Question

Assume that the risk adjusted cost of capital is 16% for project A, 18% for project...

  1. Assume that the risk adjusted cost of capital is 16% for project A, 18% for project B, and 20% for project C.


Project A:              Estimated cash flow is $25,800 per year for 10 years.
                              Cost $100,000


Project B:              Estimated cash flow is $33,500 per year for 8 years.
                              Cost $125,000


Project C:              Estimated cash flow is $44,000 per year for 7 years.
                              Cost $155,000


A. Compute the Payback, NPV, IRR and Profitability Index for each.
B. Rank order the Projects according to the value to the firm

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A

Project A
Year Cash flow stream Cumulative cash flow
0 -100000 -100000
1 25800 -74200
2 25800 -48400
3 25800 -22600
4 25800 3200
5 25800 29000
6 25800 54800
7 25800 80600
8 25800 106400
9 25800 132200
10 25800 158000
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 3 and 4
therefore by interpolation payback period = 3 + (0-(-22600))/(3200-(-22600))
3.88 Years
Project A
Discount rate 0.16
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -100000 25800 25800 25800 25800 25800 25800 25800 25800 25800 25800
Discounting factor 1 1.16 1.3456 1.560896 1.8106394 2.100342 2.436396 2.82622 3.278415 3.802961 4.411435
Discounted cash flows project -100000 22241.38 19173.6 16528.97 14249.11 12283.72 10589.41 9128.802 7869.657 6784.187 5848.437
NPV = Sum of discounted cash flows
NPV Project A = 24697.27
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
IRR is the rate at which NPV =0
IRR 22%
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -100000 25800 25800 25800 25800 25800 25800 25800 25800 25800 25800
Discounting factor 1 1.223746 1.497555 1.832628 2.2426724 2.744462 3.358526 4.109985 5.029579 6.15493 7.532074
Discounted cash flows project -100000 21082.8 17228.08 14078.14 11504.132 9400.748 7681.941 6277.396 5129.654 4191.762 3425.351
NPV = Sum of discounted cash flows
NPV Project A = 7.92529E-05
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 22.37%
Project A
PI= (NPV+initial inv.)/initial inv.
=(24697.27+100000)/100000
1.25



B

Based on NPV

Rank 1 Project A

Rank 2 Project B

Rank 3 Project C

Add a comment
Know the answer?
Add Answer to:
Assume that the risk adjusted cost of capital is 16% for project A, 18% for project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1)Compute the Payback, NPV, IRR, and Profitability Index for the following investments. Assume that the cost...

    1)Compute the Payback, NPV, IRR, and Profitability Index for the following investments. Assume that the cost of capital for each project is 15%. Project A. Estimated cash flow is 9,962.60 per year for 10 years. Cost $50,000 Project B. Estimated cash flow is $19,677.15 per year for 7 years. Cost $75,000 2) Determine the effective annualized costs of foregoing the trade credit discount on the following terms; A.3/10 net 40 B. 2/20 net 40 C. 4/20 net 60

  • a. What is the payback period for Project A? b.What is the payback period for Project...

    a. What is the payback period for Project A? b.What is the payback period for Project B? c. What is the discounted payback period for Project A? d. What is the discounted payback period for Project B? e. What is the NPV for Project A? f. What is the NPV for Project B? g. What is the IRR for Project A? h. What is the IRR for Project B? i. What is the profitability index for Project A? j. What...

  • The initial outlay for a project (cost) is $480,670 for a seven-year project. If the future...

    The initial outlay for a project (cost) is $480,670 for a seven-year project. If the future net cash flows from Assets are respectively for years 1 through seven: $100,000; $120,000; $59,000; $58,000; $102,000; $280,000; and $45,000. If the required return is 6.3%, A) What is the NPV of the project? B) What is the payback period without discounting cash flows? C) What is the profitability index? D) What is the IRR? D)

  • 6. Evaluate the following projects, using the profitability index. Assume a cost of capital of 11%....

    6. Evaluate the following projects, using the profitability index. Assume a cost of capital of 11%. Project Al Project B |Initial Cash Outflow - $260,0001-$250,000 Year 1 Cash flow 23,000 160,000 Year 2 Cash flow 127,000 95,000 Year 3 Cash flow | 190,000175,000 Ja. What is the profitability index for each project? b. If the projects are independent, which would you accept according to the profitability index criterion? c. If these projects are mutually exclusive, which would you accept according...

  • Alice Werd is a new project analyst; he is working on capital budgeting analysis of two...

    Alice Werd is a new project analyst; he is working on capital budgeting analysis of two mutually exclusive projects. The followings are the cash flow forecasts for both the projects years Project A Expected Cash flows Project B Expected Cash flows 0 (1000,000) ($900,000) 1 50000 650,000 2 200,000 650,000 3 600,000 550,000 4 1000,000 300,000 5 1500,000 100,000 The following metrics presents the key information based on capital budgeting indicators. For purposes of analysis, he plans to use a...

  • by hand #1 Questions a) to c) refer to two projects with the following cash flows:...

    by hand #1 Questions a) to c) refer to two projects with the following cash flows: Year Project B Project A - $200 80 -$200 100 80 100 80 100 Projects A and B are mutually exclusive. a) Calculate the Payback, Discounted Payback, NPV, IRR, and Profitability Index for Projects A and B using an opportunity cost of capital of 10% (where applicable). Which of these projects is worth pursuing? Explain. b) Calculate the Payback, Discounted Payback, NPV, IRR, and...

  • Please use Excel to solve! Ne Present Value and Other Capital Budgeting Measures 5. Consider a...

    Please use Excel to solve! Ne Present Value and Other Capital Budgeting Measures 5. Consider a project that has the following cash flows: initial cash flow (t-0) --$100,000; cash flows years 1 to 5 (t-1-5) - $10,000 per year, cash flows years 6 to 10 (t-6-10) - $20,000 per year. If the required return on the project is 6%, calculate the following: a. Internal Rate of Return (IRR)? b. Net Present Value (NPV)? c. Profitability index (PI)? d. Payback period?

  • Marge Simpson Inc. has following business opportunities with following cash flow information. Assume Marge’s opportunity cost...

    Marge Simpson Inc. has following business opportunities with following cash flow information. Assume Marge’s opportunity cost of capital is 12%. Year Project A Project B 0 −$20,000 −$20,000 1 15,000 2,000 2 15,000 2,500 3 13,000 3,000 4 3,000 50,000 Calculate NPV for both projects. Calculate IRR for both projects (Hint: the equation of calculating IRR). Calculate profitability index for both projects. Calculate payback period for both projects. Which business opportunity is better? Use IRRA=54.7%, IRRB=33.3%, cross over point=14.1%. (Hint:...

  • Capital Budgeting: Homework 1. Waste Management has a WACC of 12 percent and it is considering a project with a cost of...

    Capital Budgeting: Homework 1. Waste Management has a WACC of 12 percent and it is considering a project with a cost of $52,125. The project’s expected net cash inflows are $12,000 per year for 8 years. What is the project’s payback period? What is the project’s net present value (NPV)? What is the profitability index? What is the project’s internal rate of return (IRR)? What is the project’s modified internal rate of return (MIRR)?

  • answer using excel If the cost of capital is 12%, which project should be chosen? If...

    answer using excel If the cost of capital is 12%, which project should be chosen? If the cost of capital is 18% which project should be chosen? a) To determine the answer to this above questions you are to calculate the NPV of each project using a required rate of return of 12% and then a required rate of return of 18%. Then construct the NPV profiles for Project A and Project B. (Note: plot the NPVs of both projects...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT