Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....

Applying Overhead to Jobs, Costing Jobs

Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,800 and Job 94 with a beginning balance of $7,240. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows:

Job 93 Job 94 Job 95 Job 96
Direct materials $930 $4,520 $3,400 $1,260
Direct labor cost 2,240 4,800 1,920 960

During August, Jobs 95 and 96 were started. Job 93 was completed on August 17, and the client was billed at cost plus 40%. All other jobs remained in process.

Required:

1. Calculate the number of direct labor hours that were worked on each job in August.

Job 93 DLH
Job 94 DLH
Job 95 DLH
Job 96 DLH

2. Calculate the overhead applied to each job during the month of August.

Job 93 $
Job 94 $
Job 95 $
Job 96 $

Feedback

1. For each job divide the labor cost by the labor rate.

2. Multiply the applied overhead rate by the labor hours for each job.

3. Prepare job-order cost sheets for each job as of the end of August. All amount cells must have an entry; enter zeros as needed.

Jagjit Company
Job-Order Cost Sheets
August 31
Job 93 Job 94 Job 95 Job 96
Beginning balance $ $ $ $
Direct materials
Direct labor
Applied overhead
Total $ $ $ $

Feedback

Incorrect

4. Calculate the balance in Work in Process on August 31.
The work in process balance on August 31 is $.

5. What is the price of Job 93?
The price of Job 93 is $.

6. CONCEPTUAL CONNECTION: Part way through the year, Jagjit bought a bulldozer to handle larger jobs. The bulldozer cost $38,500 and is needed for larger commercial jobs. Smaller residential jobs can still be done with the smaller bobcat tractor.

Complete the statement below that outlines how the bulldozer’s cost could be applied to only those jobs that need the larger equipment.

Create a separate department  for the acquisition and use of the bulldozer. Treat the bulldozer’s depreciation, fuel, maintenance, etc. as total budgeted cost . Divide this by the anticipated annual hours of use to arrive at the overhead rate .

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

The answer has been presented in the supporting sheet. First 4 parts has been solved with detailed explanation and calculation. For detailed answer refer to the supporting sheet.

Answer 2 Part 1) 3 The number of direct Labour Hours 4 Job 93 140 (2240/16) 6 Job 94 300 (4800/16) 8 Job 95 (1920/16) 10 Job

28 24 Part 3) 25 Jagjit Company 26 Job order Cost Sheet 27 Aug-31 Job 93 Job 94 Job 95 Job 96 29 Beginning 8800 7240 30 Direc

Add a comment
Know the answer?
Add Answer to:
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two...

    Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,770, and Job 94 with a beginning balance of $7,300. Jagjit applies overhead at the rate of $10 per direct labor hour. Direct labor wages average $17 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct materials $990 $4,530 $3,300 $1,280 Direct...

  • Instructions Amount Descriptions Starting Questions Job-Order Cost Sheets Concluding Questions Instructions Jagit Company designs and builds...

    Instructions Amount Descriptions Starting Questions Job-Order Cost Sheets Concluding Questions Instructions Jagit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,770, and Job 94 with a beginning balance of 57,300 Jagjit apples overhead at the rate of $10 per direct labor hour. Direct labor wages average $17 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94...

  • please help, cant figure out the wrong ones. thank you so much Applying Overhead to Jobs,...

    please help, cant figure out the wrong ones. thank you so much Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,750 and Job 94 with a beginning balance of $7,300. Jagjit applies overhead at the rate of $8 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs...

  • Angry Birds, Inc. designs and builds retaining walls for individual customers. On August 1, 2 jobs...

    Angry Birds, Inc. designs and builds retaining walls for individual customers. On August 1, 2 jobs were in process: Level 1 with a beginning balance of $12,000 and Level 2 with a beginning balance of $8,600. During August, Level 3 and Level 4 were started. Levels 1 and 2 were sold at cost plus 30% during August. All other jobs remained in process at month end. The company applies manufacturing overhead at a rate of $9 per direct labor hour....

  • Angry​ Birds, Inc. designs and builds retaining walls for individual customers. On August​ 1, 2 jobs...

    Angry​ Birds, Inc. designs and builds retaining walls for individual customers. On August​ 1, 2 jobs were in​ process: Level 1 with a beginning balance of​ $12,000 and Level 2 with a beginning balance of​ $8,600. During​ August, Level 3 and Level 4 were started. Levels 1 and 2 were sold at cost plus 30% during August. All other jobs remained in process at month end. The company applies manufacturing overhead at a rate of ​$9 per direct labor hour....

  • Angry​ Birds, Inc. designs and builds retaining walls for individual customers. On August​ 1, 2 jobs...

    Angry​ Birds, Inc. designs and builds retaining walls for individual customers. On August​ 1, 2 jobs were in​ process: Level 1 with a beginning balance of​ $12,000 and Level 2 with a beginning balance of​ $8,600. During​ August, Level 3 and Level 4 were started. Levels 1 and 2 were sold at cost plus 30​% during August. All other jobs remained in process at month end. The company applies manufacturing overhead at a rate of ​$9 per direct labor hour....

  • Angry Birds, Inc. designs and builds retaining walls for individual customers. On August 1, 2 jobs...

    Angry Birds, Inc. designs and builds retaining walls for individual customers. On August 1, 2 jobs were in process: Level 1 with a beginning balance of $12,000 and Level 2 with a beginning balance of $8,600. During August, Level 3 and Level 4 were started. Levels 1 and 2 were sold at cost plus 30% during August. All other jobs remained in process at month end. The company applies manufacturing overhead at a rate of $11 per direct labor hour....

  • Angry Birds, Inc. designs and builds retaining walls for individual customers. On August 1, 2 jobs...

    Angry Birds, Inc. designs and builds retaining walls for individual customers. On August 1, 2 jobs were in process: Level 1 with a beginning balance of $12,000 and Level 2 with a beginning balance of $8,600. During August, Level 3 and Level 4 were started. Levels 1 and 2 were sold at cost plus 30% during August. All other jobs remained in process at month end. The company applies manufacturing overhead at a rate of $9 per direct labor hour....

  • Angry​ Birds, Inc. designs and builds retaining walls for individual customers. On August​ 1, 2 jobs...

    Angry​ Birds, Inc. designs and builds retaining walls for individual customers. On August​ 1, 2 jobs were in​ process: Level 1 with a beginning balance of​ $12,000 and Level 2 with a beginning balance of​ $8,600. During​ August, Level 3 and Level 4 were started. Levels 1 and 2 were sold at cost plus 40​% during August. All other jobs remained in process at month end. The company applies manufacturing overhead at a rate of ​$9 per direct labor hour....

  • Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications On...

    Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications On October 1, Job 877 was in process with a cost of $18.730 to date. During October, Jobs 878,879, and 880 were started Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,550 $6,070 $3,580 $1,380 Direct labor 14.2008,600 1,900 Overhead is applied to production at the rate of 75% of direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT