Question

I could use some help with the problem below: A project requires an initial outlay of...

I could use some help with the problem below:

A project requires an initial outlay of $50,000,000. The project life is determined to be 5 years at which time it will be discontinued and sold for scrap at $5,000,000. The project will generate net cash in-flows of $20,000,000 every year for the next five years. The projects required rate or discount rat is 11.25%

1. What is the projects Payback period?

2. What is the projects NPV?

3. What is the projects IRR?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Payback Period = ( Last Year with a Negative Cash Flow ) + [( Absolute Value of negative Cash Flow in that year)/ Total Cash Flow in the following year)]

= 2 + ( 10000000/20000000)

= 2.50 Years

Hence the correct answer is 2.50 Years

Note:

Year Investment Cash Inflow Net Cash Flow
0 -5,00,00,000 -    -5,00,00,000 (Investment + Cash Inflow)
1 -    2,00,00,000 -3,00,00,000 (Net Cash Flow + Cash Inflow)
2 -    2,00,00,000 -1,00,00,000 (Net Cash Flow + Cash Inflow)
3 -    2,00,00,000 1,00,00,000 (Net Cash Flow + Cash Inflow)
4 -    2,00,00,000 3,00,00,000 (Net Cash Flow + Cash Inflow)
5 -    2,50,00,000 5,50,00,000 (Net Cash Flow + Cash Inflow)

2.

Net Present Value = Present Value of Cash Inflows - Present Value of Cash Outflows

= [ $ 2,00,00,000 * 1/ (1.1125) ^ 1 +$ 2,00,00,000 * 1/ (1.1125) ^2 +$ 2,00,00,000 * 1/ (1.1125) ^3+$ 2,00,00,000 * 1/ (1.1125) ^4+$ 2,50,00,000 * 1/ (1.1125) ^5 ] -$ 5,00,00,000

= $ 26,389,490.75

Hence the correct answer is $ 26,389,490.75

3.

Let the IRR be x.

Now , Present Value of Cash Outflows=Present Value of Cash Inflows

5,00,00,000 = 2,00,00,000/(1.0x) +2,00,00,000/ (1.0x)^2 +2,00,00,000/(1.0x)^3+ $ 2,00,00,000/(1.0x)^4 +2,50,00,000/(1.0x)^5

Or x= 30.059%

Hence the IRR is 30.06%

Add a comment
Know the answer?
Add Answer to:
I could use some help with the problem below: A project requires an initial outlay of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • you are considering a project with an initial cash outlay of $74,000 and expected cash flows...

    you are considering a project with an initial cash outlay of $74,000 and expected cash flows of $23,680 at the end of each year for six years. the discount rate for the project is 9.7 percent. a. what are the project's payback discounted payback periods? - if the discount rate for this project is 9.7 percent, the discounted payback period of the project is how many years? b. what is the projects NPV? c. what is the project's PI? d....

  • There is a project. The initial outlay will be $10,800,000, and the project will generate cash...

    There is a project. The initial outlay will be $10,800,000, and the project will generate cash flows of $1,250,000 per year for 20 years. The appropriate discount rate is 9%. Calculate the NPV Calculate the PI Calculate the IRR Is it a good project? Why? Use Financial Calculator or Equations to answer this question. Show clearly which EQUATIONS could be used to solve the problem mathematically Indicating the detailed steps on how to use FINANCIAL CALCULATOR to solve the problems.

  •  You are considering a project with an initial cash outlay of ​$75,000 and expected cash flows...

     You are considering a project with an initial cash outlay of ​$75,000 and expected cash flows of ​$21,750 at the end of each year for six years. The discount rate for this project is 9.7 percent. a.  What are the​ project's payback and discounted payback​ periods? b.  What is the​ project's NPV? c.  What is the​ project's PI? d.  What is the​ project's IRR?

  • eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected...

    eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years, Mutually exclusive Project L requires an initial outlay at t = 0 of $48,000, and its expected cash flows would be $9,550 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer a. Project L, since the NPV > NPV- b. Both...

  • Newfoundland Vintners Co-operative is considering two mutually exclusive projects: Absinth and Brandy. Project Absinth requires a...

    Newfoundland Vintners Co-operative is considering two mutually exclusive projects: Absinth and Brandy. Project Absinth requires a $20,000 cash outlay today and is expected to generate after-tax cash flows of $11,000 in year 1, $8,500 in year 2, and $7,500 in year 3. Project Brandy requires a $30,000 cash outlay today and is expected to generate after-tax cash flows of $7,000 in year 1, $9,000 in year 2, $11,000 in year 3, and $16,000 in year 4. Neither project can be...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...

  • Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,500, and its expected cash flows would be $13,100 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVs > NPVĻ. b. Project L,...

  • Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT