1) Incremental Analysis :-

Particulars Make Outsource Difference
Variable Costs (80000*$14.75)=$1180000 (80000*$12.90)=$1032000 $148000
Plus : Fixed Costs (80000*$1.25)=$100000 $100000
Total Cost of 80000 Components $1280000 $1032000 $248000
Less : Profit from another Product ($26000) $26000
Net Cost $1280000 $1006000 $274000

If River Enterprises outsources the Manufacturing of component. Operating income will

Increase by $274000

2) Maximum Price Per Unit if Outsourced :-

= ((80000*$16) + $26000)/80000

= $16.325

Add a comment
Know the answer?
Add Answer to:
8 pts capacity couid be used to build a new product. This new product would be...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Instant Enterprises manufactures one of the components used to assemble its main company product ...

    instant Enterprises manufactures one of the components used to assemble its main company product Specialty Products, This current cost per unit is based on the folowing callcufations component, based on the 115,000 components that instant Enterprises currently produces. Read the tequirements see current cost is $13.50 per unvt ofthhe icon to view the information) None of Instant Enterprises' fxed costs will be eliminated if the component is outsourced However, the treed capacity couid be used to build a new product...

  • HOMIE food manufacturing company needs to make capacity decisions to produce a new product line to...

    HOMIE food manufacturing company needs to make capacity decisions to produce a new product line to export to the regional market. As chief operations officer of this company, you are considering three options in the face of considerable uncertainties over the next four years: Option 1: Build a new factory, - New site cost is $6 million, - Payoffs: Strong demand = $12 million; Weak demand= $10 million. Option 2: Expand at current site, - Expanding current site cost is...

  • Question 22 10 pts Suppose that an electricity provider would build a power plant at the...

    Question 22 10 pts Suppose that an electricity provider would build a power plant at the cost of $50 million. Once the plant is built, it would cost the plant $0.07 per kilowatt hour of electricity that it produces. Over its lifetime, the plant is expected to generate 100 million kilowatt hours. Suppose that the regulators believe that the investors who put up capital to build the plant should be able to recoup its investment plus a 300% return throughout...

  • requirmemt 3 Save omework: Chapter 08 Graded Homework core: 5.57 of 6 pts 4 of 5...

    requirmemt 3 Save omework: Chapter 08 Graded Homework core: 5.57 of 6 pts 4 of 5 (5 complete) E8-28A (similar to) HW Score: 94.97%, 28.49 of 30 pts Question Help GlobalSystems manufactures an optical switch that it uses in its final product. Global Systems incurred the following manufacturing costs when it produced 68.000 units last year: 318 (Click the icon to view the manufacturing costs.) GlobalSystems does not yet know how many ruches it will need this year, however, another...

  • Another manager wants to evaluate an internal process that would be used to produce the new produ...

    Another manager wants to evaluate an internal process that would be used to produce the new product. The fixed and variable costs and capacities for each process are listed below. Utilize this information to answer questions 3-4 Fixed Cost 140,000 200,000 90,000 Variable Cost/Unit 40 20 60 rocesS apa 5,000 7,000 2,000 3. What are the low-cost output ranges for each alternative given the cost info and capacity info above? (show ALL pertinent math and relevant ranges below (on both...

  • Fanya Construction Company expects to build three new homes during a specific accounting period and labor...

    Fanya Construction Company expects to build three new homes during a specific accounting period and labor costs are as follows: direct materials Expected Costs Direct labor Direct materials Home 1 $40,000 30,000 Home 2 11 Home 3 $60,000 $100.000 50,000 80.000 points (8 01:45:09 Assume Fanya needs to allocate two major overhead costs ($80,000 of employee fringe ployee fringe benefits and $40,000 of indirect materials costs) among the three jobs. Required Choose an appropriate cost driver for each of the...

  • Ford is going to produce a new vehicle, the Bronco, and wants to determine the amount of annual capacity it should build. Ford's goal is to maximize the profit from this vehicle over the next 5 y...

    Ford is going to produce a new vehicle, the Bronco, and wants to determine the amount of annual capacity it should build. Ford's goal is to maximize the profit from this vehicle over the next 5 years. The average vehicle will sell for $39,000 and incur a variable production cost of $26,000. Building one unit of annual capacity ill cost $2,000. Each unit of capacity will also cost $1,000 per year to maintain, even if capacity is unused. Demand for...

  • Question 6 10 pts A major retail company plans to build 30,000 square building that would...

    Question 6 10 pts A major retail company plans to build 30,000 square building that would cost $8 million to develop. It is expected to lease for $22 per foot (absolute net) with $5 per foot in operating expenses. If the company develops the property and does a sale-leaseback, what price will they get if the property is sold at a 6% cap rate? O $9,777,778 o$ 10,153,846 $ 10,560,000 $ 11,000,000 $ 11,478,261 10 pts

  • CASE-PART A Shrieves Casting Company is considering adding a new product line to its product mix,...

    CASE-PART A Shrieves Casting Company is considering adding a new product line to its product mix, and the capital budgeting analysis is being conducted by Sidney Johnson, a recent business school graduate. The production line would be set up in unused space in Shrieves’s main plant. The machinery’s invoice price would be approximately $200,000, another $10,000 in shipping charges would be required to acquire the machinery from the supplier, and it would cost an additional $30,000 to install the equipment....

  • 1. A food processor is considering the development of a new line of product. Depending on...

    1. A food processor is considering the development of a new line of product. Depending on the quality of raw material, he can expect äifferent yields process-wise, and the quality of the final products will also alternatives, and produced them in a pilot scale. The marketing department has used those samples for surveys to estimate potential sales and pricing strategies. The three alternatives would use existing equipment, but different process conditions and specifications, and they are summarized as follows. Indicate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT