Answer -
1. Answer -
Gorman Company | ||||
Job-Order Cost Sheet | ||||
For the Month of October | ||||
Job 877 | Job 878 | Job 879 | Job 880 | |
Beginning balance | $18730 | $0 | $0 | $0 |
Direct materials | $14550 | $6070 | $3580 | $1880 |
Direct labor | $14200 | $8600 | $1900 | $2100 |
2. Answer -
The overhead applied to Job 877 is | $10650 |
The overhead applied to Job 878 is | $6450 |
The overhead applied to Job 879 is | $1425 |
The overhead applied to Job 880 is | $1575 |
Calculation:
As per given information,
Overhead is applied to production at the rate of 75% of direct labor cost.
So,
Job 877:
= Direct labor cost * 75%
= $14200 * 75%
= $10650
Job 878:
= Direct labor cost * 75%
= $8600 * 75%
= $6450
Job 879:
= Direct labor cost * 75%
= $1900 * 75%
= $1425
Job 880:
= Direct labor cost * 75%
= $2100 * 75%
= $1575
3. Answer -
The balance in work in process for Job 878 is | $21120 |
The balance in work in process for Job 879 is | $6905 |
The balance in work in process for Job 880 is | $5555 |
The total balance in work in process | $33580 |
Calculation:
Job 878:
Work in Process balance:
= Beginning balance + Direct materials + Direct labor + Overhead applied
= $0 + $6070 + $8600 + $6450
= $21120
Job 879:
Work in Process balance:
= Beginning balance + Direct materials + Direct labor + Overhead applied
= $0 + $3580 + $1900 + $1425
= $6905
Job 880:
Work in Process balance:
= Beginning balance + Direct materials + Direct labor + Overhead applied
= $0 + $1880 + $2100 + $1575
= $5555
The total balance in work in process:
= $21120 + $6905 + $5555
= $33580
4. Answer -
The price of Job 877 is $87195
Calculation:
As per given information,
Client was billed at cost plus 50%
Therefore,
Price = Cost + (Cost * 50%)
So,
Total cost of Job 877:
= Beginning balance + Direct materials + Direct labor + Overhead applied
= $18730 + $14550 + $14200 + $10650
= $58130
Now,
Price = Cost + (Cost * 50%)
= $58130 + ($58130 * 50%)
= $87195
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications On...
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,690 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,380 $5,970 $3,510 $1,770 Direct labor 14,600 8,500 2,200 2,400 Overhead is applied to production at the rate of...
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,690 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,380 $5,970 $3,510 $1,770 Direct labor 14,600 8,500 2,200 2,400 Overhead is applied to production at the rate of...
Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,580 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,480 $6,010 $3,560 $1,710 Direct labor 13,800 8,600 1,700 1,800 Overhead is applied to production at the rate of 85% of direct labor cost. Job...
Applying Overhead to Jobs, Costing Jobs Brebeur Company builds internal conveyor equipment to dient specifications. On October 1, Job 877 was in process with a cost of $29,900 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $23,200 $34,000 $16,400 $7,100 Direct labour 15,200 90,000 1,300 33,500 Overhead is applied to production at the rate of...
Applying Overhead to Jobs, Costing Jobs Instructions Amount Descriptions Job-Order Cost Sheet Calculations and Joo Price Instructions Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18.640 to date. During October, Jobs 878 879 and 880 were started Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,460 $6.000...
If someone could solve this and explain how they did so that would be great. I solved some of it and it was marked mostly incorrect. Thanks, ----------------------------------------------------- Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,690 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job...
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,800 and Job 94 with a beginning balance of $7,240. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...
Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,770, and Job 94 with a beginning balance of $7,300. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $17 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct materials $990 $4,530 $3,300 $1,280 Direct...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...