APPLY THE CONCEPTS: Complete the job cost sheets for In the Doghouse Company
In the Doghouse Company builds doghouses. They have three sizes: small, medium and large. Each size can be built in one of two styles, standard or deluxe. All doghouses are built with treated lumber and have shingled roofs. The deluxe model is insulated and has a covered porch. In the Doghouse sells mostly to local hardware and garden stores.
The costs for direct materials and direct labor for each type of doghouse are shown in the table below. The direct materials cost includes costs for lumber, shingles, stain or paint, and insulation. Nails and glue are also used in the construction and are considered indirect materials which make them part of overhead. The company employs two carpenters and a part-time student to maintain the equipment and clean the shop. The carpenters' wages are direct labor. The student's wages are indirect labor and, therefore, part of overhead. Other overhead costs include depreciation of equipment and the building, insurance, utilities, and taxes. Overhead is applied at 10% of direct labor cost. In the Doghouse summarizes costs by direct materials, direct labor, and overhead on its job cost sheets.
Direct Materials |
Direct Labor |
|
Standard: | ||
Small | $64 | $60 |
Medium | 111 | 90 |
Large | 135 | 150 |
Deluxe: | ||
Small | $78 | $120 |
Medium | 152 | 180 |
Large | 256 | 240 |
At the beginning of August, the company has one job, job number 706, in progress from the previous month. This job is for an order of 16 large, standard doghouses. As of August 1, $432.00 of direct materials have been used, $480.00 of direct labor have been charged to the job and $48.00 of overhead was applied to the job. Click on the link below to get more detail on job number 706.
During August, In the Doghouse received an order for 20 medium, standard doghouses. This is job number 801 and was completed by the end of the month.
Another order was received during the month, job 802, for 12 small, deluxe doghouses. At the end of August, job 802 was still in process. $561.6 of direct materials has been used, $864 of direct labor has been charged to the job, and overhead was applied to job 802 using the predetermined overhead rate of 10% of direct labor cost.
Complete the following job cost sheets for the month of August In the Doghouse and answer the following questions.
Job 706 | ||
16 large, standard doghouses | ||
Direct materials | $ | |
Direct labor | ||
Overhead | ||
Total job cost | $ |
Job 801 | ||
20 medium, standard doghouses | ||
Direct materials | $ | |
Direct labor | ||
Overhead | ||
Total job cost | $ |
Job 802 | ||
12 small, deluxe doghouses | ||
Direct materials | $ | |
Direct labor | ||
Overhead | ||
Total job cost | $ |
What is the balance in Work in Process on August 1? $
What is the balance in Work in Process on August 31? $
Think outside the box:
What element would most likely be missing from a job cost sheet for a service organization? Direct materials
+ Job number 706 Job number 706: The following job cost sheet was prepared at the end of the previous month and shows the direct materials, direct labor, and overhead costs as of the end of the month. When the job is completed in August, the amounts should show the totals for direct materials, direct labor, and overhead.
|
Job 706 | ||||
16 large, standard doghouses | working | |||
Total | Beg Inventory | Cost added | ||
Direct materials (16*135) | 2160 | $432 | $1,728 | |
Direct labor (150*16) | 2400 | 480 | $1,920 | |
Overhead (2400*10%) | 240 | 48 | $192 | |
Total | $4,800 | $960 | $3,840 | |
Job 801 | ||||
20 medium, standard doghouses | ||||
Direct materials (20*111) | 2220 | |||
Direct labor (20*90) | 1800 | |||
Overhead | 180 | |||
Total job cost | 4200 | |||
Job 802 | ||||
12 small, deluxe doghouses | ||||
Direct materials | $561.60 | |||
Direct labor | 864 | |||
Overhead | 86.4 | |||
Total job cost | $1,512.00 | |||
balance in Work in Process on August 1 | $960 | |||
balance in Work in Process on August 31 | $1,512.00 | |||
If any doubt please comment |
APPLY THE CONCEPTS: Complete the job cost sheets for In the Doghouse Company In the Doghouse...
Direct Materials Direct Labor Standard: Small $64 $60 Medium 111 90 Large 135 150 Deluxe: Small $78 $120 Medium 152 180 Large 256 240 At the beginning of September, the company has one job, job number 807, in progress from the previous month. This job is for an order of 12 medium, deluxe doghouses. As of September 1, $729.60 of direct materials have been used, $864.00 of direct labor have been charged to the job and $86.40 of overhead was...
Instructions Amount Descriptions Starting Questions Job-Order Cost Sheets Concluding Questions Instructions Jagit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,770, and Job 94 with a beginning balance of 57,300 Jagjit apples overhead at the rate of $10 per direct labor hour. Direct labor wages average $17 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94...
Please complete part (c)-(f) Sunland Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,200 direct labor $ 14,520, and manufacturing overhead $ 19,360. As of January 1, Job 49 had been completed at a cost of $ 108,900 and was part...
C-F Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods...
5 (az) Post all costs to the job cost sheets as necessary. Job Cost Sheets Job No. 50 Direct Direct Date Materials Labour Beg. $30,500 $15,500 Manufacturing Overhead $20,500 Jan. Job No. 51 Date Direct Materials Direct Labour Manufacturing Overhead Jan. $ $ $ Job No. 52 Date Direct Materials Direct Labour Manufacturing Overhead Jan. SHOW LIST OF ACCOUNTS Help System Announcements Grace Periodi 7 days left Register Now PRINTER VERSION BACK SOURCES LEA 20 Questions Bertrand Manufacturing uses a...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
Job order cost sheets accumulate all of the following costs except for: factory overhead applied indirect materials direct labor direct materials
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. JOD 102 922,000 Diegt materials Direct labor Overhead applied JOB 103 $71,000 27.300 10.920 JOD 104 $55,000 41.000 16.400 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $11.000; direct labor, $3,900; and overhead, $1,560. Jobs 103 and 104 were started in June. Overhead cost...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...