Plotted fallout rate function, 1 - Y(T), given by: Fitting yields Af=2.1 and β=0.083. This gives f = Af/A = 2.1/(0.94*0.88) = 2.54 faults/sq. cm. Using these values, Eq (5) gives Y = 76.23 and (6) gives DL = 168 for T=0.9979
Testing Of Digital Systems A digital system board uses 40 ICs manufactured with two different independent...
Testing Of Digital Systems A digital system board uses 40 ICs manufactured with two different independent processes. 25 ICs are manufactured using process 1 that has 80 % yield and 90 % fault coverage. The cost of these ICs is 10 KD each. The remaining ICs (15) are manufactured using process 2 with 85 % yield and 95 % fault coverage. The cost of these ICs is 20 KD each. The board manufacturer spends 50 KD on the design and...
A digital system board uses 40 ICs manufactured with two different independent processes. 25 ICs are manufactured using process 1 that has 80 % yield and 90 % fault coverage. The cost of these ICs is 10 KD each. The remaining ICs (15) are manufactured using process 2 with 85 % yield and 95 % fault coverage. The cost of these ICs is 20 KD each. The board manufacturer spends 50 KD on the design and test of each board...