Question

Decision Variables: B= # of external modems to be produced, profit=$40/unit P= # of internal modems...

Decision Variables:

B= # of external modems to be produced, profit=$40/unit

P= # of internal modems to be produced, profit=$120/unit

Objective: MaxTotal Profit= Max $40 B + $120 P                  

Constraints:                       

Software Engineer (SE):     20 B + 5 P                             <= 2400 minutes               

QC Manager:                       15 B + 30 P                         <= 2400 minutes               

Demand for B:                    B                                           <= 100   units                    

Demand for P:                    P                                           <= 50     units

QC is the Bottleneck. P is the preferred product since $120/30 > $40/15

Optimal production quantities: B=60, P=50.

Questions:

1. True/False - Allowable Increase in profit for B is $20.

2. True/False - Allowable decrease for profit per unit of P is $40

3. True/False - QC Manager SP: $4 per min

4. True/False - Demand for P:
SP: $120 per unit

5. If:

Software Engineer (SE):     20 B + 5 P                             <= 2010 minutes               

QC Manager:                       15 B + 30 P                         <= 4000 minutes  

Then: True/False - Demand for P:
SP: $110 per unit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We have to find the Allowable increases for profit per unit of B, allowable decrease for profit per unit of P, Shadow Price for QC manager and Shadow price for Demand of P. In order to find above parameters, we solve the given problem using the Excel solver and generate a sensitivity report.

The solution is as shown. This is solved using excel solver.

We generate a sensitivity report as shown below. The sensitivity report is generated by clicking on the sensitivity section in Excel solver output window and then clicking OK as shown below:

The sensitivity report extract is shown below:

As seen from the above 2 tables:

1. The Profit for B is in Cell B2. Against B2 in the above sensitivity table, the Allowable Increase is given as 20.

Hence, the statement is given in the question; Allowable Increase for profit per unit of B is $20, is correct

Answer: True

2. The Profit for P is in Cell B3. Against B3 in the above sensitivity table, the Allowable decrease is given as 40.

Hence, the statement is given in the question, Allowable decrease for profit per unit of P is $40 is correct

Answer: True

3. The Constraint for QC manager is in Cell B10. Against B10 in the above sensitivity table, the Shadow price is given as 2.667.

Hence, the statement is given in the question, QC Manager SP: $4 per min is incorrect

Answer: False

4. The Constraint for Demand of P is in Cell B12. Against B12 in the above sensitivity table, the Shadow price is given as 40.

Hence, the statement is given in the question, Demand for P SP: $120 per unit is incorrect

Answer: False

Now, if the Constraints are changed,

The solution is as shown. This is solved using excel solver.

The revised sensitivity report extract is shown below:

As seen from the above 2 tables, the Constraint for Demand for P is in Cell B12. Against B12, the shadow price is given as 110.

Hence, the statement given in the question, Demand for SP = $110 per unit is correct

5. Answer: True.

__________________________________________________________________________________________________

In case of any doubt, please ask through comment section before Upvote / downvote.

Kindly rate the answer as it will be encouraging for me to keep answering further questions!!!

Add a comment
Know the answer?
Add Answer to:
Decision Variables: B= # of external modems to be produced, profit=$40/unit P= # of internal modems...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Decision Variables: B= # of Basic models to be produced, profits$45/unit P= # of Premium models t...

    Decision Variables: B= # of Basic models to be produced, profits$45/unit P= # of Premium models to be produced, profit-$120/unit Objective: MaxTotal Profit Max $45 B $120 P Constraints: Software Engineer (SE): 20 B5 P QC Manager: Demand for B: Demand for P: Preferred product is: a)B b)P c)QC Manager d) SE e)none of these <= 2400 minutes 15 B+30 P 2400 minutes <=100 units <= 50 units Decision Variables: B= # of Basic models to be produced, profits$45/unit P=...

  • Decision Variables: B= # of Basic models to be produced, profit=$45/unit P= # of Premium models...

    Decision Variables: B= # of Basic models to be produced, profit=$45/unit P= # of Premium models to be produced, profit=$120/unit Objective: MaxTotal Profit= Max $45 B + $120 P Constraints: Software Engineer (SE): 20 B + 5 P <= 2400 minutes QC Manager: 15 B + 30 P <= 2400 minutes Demand for B: B <= 100 units Demand for P: P <= 50 units. Optimal production quantities are: a) B=100 & P=50 b) B=50 & P=60 c)B=60 & P=50...

  • Q1: Decision Variables:             ...

    Q1: Decision Variables:                B= # of Basic models to be produced, profit=$45/unit P= # of Premium models to be produced, profit=$120/unit Objective: MaxTotal Profit= Max $45 B + $120 P                   Constraints:                        Software Engineer (SE):     20 B + 5 P                             <= 2400 minutes                QC Manager:                       15 B + 30 P                         <= 2400 minutes                Demand for B:                    B                                           <= 100   units                     Demand for P:                    P                                           <= 50     units QUESTION 5 Refer to the data given in Q1. Shadow Price for “Demand for...

  • MaxTotal Revenue= Max $45 B + $120 P +$89 V Software Engineer (SE) 20 B+5 P + 40 V QC Manager: De...

    MaxTotal Revenue= Max $45 B + $120 P +$89 V Software Engineer (SE) 20 B+5 P + 40 V QC Manager: Demand for B: Demand for P: = 1400 minutes < 4000 minutes <- 60 units <-100 units 15 B 30 P 35 V Objective Cell (Max) Cell Name Original Value Final Value SF$3 Objective 254 14025 Variable Cells Cell $C$3 # Produced Basic $D$3 # Produced Premium SE$3 |# Produced Video Name Original Value Final Value 45 100 0...

  • MaxTotal Revenue Max $45 B $120 P +$89 V Software Engineer (SE) 20 B+5P 40 V QC Manager: Demand f...

    MaxTotal Revenue Max $45 B $120 P +$89 V Software Engineer (SE) 20 B+5P 40 V QC Manager: Demand for B Demand for P: 1400 minutes 15 B 30 P + 35 V 4000 minutes 60 units <100 units Objective Cell (Max) Cell Name Original Value Final Value SF$3 Objective 254 14025 Variable Cells Cell $C$3 |# Produced Basic $DS3 |# Produced Premium SES3 Produced Video Name Original Value Final Value 1 1 1 45 100 0 Integer Contin Contin...

  • Q.1: “Marginal Cost” for B is: a) $45 b) $0 c) -$1 d) none of these Q.2: “Marginal Cost for V is:...

    Q.1: “Marginal Cost” for B is: a) $45 b) $0 c) -$1 d) none of these Q.2: “Marginal Cost for V is: a) -$1 b) $1 c) $0 d) none of these Q.3: If you were asked to produce V, the lowest price for V that is acceptable to you: a) $46 b) $91 c)$88 d) $87 Q.4: Suppose the SE is available for only 1000 min. Then Objective Function Value, OFV = $13125 a) True b)False Q.5: Suppose the...

  • 1 . Product A has a unit profit of $40 and takes 10 minutes on the...

    1 . Product A has a unit profit of $40 and takes 10 minutes on the bottleneck; Product B has unit profit of $60 and takes 30 minutes on the bottleneck. Non-bottleneck operations have infinite capacity because capacity can be added at no cost. The bottleneck has a capacity of 24 hours in a day. Should I maximize feasible production of: a. Product A b. Product B   2In terms of setting up a safety program, Heinrich’s Safety Triangle states the...

  • Question 9 Figure 15-10 Price and cost per unit Po MC P, P2 P3 Demand MR...

    Question 9 Figure 15-10 Price and cost per unit Po MC P, P2 P3 Demand MR Quantity Refer to Figure 15-10. The deadweight loss due to a monopoly is represented by the area GEH. FGE. O FQ1 Q2E. FHE. Question 10 Table 15-1 Quantity Demanded (units) Total Cost of Production (dollars) $530 Price per Unit 10 $85 540 80 75 11 550 12 560 13 70 65 575 14 595 15 60 625 16 55 A monopoly producer of foreign...

  • 1 2 12 1 14 Performance Cooling Inc. manufactures air conditioners for home use and they...

    1 2 12 1 14 Performance Cooling Inc. manufactures air conditioners for home use and they currently have three models serving this market: (1) the essential model, (2) the comfort model, and (3) the majestic model. The units sell for reasonable prices and bring in a profit of $63, 995, and $135 respectively. Currently, the resources required for production of each unit is given in the table below. Fans Cooling Coils Assembly Time (hr) Essential 8 Comfort Majestic In Stock/Available...

  • Activity 2 $40 A ctivity 3 $30 Activ ity 1 $20 Unit Profit Totals 400 100...

    Activity 2 $40 A ctivity 3 $30 Activ ity 1 $20 Unit Profit Totals 400 100 200 Available Resource Resource Used per Unit Produced 3 400 <= 2 1 100 3 200 Total Cost $3,000 Activ ity 1 A ctivity 3 Activity 2 Units Produced 10 50 50 Where are the output cells located? Multiple Choice B10:D10 G10 E5:E7 B2:D2, B4:D7, and G5:G7 B2:D2 Jolulolol

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT