A remote small mining town in Africa with a population of some 5600 residents is supplied...

A remote small mining town in Africa with a population of some 5600 residents is supplied with
electricity from a diesel power plant with a peak demand of 5 MW.

The mine engineer has identified a possible alternative supply in the form a Run-of-River (RoR)
hydroelectric plant which would be installed in the hills some 25 km from the town.

Assume the power to the town will be transmitted via an overhead line from the Run-of-River (RoR) hydroelectric plant with the following
parameters:

R = 0.16 Ω/km;

XL = 0.24 Ω/km;

length = 25 km

Receiving end voltage 22 kV and load at pf = 0.8 lagging. Taking the receiving end voltage as the
reference phasor i.e. VR ∠ 0º, calculate

a) Sending end voltage
b) % regulation
c) Line losses
d) Transmission efficiency
e) Draw single phase phasor diagram
f) Draw a simple line diagram of the town sub-station.

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
A remote small mining town in Africa with a population of some 5600 residents is supplied...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT