The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The Money Pit Mortgage Company made some changes to the process and undertook a process capability study. The following data were obtained for 15 samples of size 5. Based on the individual observations, management estimated the process standard deviation to be 4.98 (days) for use in the process capability analysis. The lower and upper specification limits (in days) for the mortgage process times were 9 and 23. Sample 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Mean 13 15 11 19 16 14 20 19 16 17 20 12 18 17 12 Range 6 11 2 9 8 6 6 13 12 9 5 4 10 8 9 a. Calculate the process capability index and the process capability ratio values. The process capability index Upper C Subscript pkequals nothing. (Enter your response rounded to three decimal places.) The process capability ratio Upper C Subscript pequals nothing. (Enter your response rounded to three decimal places.) b. Suppose management would be happy with three-sigma performance. What conclusions is management likely to draw from the capability analysis? Since Upper C Subscript pk is ▼ greater than equal to less than the critical value, the process ▼ is is not capable at the three-sigma level. Since Upper C Subscript p is ▼ less than greater than equal to the critical value, this indicates that ▼ the process variability is too large the process is not centered adequately . c. What remedial actions, if any, do you suggest that management take? A. Management should use a lower target process capability ratio. B. The specification limits must be revised. C. The variability of the process must be greatly reduced. D. Nothing. The process is capable.
Average of data |
µ |
15.93 |
|
Standard deviation of Data |
σ |
4.98 |
|
Upper Specification Limit (USL) |
USL |
23 |
|
Lower Specification Limit (LSL) |
LSL |
9 |
|
Process Capability |
Cp = (USL – LSL)/6σ Cp = (23 – 9)/(6*4.98) |
Cp = 0.4685 |
|
Upper Cpk |
Upper Cpk = [(USL - µ) / (3σ)] Upper Cpk = (23 – 15.93)/(3*4.98) |
0.4732 |
|
Lower Cpk |
Lower Cpk = [(µ - LSL) / (3σ)] Lower Cpk = (15.93 – 9)/(3*4.98) |
0.4638 |
|
Process Cpk |
Cpk = Min (Upper Cpk, Lower Cpk) = Min ([(USL - µ) / (3σ)],[(µ - LSL) / (3σ)]) |
=min(0.4732, 0.4638) = 0.6836 |
a. Calculate the process capability index and the process capability ratio values.
The process capability index, Cpk = 0.4732
Process capability ratio, Cp = 0.4685
b. According to 3-sigma performance the critical value is 1, if capability is less than 1 not capable and more than 1 the process is capable.
Since Cpk less than critical value, the process is not capable at the three sigma level.
Since Cp is less than critical value, this indicates that process variability is too large.
c.
Remedial actions,
Correct Option: The variability must be greatly reduced.
(Since the Cp < 1 and also Cpk <1, the process control limits way beyond specification limits.
The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen...
The Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The Money Pit Mortgage Company made some changes to the process and undertook a process capability study. The following data were obtained for 15 samples of size 5. Based on the individual observations, management estimated...
The
Money Pit Mortgage Company is interested in monitoring the
performance of the mortgage process. Fifteen samples of five
completed mortgage transactions each were taken during a period
when the process was believed to be in control. The times to
complete the transactions were measured. The means and ranges of
the mortgage process transaction times, measured in days, are as
follows:
b.
Sample123456789 10 11 12 13 14 15 Mean 5 103 7 8 13 14 9 9 9 5...
The Money Pit Mortoage Company is interested in monitoring the performance of the mortoage procees. Firieen samples of five compieted mortgage traneactions each were teken duing a period when the procees was beieved to be in control The times to complete the transsctons were meesured. The meens and ranges of the mongege process trensschon imes, measured in days, are as folows: Sample 1 2 3 4 9 10 11 12 13 14 15 Mean 13 11 5 14 12 13...
1) Triangle Packaging Machinery wants to test the quality of its cereal bag filling machines. The firm’s quality analyst took 35 samples of size 7 each from a cereal-bag-filling machine. The results were overall mean = 57.75 pounds; average range = 1.78 pounds. a) Determine the upper and lower control limits of the x-chart, where sigma = 3 b) Determine the upper and lower control limits of the R-chart, where sigma = 3 2) The results of an inspection of...
Management at Webster Chemical Company is concerned as to whether caulking tubes are being properly capped. If a significant proportion of the tubes are not being sealed, Webster is placing its customers in a messy situation. Tubes are packaged in large boxes of 145145. Several boxes are inspected, and the following numbers of leaking tubes are found: Sample Tubes Sample Tubes Sample Tubes 1 11 8 22 15 55 2 99 9 88 16 44 3 44 10 22...
Question 4 [20 marks] By utilising Annexure A, answer the following questions: (a) 15 samples of n 8 have been taken from a cleaning operation. The average sample range for the 20 samples was 0.016 minute, and the average mean was 3 minutes. Determine the three-sigma control limits for this process. (4 marks) (b) 15 samples of n 10 observations have been taken from a milling process. The average sample range is 0.01 centimetres. Determine upper and lower control limits...
54 A manufacturing process for the company producing wheel bearings was investigated Samples of 4 subgroups where tested each containing 6 wheel bearings The specification limits for the process are given as 40 and 5 2 Given the following data for random measurements taken on the wheel bearing dunng their three shifts 56 54 Subgroup 1 Subgroup 2 Subgroup 3 59 50 48 52 51 50 464258 52 57 50 543 56 47 | 49 Subgroup 4 55 51 50...
kon over the past 10 days are given below. Sample size is 100. Day Defectives 1 7 2 9 3 9 4 11 5 7 6 8 7 0 8 11 9 13 10 2 a) The upper and lower 3-sigma control chart limits are: UCL, -(enter your response as a number between 0 and 1, rounded to three decimal places). LCL - Center your response as a number between 0 and 1, rounded to three decimal plocos). b) Given...
54 A manufacturing process for the company producing wheel bearings was investigated Samples of 4 subgroups where tested each containing 6 wheel bearings The specification limits for the process are given as 40 and 52 Given the following data for random measurements taken on the wheel bearing dunng their three shifts Subgroup 1 59 5 0 48 52 56 Subgroup 2 52 56 5 43 51 42 50 58 57 50 Subgroup 3 46 49 49 Subgroup 4 55 50...
Question pertains to the
x-chart part
Sample Mean Range 16 8 12 13 6 6 4 15 10 10 11 10 16 13 14 0 14 17 11 12 IU 12 12 11 13 14 12 7 8 13 9 11 14 7 13 15 10 15 Subsequently, samples of size 5 were taken from the process every week for the next 10 weeks. The times were measured and the following results oblained: Sample Mean Range 16 9 17 12...