The Money Pit Mortoage Company is interested in monitoring the performance of the mortoage procees. Firieen samples of five c

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

R= Max- Min X-bar= average of sample
4 13
10 11
3 5
7 14
8 9
14 9
11 12
14 13
9 10
9 11
11 13
5 6
8 8
10 6
12 9
9.000 9.933
R-bar (Average of above values)

X-bar-bar (average of above values)

D4, D3 and A2 are taken from table of factors computing 3 sigma control limits, sample size= 5

Range

D4 (n=5)= 2.115
D3 (n=5)= 0
control limits for Range,
CL or R-bar= 9.000
UCL=R-bar*D4 19.035
LCL=R-bar*D3 0.000

Mean

A2 (n=5) 0.577
control limits for X bar,
CL or Xbarbar 9.933
UCL=Xbarbar+ (A2)*Rbar 15.126
LCL=Xbarbar- (A2)*Rbar 4.740
Add a comment
Know the answer?
Add Answer to:
The Money Pit Mortoage Company is interested in monitoring the performance of the mortoage procees. Firieen...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen...

    The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The means and ranges of the mortgage process transaction​ times, measured in​ days, are as​ follows: b. Sample123456789 10 11 12 13 14 15 Mean 5 103 7 8 13 14 9 9 9 5...

  • Question pertains to the x-chart part Sample Mean Range 16 8 12 13 6 6 4...

    Question pertains to the x-chart part Sample Mean Range 16 8 12 13 6 6 4 15 10 10 11 10 16 13 14 0 14 17 11 12 IU 12 12 11 13 14 12 7 8 13 9 11 14 7 13 15 10 15 Subsequently, samples of size 5 were taken from the process every week for the next 10 weeks. The times were measured and the following results oblained: Sample Mean Range 16 9 17 12...

  • The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen...

    The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The Money Pit Mortgage Company made some changes to the process and undertook a process capability study. The following data were obtained for 15 samples of size 5. Based on the individual observations, management estimated...

  • The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen...

    The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The Money Pit Mortgage Company made some changes to the process and undertook a process capability study. The following data were obtained for 15 samples of size 5. Based on the individual​ observations, management estimated...

  • 1st*variability is: in control/out of control 2nd*no samples fall/one/two/more 3rd* in control/out of control The following...

    1st*variability is: in control/out of control 2nd*no samples fall/one/two/more 3rd* in control/out of control The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. X Sample R 1 95.72 1.0 95.24 2 0.9 0.9 95.18 95.42 0.4 4 5 95.46 0.5 95.32 1.1 6 7 95.40 0.9 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12...

  • Problem 10-25 Resistors for electronic circuits are manufactured on a high-speed automated machin...

    Problem 10-25 Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is set up to produce a large run of resistors of 1,000 ohms each. Use Exhibit 10.13. To set up the machine and to create a control chart to be used throughout the run, 15 samples were taken with four resistors in each sample. The complete list of samples and their measured values are as follows: Use three-sigma control limits READINGS (IN OHMS) 1014 1019...

  • Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is set up...

    Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is set up to produce a large run of resistors of 1,000 ohms each. Use Exhibit 10.13.      To set up the machine and to create a control chart to be used throughout the run, 15 samples were taken with four resistors in each sample. The complete list of samples and their measured values are as follows: Use three-sigma control limits. SAMPLE NUMBER READINGS (IN OHMS) 1 1000...

  • Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is set up...

    Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is set up to produce a large run of resistors of 1,000 ohms each. Use Exhibit 10.13. To set up the machine and to create a control chart to be used throughout the run, 15 samples were taken with four resistors in each sample. The complete list of samples and their measured values are as follows: Use three-sigma control limits. SAMPLE NUMBER READINGS (IN OHMS) 1 992...

  • Refer to Table 56.1 - Factors for Computing Control Chart Limits (sigma) for this problem. Thirty-five...

    Refer to Table 56.1 - Factors for Computing Control Chart Limits (sigma) for this problem. Thirty-five samples of size 7 each were taken from a fertilizer-bag-filling machine at Panos Kouvels Lifelong Lawn Lid. The results were: Overal mean = 54.75 lb.: Average range R 164 b. a) For the given sample size, the control limits for 3-sigma x chart are Upper Control Limit (UCL) - D. (round your response to three decimal places). Lower Control Limit (LCL)-1. (round your response...

  • Problem 10-25 Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is...

    Problem 10-25 Resistors for electronic circuits are manufactured on a high-speed automated machine. The machine is set up to produce a large run of resistors of 1,000 ohms each. Use Exhibit 10.13 To set up the machine and to create a control chart to be used throughout the run, 15 samples were taken with four resistors in each sample. The complete list of samples and their measured values are as follows: Use three-sigma control limits. SAMPLE NUMBER 1 2 3...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT