Question

IT Project Management: Chapter 13 Project Stakeholder Management 1. One of the main outputs of the...

IT Project Management: Chapter 13 Project Stakeholder Management

1. One of the main outputs of the _____ process are the issue logs.

a. Controlling stakeholder engagement

b. Planning stakeholder management

c. Identifying stakeholders

d. Managing stakeholder engagement

2.  The project team must take corrective action if stakeholders with high interest and high power are categorized as _____.

a. leading

b. neutral

c. supportive

d. resistant

3. After identifying and analyzing stakeholders, the project manager and team should develop a(n) ______ to help them effectively engage stakeholders and make sure that good decisions are made throughout the life of the project.

a. stakeholder management plan

b. issue log

c. stakeholder register

d. power/ interest grid

4. Doctors who have been co-opted to actively participate in a project related to using information technology for chronic health problems would be examples of _____ stakeholders.

a. supportive

b. neutral

c. leading

d. resistant

5. Key stakeholders need not be invited to participate in a kick-off meeting.

True or False

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)  Managing stakeholder engagement
2)  resistant
3)  stakeholder management plan
4)  leading
5)  False
Add a comment
Know the answer?
Add Answer to:
IT Project Management: Chapter 13 Project Stakeholder Management 1. One of the main outputs of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Based on the Getta Byte team the stakeholder management and communication plans development, complete the files...

    Based on the Getta Byte team the stakeholder management and communication plans development, complete the files linked below with your recommendations. Add frequency and methods of communication to the Stakeholder Management Plan. Add additional forms of communication to specific stakeholders to the Communication Plan. Transcript ====== Before we get started, we need to know who our stakeholder are? I thought stakeholders where vampire Hunters. haha.... get it? Very funny A stakeholder is anyone who is impacted, positively or negatively. By...

  • 1. Mary is a key stakeholder in your company and is part of your Agile project....

    1. Mary is a key stakeholder in your company and is part of your Agile project. She is at a planning meeting and says, “I thought you don’t do formal planning in Agile.” You respond: Select one: a. We plan project, but we keep the focus on immediate items and we value working software over comprehensive documentation b. We plan as other projects do and incorporate stakeholder considerations into the planning to produce working software at the end c. Normally...

  • IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the...

    IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the basis for contract awards and performance reporting, it should be a ____ and as accurate as possible. a. budgetary estimate b. definitive estimate c. rough order of magnitude estimate d. final estimate 2. The main outputs of the ____________________ process are activity cost estimates, basis of estimates, and project document updates. 3. It’s important for the team to ____________________ assumptions they made when developing...

  • 1) "Once you have identified all of the stakeholders, it is important to determine which group...

    1) "Once you have identified all of the stakeholders, it is important to determine which group of stakeholders holds the most power and which group may have the greatest impact in the overall outcome of the project. " a) true b) false 2) You are leading an international team and you are considering how this might impact your communications and decision making processes as a team. Your goal is to _______________. a) adapt the work processes to cope with the...

  • •Please help develop an overall delivery Process using the below to be in line with Agile project...

    •Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...

  • BSBMGT403_SIC - IMPLEMENT CONTINUOUS IMPROVEMENT Summative assessment 2 (0% completed) Project 1 Senior management in your...

    BSBMGT403_SIC - IMPLEMENT CONTINUOUS IMPROVEMENT Summative assessment 2 (0% completed) Project 1 Senior management in your organisation has identified, as part of the continuous improvement process, a number of improvement activities to be implemented by your team/ division/ section. The improvements will mean some fairly large changes to your work routines and practices. As frontline manager, you are responsible for ensuring that these changes are made and the new targets are met. Unfortunately, one of your team members is very...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

  • Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241...

    Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong...

    Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT