Question

The following data for the Fufkin Company pertain to the produc­tion of 3,000 clay pigeons during...

The following data for the Fufkin Company pertain to the produc­tion of 3,000 clay pigeons during July: Standard variable-overhead cost was $5.00 per pound of clay. The actual variable-overhead cost was $11,340. Standard variable-overhead cost allowed for units produced was $12,000. Variable-overhead efficiency variance was $340 unfavorable. _____ is the variable-overhead rate variance.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Variable overhead efficiency variance = (Standard hour-actual hour)Standard rate

-340 = (12000-5X)

5X = 12340

X(actual hour) = 2468 Hour

Variable overhead rate variance = (5*2468-11340)= 1000 F

So answer is $1000 F

Add a comment
Know the answer?
Add Answer to:
The following data for the Fufkin Company pertain to the produc­tion of 3,000 clay pigeons during...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Elixer Corporation planned to produce 10,000 units. Processing required 15,000 machine hours at a cost of...

    Elixer Corporation planned to produce 10,000 units. Processing required 15,000 machine hours at a cost of $14,000 + $10.00 per machine hour. Actual sales were 14,000 units requiring 20,000 machine hours. Actual processing cost was $222,000. _____ is the static-budget variance for processing. Group of answer choices $39,000 unfavorable $58,000 favorable $39,000 favorable $58,000 unfavorable The following data for the Alpha Beta Company pertain to the produc­tion of 3,000 clay pigeons during July: Standard variable-overhead cost was $5.00 per pound...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used) Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the direct manufacturing labour...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the total direct materials...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the standard direct material...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $2.00 per kilogram of clay Total actual cost: $10,640 Standard cost allowed for units produced was $12,000 Materials quantity variance was $800 favourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 1028 hours show all steps! a. What is...

  • Prob 12 3 C rate is Sz0.00 13) Machine-hours Fixed overhead cos fixed overhead data pertain...

    Prob 12 3 C rate is Sz0.00 13) Machine-hours Fixed overhead cos fixed overhead data pertain to Ma kits for horses during March. The What is the a th flexible-budget variance for variable manufacturing overhead? Required5500 ofa,бrable B)KA300 favorable None of these answers is correct. unfav but not the 55.500 unfavorable The 1Jenny's Corporation manufactured 25,000 grooming kits for horses d d C ch. The fixed-Merhead cost-allocation rate is $20.00 per machine-hour. The following fixed overhead data pertain to Actual...

  • Computation of Variances and Other Missing Data

    The following data for Bernie Company pertain to the production of 1,000 units of Product X during December. Selected data items are omitted.  Fill in the missing amounts.Direct materials (all materials purchased were used during period)Standard cost per unit: Answer pounds at $3.20 per poundTotal actual cost: Answer pounds costing $10,626Standard cost allowed for units produced: $9,600Materials price variance: $AnswerAnswerFUMaterials quantity variance: $704 UDirect laborStandard cost: 2.5 hours at $12.00Actual cost per hour: $12.25Total actual cost: $AnswerLabor rate variance: AnswerAnswerFULabor efficiency variance: $144 FVariable overheadStandard costs: Answer hours at $4.00 per direct labor hourActual cost: $10,600Variable overhead spending variance: $AnswerAnswerFUVariable overhead efficiency variance: $AnswerAnswerFU

  • Bovar Company began the manufacture of new paging machines. The company installed a standard costing system...

    Bovar Company began the manufacture of new paging machines. The company installed a standard costing system to account for manufacturing costs. The standard cost per unit is:               Direct materials   3 pound @ $5 per pound               Direct labor         .5 hours @ $20 per direct labor hour               Variable overhead       75% of direct labor cost Actual production was 4,000 units; actual sales were 2,500 units. There is no beginning inventory for direct materials. Other data are: Materials price variance is...

  • 1. Colina Production Company uses a standard costing system. The following information pertains to the current...

    1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34 setups and 34,000 machine hours to manufacture 8,500 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 85,000 Other 186,000 $ 271,000 Total factory overhead cost incurred $ 485,000 Variable factory overhead rate: Per setup $ 400 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 27,000 hours Machine hours actually worked...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT