1) | Job 106 | Job 107 | Job 108 | ||||
Beginning balance | 21,310 | 6,250 | 0 | ||||
Direct Materials | 10,450 | 12,300 | 16,150 | ||||
Direct labor | 16,000 | 12,200 | 24,000 | ||||
Applied overhead | 8000 | 4800 | 16000 | ||||
total | 55,760 | 35,550 | 56150 | ||||
2) | the balance in Work in process on July 31 | 35,550 | |||||
Work in process | |||||||
opening | 27,560 | Finished | 111,910 | ||||
DM | 38,900 | ||||||
DL | 52,200 | ||||||
OH | 28800 | ||||||
End bal | 35,550 | ||||||
3) | finished goods on July 31 is | 79,550 | |||||
Finished goods | |||||||
opening | 49,000 | COGS | 81,360 | (job 102&106) | |||
WIP | 111,910 | ||||||
End bal | 79,550 | ||||||
4) | the cost of goods sold for july is | 81,360 | |||||
5) | the operating income for the month of july is | 13,540 | |||||
sales | (81360*130%)= | 105768 | |||||
cost of goods sold | 81,360 | ||||||
Gross profit | 24,408 | ||||||
operating expense | |||||||
marketing exp | 4068 | ||||||
Adm expense | 4,800 | ||||||
fixed marketing expense | 2,000 | ||||||
operating income | 13,540 | ||||||
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $15,310 $4,250 $0 Direct materials $4,450 $10,300 $13,150 Direct labor $16,000 $12,200 $24,000 Machine hours 500 300 1,000 Overhead is applied to jobs at the rate of $10 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Instructions Job-Order Cost Sheets, Balance In Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,330 $6,250 $0 Direct materials $10,470 $12,220 $16,070 Direct labor $16,030 $12,200 $23,910 Machine hours 520 280 1,010 Overhead is applied to jobs at the rate of $17 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,100 $1,500 Direct labor 1,200 3,000 Applied overhead 780 1.950 Balance, June 1 $7,080 $6,450 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,300 $1,300 Direct labor 1,400 3,100 Applied overhead 980 2,170 Balance, June 1 $7,680 $6,570 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
Amount De Cost Sheets structions Yurman Inc uses a job-order costing system. During the month of May, the following transactions occurred May Purchased materials on account for $29.670. Requisitioned materials totaling S24 500 for use in production of the total 59.200 was for Job 58 $8.900 for Job 59, and the remainder for Job 60 Incurred direct labor for the month of $32.400 with an average wage of $18 per hour. Job 58 used 800 hours Job 59, 600 hours...
Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...