Question

Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On...

Applying Overhead to Jobs, Costing Jobs

Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,690 to date.

During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows:

Job 877 Job 878 Job 879 Job 880
Direct materials $14,380 $5,970 $3,510 $1,770
Direct labor 14,600 8,500 2,200 2,400

Overhead is applied to production at the rate of 75% of direct labor cost. Job 877 was completed on October 28, and the client was billed at cost plus 50%. All other jobs remained in process.

Required:
1. Prepare a brief job-order cost sheet showing the October 1 balances of all four jobs, plus the direct materials and direct labor costs during October. There is no need to calculate applied overhead at this point or to total the costs.
2. Calculate the overhead applied to each job during October.
3. Calculate the balance in Work in Process on October 31.
4. What is the price of Job 877?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part 1

Job 877

Job 878

Job 879

Job 880

Beginning balance

18690

Direct materials

14380

5970

3510

1770

Direct labor

14600

8500

2200

2400

Part 2

Applied overhead in October for:

Job 877 = $14,600 × 0.75 = $10,950

Job 878 = $8,500 × 0.75 = $6,375

Job 879 = $2,200 × 0.75 = $1,650

Job 880 = $2,400 × 0.75 = $1,800

Part 3

Work in Process, October 31:

Job 878 (5970+8500+6375)

$20845

Job 879 (3510+2200+1650)

$7360

Job 880 (1770+2400+1800)

$5970

Total

$34175

Part 4

Cost of Job 877 = 18690+14380+14600+10950 = $58620

Price of Job 877 = 58620+(58620*0.50) = $87930

Add a comment
Know the answer?
Add Answer to:
Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On...

    Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,690 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,380 $5,970 $3,510 $1,770 Direct labor 14,600 8,500 2,200 2,400 Overhead is applied to production at the rate of...

  • Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications On...

    Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications On October 1, Job 877 was in process with a cost of $18.730 to date. During October, Jobs 878,879, and 880 were started Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,550 $6,070 $3,580 $1,380 Direct labor 14.2008,600 1,900 Overhead is applied to production at the rate of 75% of direct...

  • Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in...

    Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,580 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,480 $6,010 $3,560 $1,710 Direct labor 13,800 8,600 1,700 1,800 Overhead is applied to production at the rate of 85% of direct labor cost. Job...

  • Applying Overhead to Jobs, Costing Jobs Brebeur Company builds internal conveyor equipment to dient specifications. On...

    Applying Overhead to Jobs, Costing Jobs Brebeur Company builds internal conveyor equipment to dient specifications. On October 1, Job 877 was in process with a cost of $29,900 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $23,200 $34,000 $16,400 $7,100 Direct labour 15,200 90,000 1,300 33,500 Overhead is applied to production at the rate of...

  • If someone could solve this and explain how they did so that would be great. I...

    If someone could solve this and explain how they did so that would be great. I solved some of it and it was marked mostly incorrect. Thanks, ----------------------------------------------------- Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,690 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job...

  • Applying Overhead to Jobs, Costing Jobs Instructions Amount Descriptions Job-Order Cost Sheet Calculations and Joo Price...

    Applying Overhead to Jobs, Costing Jobs Instructions Amount Descriptions Job-Order Cost Sheet Calculations and Joo Price Instructions Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18.640 to date. During October, Jobs 878 879 and 880 were started Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,460 $6.000...

  • Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....

    Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,800 and Job 94 with a beginning balance of $7,240. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: beginning work in process Job #1-A $3,250 Job #3-G $2,690 Job #7-L $3,720 COSTS ADDED DURING JUNE: direct materials direct labor ..... $4,680 3,530 $3,950 4,180 $2,870 2,410 During June,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT