all to be spent in the current year. The contract with the plant construction company limits the maximum cost to the engineering firm estimate plus 10%. NOTE: Answer 1 through 3 with the number in $ millions to two decimal places and number 4 as an annual percentage.

1. What are our expected annual savings if we build the plant?

2. If we own the building site, and its market value is $8 million, what is the NPV of the investment if the engineering estimate is correct, and the cost of capital is 12% per annum?

3. What is the NPV of the given assumptions in b., but now the plant costs the maximum plant construction contract?

4. What is the IRR of the project if the engineering estimate is correct?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans Annual Savings production so to new facility million pounds $1 $ 0.70 $0.30 Ilbs 1 Expected annual savings = 50 million xPage 3 Plant construction cost $ 80 million NPV of Investment = Annual Saving x PVA F (12%, 20)- Initial Investment 15× 7.469

Add a comment
Know the answer?
Add Answer to:
We have the opportunity to building a new manufacturing facility which will reduce our annual cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are considering opening a new plant. The plant will cost $97.7 million up front and...

    You are considering opening a new plant. The plant will cost $97.7 million up front and will take one year to build. After that it is expected to produce profits of $28.7 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.3%. Should you make the investment? Calculate the IRR and use it to determine the maximum deviation allowable...

  • You are considering opening a new plant. The plant will cost $103.8 million up front and...

    You are considering opening a new plant. The plant will cost $103.8 million up front and will take one year to build. After that it is expected to produce profits of $31.1 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.8%. Should you make the investment? Calculate the IRR and use it to determine the maximum deviation allowable...

  • You are considering opening a new plant. The plant will cost $100.6 million up front and...

    You are considering opening a new plant. The plant will cost $100.6 million up front and will take one year to build. After that it is expected to produce profits of $30.1 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.2%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...

  • You are considering opening a new plant. The plant will cost $101.8 million up front and...

    You are considering opening a new plant. The plant will cost $101.8 million up front and will take one year to build. After that it is expected to produce profits of $29.7 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.7%. Should you make the investment? Calculate the IRR and use it to determine the maximum deviation allowable...

  • You are considering opening a new plant. The plant will cost $100.5 million up front and will take one year to build. Af...

    You are considering opening a new plant. The plant will cost $100.5 million up front and will take one year to build. After that it is expected to produce profits of $29.1 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.1%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...

  • you are considering opening a new plant. The plant will cost $103.1 million upfront and will...

    you are considering opening a new plant. The plant will cost $103.1 million upfront and will take one year to build. After that it is expected to produce profits of $30.2 million at the end of every year of production. The cash flow's are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.2%. Should you make the investment. Calculate the IRR and use it to determine the maximum deviation allowable in...

  • Your firm has been hired to develop new software for the​ university's class registration system. Under...

    Your firm has been hired to develop new software for the​ university's class registration system. Under the​ contract, you will receive $ 508,000 as an upfront payment. You expect the development costs to be $ 431,000 per year for the next 3 years. Once the new system is in​ place, you will receive a final payment of $ 825,000 from the university 4 years from now. a. What are the IRRs of this​ opportunity?  ​ (Hint: Build an Excel model...

  • Your firm has been hired to develop new software for the​ university's class registration system. Under...

    Your firm has been hired to develop new software for the​ university's class registration system. Under the​ contract, you will receive $ 506,000 as an upfront payment. You expect the development costs to be $ 441,000 per year for the next 3 years. Once the new system is in​ place, you will receive a final payment of $ 857,000 from the university 4 years from now. a. What are the IRRs of this​ opportunity?  ​ (Hint: Build an Excel model...

  • Your firm has been hired to develop new software for the​ university's class registration system. Under...

    Your firm has been hired to develop new software for the​ university's class registration system. Under the​ contract, you will receive $ 505 comma 000 as an upfront payment. You expect the development costs to be $ 434 comma 000 per year for the next 3 years. Once the new system is in​ place, you will receive a final payment of $ 837 comma 000 from the university 4 years from now. a. What are the IRRs of this​ opportunity?  ...

  • Your firm has been hired to develop new software for the​university's class registration system. Under the​...

    Your firm has been hired to develop new software for the​university's class registration system. Under the​ contract, you will receive $ 497,000 as an upfront payment. You expect the development costs to be $ 439,000 per year for the next 3 years. Once the new system is in​ place, you will receive a final payment of $ 860,000 from the university 4 years from now. a. What are the IRRs of this​ opportunity?(Hint: Build an Excel model which tests the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT