Question

The following data for a pottery company pertain to the production of 2,000 clay pots during...

The following data for a pottery company pertain to the production

of 2,000 clay pots during July.

Direct Materials (all materials purchased were used):

Standard cost: $2.00 per kilogram of clay

Total actual cost: $10,640

Standard cost allowed for units produced was $12,000

Materials quantity variance was $800 favourable

Direct Manufacturing Labour:

Standard cost is 2 pots per hour at $24.00 per hour

Actual cost per hour was $24.50

Actual labour was 1028 hours

show all steps!

a. What is the standard direct material amount per pot (in Kilograms)?

b. What is the materials price variance?

None of the other answers are correct

$1,040 favourable

$560 unfavourable

$800 unfavourable

$800 favourable

$560 favourable

c. What is the labour efficiency variance?

$500 unfavourable

$672 favourable

$672 unfavourable

None of the other answers are correct

$28 favourable

$500 favourable

d. What is the labour rate variance?

$486 favourable

$672 unfavourable

None of the other answers are correct

$186 favourable

$486 unfavourable

$514 favourable

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
The following data for a pottery company pertain to the production of 2,000 clay pots during...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the total direct materials...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used) Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the direct manufacturing labour...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $6.00 per kilogram of clay Total actual cost: $11,200 Standard cost allowed for units produced was $12,000 Materials efficiency variance was $240 unfavourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 972 hours What is the standard direct material...

  • Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city...

    Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city in which a company has a factory. The company finds that they are able to pay new employees a lower wage per hour than when the unemployment rate was lower a year ago. Which variance is directly impacted? A) Materials price variance B) Materials efficiency variance C) Labour price variance D) Labour efficiency variance 2) Thomas Corporation produces stopwatches. According to company standards, it...

  • Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant...

    Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report: Budget Actual Variance Favourable (F)/ Unfavourable (U) Production in units 332,000 347,000 15,000 F Production costs:    Direct material $996,000 $1,017,940 $(21,940) U    Direct labour 1,411,000 1,442,700 (31,700) U    Variable overhead costs 166,000 172,957 (6,957) U    Fixed overhead costs 174,300 168,620 5,680 F Total production costs $2,747,300 $2,802,217 $(54,917) U The manager immediately called the production supervisor,...

  • Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...

    Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $6 per kilogram) $12.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.90 Fixed manufacturing overhead 6.25 Total standard cost per unit $54.15 Actual costs for producing 2,740 units were as follows: Direct materials used 5,560 kg Direct materials purchased (6,780 kg) $40,002 Direct labour (6,880 hours) $67,424 Variable manufacturing costs $32,600 Fixed manufacturing costs $17,600 Your...

  • Tidex Company is a manufacturer of cleaning detergent. Cleanx is manufactured on a weekly basis. The...

    Tidex Company is a manufacturer of cleaning detergent. Cleanx is manufactured on a weekly basis. The following standards have been established to produce 10,000 litres of Cleanx. Standard direct labour hours of 5,000 to mix 10,000 litres of detergent Standard direct labour rate per hour: $18 Actual direct labour hours consumed: 5,500 Actual direct labour rate: $18.45 Calculate the Labour Quantity Variance (LQV). $11,475 Favourable $9,000 Unfavourable $2,475 Favourable $2,475 Unfavourable Tidex Company is a manufacturer of cleaning detergent. Cleanx...

  • If the actual labour hours worked exceed the standard labour hours allowed, what type of variance...

    If the actual labour hours worked exceed the standard labour hours allowed, what type of variance will occur? Multiple Choice Favourable labour efficiency variance. ) Favourable labour rate variance. 0 Unfavourable labour efficiency variance. 0 Unfavourable labour rate variance. The standards for direct labour for a product are 2.5 hours at $8 per hour. Last month, 9,000 units of the product were made, and the labour efficiency variance was $8,000 favourable. What was the actual number of hours worked during...

  • The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given...

    The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 5.0   millilitres $ 0.30 per millilitre $ 1.50     Direct labour 0.4   hours $ 12.00 per hour $ 4.80   During the most recent month, the following activity was recorded: 28,000 millilitres of material was purchased at a cost of $0.25 per millilitre. All of the material was used to produce 3,000 bottles...

  • The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given...

    The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 7.0   millilitres $ 0.26 per millilitre $ 1.82     Direct labour 0.4   hours $ 12.00 per hour $ 4.80   During the most recent month, the following activity was recorded: 26,000 millilitres of material was purchased at a cost of $0.21 per millilitre. All of the material was used to produce 3,000 bottles...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT