Question
- Do NOT round calculations, ONLY round final answer for each individual required in a problem
- Use rounded answers for subsequent questions for same problem
- Dollar amount - round to nearest penny
- % to two decimal places
- round units to the next unit


Greene Inc. uses a job-order costing system with machine hours as the allocation base for overhead. The company uses normal c
Question 20 (1 point) What is the overhead allocation rate per machine hour? A Question 21 (1 point) The amount of overhead a
Question 23 (2 points) Job 4560 was completed in July and the client was billed at cost plus 60%. The price of Job 4560 was $
Question 25 (1 point) At the end of the year actual factory overhead is $1,587,000. This means that factory overhead is a) Ne
0 0
Add a comment Improve this question Transcribed image text
Answer #1

20. Answer: $15.00

Calculations:

Total Estimated factory overhead costs $1,725,000
÷ Total Estimated machine hours 115,000
= Overhead allocation rate per machine hour $15.00

21.Answer: $2,250.00

Calculations:

Machine hours for Job # 4560 150
x Overhead allocation rate per machine hour $15.00
= The amount of overhead applied to Job 4560 $2,250.00

22.Answer: $1,050.00

Calculations:

Machine hours for Job # 4570 70
x Overhead allocation rate per machine hour $15.00
= The amount of overhead applied to Job 4570 $1,050.00

23.Answer: $42,960.00

Calculations:

Job # 4560
Direct materials $14,400
Direct labor $10,200
Overhead $2,250
Total cost $26,850
Add: Mark up [$26,850 x 60%] $16,110
Price for the Job #4560 $42,960

24. Answer: $1,620,000.00

Calculations:

Total Machine hours 108,000
x Overhead allocation rate per machine hour $15.00
= The amount of overhead applied to all Jobs $1,620,000.00

25. Answer: c)Over-applied

Explanation:

Applied overhead is more than the Actual. Therefore, it is over-applied.

26.Answer: Over-applied of $33,000.00

Calculations:

Overhead applied $1,620,000.00
Actual overhead ($1,587,000)
Over-applied (Under-applied) $33,000.00
Add a comment
Know the answer?
Add Answer to:
- Do NOT round calculations, ONLY round final answer for each individual required in a problem...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Bouldevard Inc. estimates that the factory overhead for the following year will be $975,000. The company...

    Bouldevard Inc. estimates that the factory overhead for the following year will be $975,000. The company has decided that the basis for applying factory overhead should be machine hours, which is estimated to be 48,000 hours. The total machine hours for the year were 49,250. The actual factory overhead for the year was $1,198,500 Note: Round to the nearest cent "You must provide calculations to receive credit. a. Compute the predetermined factory overhead rate. b. Determine the amount of factory...

  • 2 points Saved QUESTION 10 The Thomlin Company forecasts that total overhead for the current year...

    2 points Saved QUESTION 10 The Thomlin Company forecasts that total overhead for the current year will be $15,000,000 and that total machine hours will be 200,000 hours. Year to date, the actual overhead is $15,500,000 and the actual machine hours are 220,000 hours. If the Thomlin Company uses a predetermined overhead rate based on machine hours for applying overhead, as of this point in time (year to date), by how much is the overhead is over/underapplied? $500,000 over $1,000,000...

  • 5 pts Question 5 The Thomlin Company forecasts that total overhead for the current year will...

    5 pts Question 5 The Thomlin Company forecasts that total overhead for the current year will be $15,000,000 with 300,000 total machine hours. Year to date, the actual overhead is $16,000,000 and the actual machine hours are 330,000 hours. If the Thomlin Company uses a predetermined overhead rate based on machine hours for applying overhead, as of this point in time (year to date), the overhead is e $500,000 over applied O $1,000,000 over applied $500,000 under applied $1,000,000 under...

  • Hello, Please have a look at the picture attached and help me with questions below. Compute...

    Hello, Please have a look at the picture attached and help me with questions below. Compute the overhead allocation rate. If job number 1070 is chosen, find the allocated overhead and any over or under-applied overhead. Q1. Yahya Company uses a job costing system with machine hours as the allocation base for overhead. The company uses normal costing to develop the overhead allocation rate. The following data are available for the latest accounting period: Estimated fixed factory overhead cost Estimated...

  • can you show me with detailed calculations how to arrive at each answer. thanks Bierce Corporation...

    can you show me with detailed calculations how to arrive at each answer. thanks Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing 4, e00 $4 Total Estimated total machine-hours (MHs) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH 6, 000 $ 42, 000 10,000 $ 46, e00 $ 4, 000 $ 2.20 24 6.00 $4 warded...

  • A manufacturing company estimates it will incur $240,000 of overhead costs in the next vear The...

    A manufacturing company estimates it will incur $240,000 of overhead costs in the next vear The company applies overhead using machine hours and estimates it will use 1,600 machine 2. hours in the next year. What is the predetermined overhead rate for 2020? a) Fast forward to June 2020 when the company used 80 machine hours on Job 1 and 70 machine hours on Job 2. b) What is the overhead applied to Job 1? What is the overhead applied...

  • 6. What was the total manufacturing cost assigned to Job Q? (Do not round intermediate calculations.)...

    6. What was the total manufacturing cost assigned to Job Q? (Do not round intermediate calculations.) a. What was the company’s plant wide predetermined overhead rate? (Round your answer to 2 decimal places.) b. How much manufacturing overhead was applied to Job P and how much was applied to Job Q? (Do not round intermediate calculations.) 12. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest...

  • Part II - Job Costing Use the information below to answer the following questions: County Lawn...

    Part II - Job Costing Use the information below to answer the following questions: County Lawn and Garden Company is a manufacture of lawn and garden equipment: Budgeted and Actual for 2017 Budgeted variable factory overhead (Budgeted fixed factory overhead (Actual variable factory overhead (Actual fixed factory overhead Budgeted direct labor hours Budgeted direct labor dollars - Budgeted machine hours (Actual direct labor hours Actual direct labor dollars LActual machine hours Direct materials used $ 44,000 $31.000 $ 45,000 $...

  • Felix Company has decided to use a predetermined rate to assign factory overhead to production. The...

    Felix Company has decided to use a predetermined rate to assign factory overhead to production. The following predictions have been made for 2019: Estimate total factory overhead costs $480,000 Estimate direct labor hours 40,000 DLH Estimate direct labor costs $400,000 Estimate machine hours 120,000 MH Actual direct labor hours 38,000 DLH Actual direct labor costs $416,000 Actual machine hours 122,000 MH Required: Compute the predetermined factory overhead rate under three different bases: (1) direct labor hours, (2) direct labor costs,...

  • 3. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.)...

    3. What was the total manufacturing cost assigned to Job P? (Do not round intermediate calculations.) 4. If Job P included 20 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to nearest whole dollar.) 5. What was the total manufacturing cost assigned to Job Q? (Do not round intermediate calculations.) 6. If Job Q included 30 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT