Instructions Job-Order Cost Sheets, Balance In Work in Process and Finished Goods Prull Company, a job-order costing firm, wo
Job-Order Cost Sheets 1. Prepare job-order cost sheets for all jobs in process during July, showing all costs through July 31
Balances and Calculations 2. Calculate the balance in Work in Process on July 31. The balance in Work in Process on July 31 i
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Prull
Workings for Answer 1 Job 86 Job 87 Job 88
Machine hours           520.00           280.00        1,010.00
Overhead absorption rate             17.00             17.00             17.00
Overhead applied        8,840.00        4,760.00     17,170.00
Answer 1 Job 86 Job 87 Job 88
Balance, July 1      21,330.00        6,250.00                    -  
Direct material      10,470.00      12,220.00      16,070.00
Direct labor      16,030.00      12,200.00      23,910.00
Overhead applied        8,840.00        4,760.00      17,170.00
Total     56,670.00     35,430.00     57,150.00
Answer 2 Amount $
Cost of Job 87      35,430.00
Work in process on July 31     35,430.00
Answer 3 Amount $
Cost of Job 84      23,430.00
Cost of Job 88      57,150.00
Finished goods on July 31     80,580.00
Answer 4 Amount $
Cost of Job 82      25,560.00
Cost of Job 86      56,670.00
Cost of goods sold in July     82,230.00
Answer 5 Job 82 Job 86 Total
Cost of Job      25,560.00      56,670.00     82,230.00
Markup at 30%        7,668.00     17,001.00     24,669.00
Sale value     33,228.00     73,671.00 106,899.00
Less: Cost of goods sold      25,560.00      56,670.00     82,230.00
Gross margin        7,668.00     17,001.00     24,669.00
Less: Expenses
Marketing expense at 5 %        1,661.00        3,684.00        5,345.00
Fixed Marketing expense        1,960.00
Admin expense        4,800.00
Total Expenses     12,105.00
Operating Income     12,564.00
Add a comment
Know the answer?
Add Answer to:
Instructions Job-Order Cost Sheets, Balance In Work in Process and Finished Goods Prull Company, a job-order...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing...

    Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...

  • Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing...

    Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $15,310 $4,250 $0 Direct materials $4,450 $10,300 $13,150 Direct labor $16,000 $12,200 $24,000 Machine hours 500 300 1,000 Overhead is applied to jobs at the rate of $10 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...

  • Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing...

    Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...

  • Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing...

    Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Balance, July 1 Direct materials Direct labor Machine hours Job 106 $21,310 $10,450 $16,000 500 Job 107 $6,250 $12,300 $12,200 300 Job 108 $0 $16,150 $24,000 1,000 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 106 and 108 were completed. Jobs 102 and 106...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Donewell Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,000 $1,800 Direct labour 4,400 3,520 Applied overhead 3,800 3,040 Balance, June 1 $13,200 $8,360 During June, two more jobs (46 and 47) were started. The following direct materials and direct labour costs were added to...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,300 $1,300 Direct labor 1,400 3,100 Applied overhead 980 2,170 Balance, June 1 $7,680 $6,570 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...

  • Balance of Work in Process and Finished Goods, Cost of Goods Sold Derry Company uses job-order...

    Balance of Work in Process and Finished Goods, Cost of Goods Sold Derry Company uses job-order costing. At the end of the month, the following information was gathered: Job Total Cost Complete? Sold? 301 $1,600 1,270 890 2.170 560 The beginning balance of Finished Goods was $570, consisting of Job 300, which was not sold by the end of the month. Required: 1. Calculate the balance in Work in Process at the end of the month Cathahalin nicht andet that...

  • help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets,...

    help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and Instructions Amount Descriptions Overhead Rate Job-Order Cost Sheets Concluding Questions Instructions Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT