1.
Job 93 | Job 94 | Job 95 | Job 96 | |
Direct Labor | $ 2,380 | $ 5,100 | $ 2,550 | $ 1,020 |
Labor rate per hour | $ 17 | $ 17 | $ 17 | $ 17 |
Labour hours | 140 | 300 | 150 | 60 |
2.
Job 93 | Job 94 | Job 95 | Job 96 | |
Direct Labor | $ 2,380 | $ 5,100 | $ 2,550 | $ 1,020 |
Labor rate per hour | $ 17 | $ 17 | $ 17 | $ 17 |
Labour hours | 140 | 300 | 150 | 60 |
Overhead rate per hour | $ 10 | $ 10 | $ 10 | $ 10 |
Overhead applied | $ 1,400 | $ 3,000 | $ 1,500 | $ 600 |
3.
Job 93 | Job 94 | Job 95 | Job 96 | |
Beginning Balance | $ 8,770 | $ 7,300 | ||
Direct Material | $ 990 | $ 4,530 | $ 3,300 | $ 1,280 |
Direct Labor | $ 2,380 | $ 5,100 | $ 2,550 | $ 1,020 |
Overhead applied | $ 1,400 | $ 3,000 | $ 1,500 | $ 600 |
Total | $ 13,540 | $ 19,930 | $ 7,350 | $ 2,900 |
4.
Work in Process on August 31 = $19930+7350+2900 = $30180
5.
Price of Job 93 = $13540 x 1.4 = $18956
Instructions Amount Descriptions Starting Questions Job-Order Cost Sheets Concluding Questions Instructions Jagit Company designs and builds...
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,770, and Job 94 with a beginning balance of $7,300. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $17 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct materials $990 $4,530 $3,300 $1,280 Direct...
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,800 and Job 94 with a beginning balance of $7,240. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...
please help, cant figure out the wrong ones. thank you so much Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,750 and Job 94 with a beginning balance of $7,300. Jagjit applies overhead at the rate of $8 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs...
Applying Overhead to Jobs, Costing Jobs Instructions Amount Descriptions Job-Order Cost Sheet Calculations and Joo Price Instructions Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18.640 to date. During October, Jobs 878 879 and 880 were started Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,460 $6.000...
help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and Instructions Amount Descriptions Overhead Rate Job-Order Cost Sheets Concluding Questions Instructions Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Balance, July 1 Direct materials Direct labor Machine hours Job 106 $21,310 $10,450 $16,000 500 Job 107 $6,250 $12,300 $12,200 300 Job 108 $0 $16,150 $24,000 1,000 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 106 and 108 were completed. Jobs 102 and 106...
Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...
Instructions Job-Order Cost Sheets, Balance In Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,330 $6,250 $0 Direct materials $10,470 $12,220 $16,070 Direct labor $16,030 $12,200 $23,910 Machine hours 520 280 1,010 Overhead is applied to jobs at the rate of $17 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and...
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications On October 1, Job 877 was in process with a cost of $18.730 to date. During October, Jobs 878,879, and 880 were started Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,550 $6,070 $3,580 $1,380 Direct labor 14.2008,600 1,900 Overhead is applied to production at the rate of 75% of direct...