Answer:-
Job | Total Cost | Complete? | Sold? |
Work-in-Process (If work is not complete and not sold then the Job is treated as work in progress) |
Finished Goods Inventory (If Job is complete but Not sold then that Job comes under Finished good Inventory) |
Cost of Goods Sold (If Job is Complete and sold than that Job Cost comes under Cost of good sold) |
Explanation |
---|---|---|---|---|---|---|---|
301 | $1,600 | Yes | No | $1,600 |
Job 301 is complete but Not sold.Then it includes in Finished good Inventory. |
||
302 | 1,270 | Yes | Yes | $1,270 |
Job 302 is complete and sold then it includes in Cost of good sold. |
||
303 | 890 | No | No | $890 |
Job 303 is not complete and sold so it includes in work in progress |
||
304 | 2,170 | Yes | No | $2,170 |
Job 304 is complete but Not sold.Then it includes in Finished good Inventory. |
||
305 | 4,090 | Yes | No | $4,090 |
Job 305 is complete but Not sold.Then it includes in Finished good Inventory. |
||
306 | 410 | No | No | $410 |
Job 306 is not complete and sold so it includes in work in progress |
||
307 | 670 | Yes | Yes | $670 |
Job 307 is complete and sold then it includes in Cost of good sold |
||
308 | 610 | No | No | $610 |
Job 308 is not complete and sold so it includes in work in progress |
||
309 | 1,270 | No | No | $1,200 |
Job 309 is not complete and sold so it includes in work in progress |
||
310 | 560 | No | No | $515 |
Job 310 is not complete and sold so it includes in work in progress |
||
$13,540 | $3,625 | $7,860 |
$1,940 |
The balance in Work in progress is $ 3,625
The balance in Finished good Inventory is ($ 7,860 + $570 Beginning balance of Job 300) = $8,430
The balance in Cost of good sold is $ 1,940
Balance of Work in Process and Finished Goods, Cost of Goods Sold Derry Company uses job-order...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Instructions Job-Order Cost Sheets, Balance In Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,330 $6,250 $0 Direct materials $10,470 $12,220 $16,070 Direct labor $16,030 $12,200 $23,910 Machine hours 520 280 1,010 Overhead is applied to jobs at the rate of $17 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $15,310 $4,250 $0 Direct materials $4,450 $10,300 $13,150 Direct labor $16,000 $12,200 $24,000 Machine hours 500 300 1,000 Overhead is applied to jobs at the rate of $10 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Balance, July 1 Direct materials Direct labor Machine hours Job 106 $21,310 $10,450 $16,000 500 Job 107 $6,250 $12,300 $12,200 300 Job 108 $0 $16,150 $24,000 1,000 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 106 and 108 were completed. Jobs 102 and 106...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
help please. theres a lot of pictures, but it is 1 problem. Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and Instructions Amount Descriptions Overhead Rate Job-Order Cost Sheets Concluding Questions Instructions Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
Appendix 4A) Journal Entries, T-Accounts structions Chart of Accounts Amount Descriptions Instructions Lowder Inc. builds custom conveyor systems for warehouses and distribution centers. During the month of July, the following occurred Ju 2 28 Purchased materials on account for $42.630 Requisitioned materials totaling $27.000 for use in production: $12.500 for Job 703 and the remainder for Job 704 Recorded direct labor payroll for the month of $26,320 with an average wage of 14 per hour, Job 703 required 780 direct...
eBook Calculator (Appendix 4A) Journal Entries, T-Accounts Instructions Chart of Accounts Amount Descriptions Jouma I Job-Order Cost Sheets Instructions Lowder Inc, builds custom conveyor systems for warehouses and distribution centers. During the month of July, the following occurred: Jul 1 2 Purchased materials on account for $42,630. Requisitioned materials totaling $27,000 for use in production: $12.500 for Job 703 and the remainder for Job 704. 28 Recorded direct labor payroll for the month of $26,320 with an average wage of...
Instructions Hayward Company, a manufacturing firm, has supplied the following information from its accounting records for the month of May $10,500 Direct labor cost Purchases of raw materials 15,000 Supplies used Factory Insurance 350 Commissions paid 2,500 Factory supervision Advertising Material handing Materials inventory, May 1 Work-in-process inventory, May 1 Finished goods inventory, May 1 Materials inventory, May 31 Work-in-process inventory, May 31 Finished goods inventory, May 31 Factory insurance Previous Next > Check My Work 5 more Check My...