Question

Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (st

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:

Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6
A 1 2 4 2.17
B 11 12.5 14 12.50
C 9 12 15 12.00
D 4 5 7 5.17
E 2 4 5 3.83
F 4 7 8 6.67
G 3 5 6.5 4.92
H 4 7 9 6.83
I 10.5 13 14 12.75
J 3 4 7 4.33
K 2 4 6 4.00
L 1 5 6 4.50
M 3 6 6.5 5.58
N 8 12.3 15 12.03
O 4 7 8 6.67
P 3 8 9 7.33
step 1 find early start, and early finish from the start of the project for each activity
Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D
A 2.17 0.00 2.17
B 12.50 0.00 12.50
C 12.00 0.00 12.00
D 5.17 0.00 5.17
E 3.83 0.00 3.83
F 6.67 2.17 8.84
G 4.92 12.50 17.42
H 6.83 12.00 18.83
I 12.75 12.00 24.75
J 4.33 12.00 16.33
K 4.00 5.17 9.17
L 4.50 3.83 8.33
M 5.58 18.83 24.41
N 12.03 16.33 28.36
O 6.67 24.75 31.42
P 7.33 28.36 35.69
step 2 Find Maximum EF

Max of EF is 35.69, hence the project will take 35.69 weeks

Answer a: So we should start the project 35.69 weeks before

Please ask, if you have any doubts through the comment section. Do rate the answer

Add a comment
Know the answer?
Add Answer to:
Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT