Question

Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...

Jay Levitt Company budgeted the following cost standards for the current year:
Direct materials (2 kg of plastic at $6 per kilogram) $12.00
Direct labour (2 hours at $12 per hour) 24.00
Variable manufacturing overhead 11.90
Fixed manufacturing overhead 6.25
Total standard cost per unit $54.15

Actual costs for producing 2,740 units were as follows:
Direct materials used 5,560 kg
Direct materials purchased (6,780 kg) $40,002
Direct labour (6,880 hours) $67,424
Variable manufacturing costs $32,600
Fixed manufacturing costs $17,600
Partially correct answer. Your answer is partially correct. Try again.
Calculate the materials price variance for materials purchased.
Materials price variance $enter the materials price variance

Entry field with incorrect answer

select a type of the materials price variance

Entry field with correct answer UnfavourableFavourableNeither favourable nor unfavourable

Partially correct answer. Your answer is partially correct. Try again.
Calculate the materials quantity variance.
Materials quantity variance $enter the materials quantity variance

Entry field with incorrect answer

select a type of the materials quantity variance

Entry field with correct answer Neither favourable nor unfavourableFavourableUnfavourable

Partially correct answer. Your answer is partially correct. Try again.
Calculate the labour price variance. (Round answer to the nearest whole dollar, e.g. 5,275.)
Labour price variance $enter the labour price variance rounded to the nearest whole

Entry field with incorrect answer

select a type of the labour price variance

Entry field with correct answer UnfavourableFavourableNeither favourable nor unfavourable

Partially correct answer. Your answer is partially correct. Try again.
Calculate the labour quantity variance.
Labour quantity variance $enter the labour quantity variance

Entry field with incorrect answer

select a type of the labour quantity variance

Entry field with correct answer UnfavourableNeither favourable nor unfavourableFavourable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Material price variance = (Standard price-actual price)actual qty = (6*6780-40002) = 678 F

Material quantity variance = (2740*2-5560)*6 = 480 U

2) Labor rate variance = (12*6880-67424) = 15136 F

Labor efficiency variance = (2740*2-6880)*12 = 2800 u

Add a comment
Know the answer?
Add Answer to:
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • EWWIELS Helir n Jj , Managerial Accounting, Fifth Canadian Edition Concordia: Managerial Accounting (COMM 305 Practice...

    EWWIELS Helir n Jj , Managerial Accounting, Fifth Canadian Edition Concordia: Managerial Accounting (COMM 305 Practice Assignment Gradebook ORION Downloadable eTextbook signment FULL SCREEN PRINTER VERSION 8A Question 20 Mercuri Company has gathered the following information: Variable manufacturing overhead costs $12,330 Fixed manufacturing overhead costs Normal production level in labour hours $9,360 9,000 Standard labour hours 9,400 During the year, 3,490 units were produced, 10,600 hours were worked, and the actual manufacturing overhead was $20,300. Actual fixed overhead totalled $9,430...

  • Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant...

    Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report: Budget Actual Variance Favourable (F)/ Unfavourable (U) Production in units 332,000 347,000 15,000 F Production costs:    Direct material $996,000 $1,017,940 $(21,940) U    Direct labour 1,411,000 1,442,700 (31,700) U    Variable overhead costs 166,000 172,957 (6,957) U    Fixed overhead costs 174,300 168,620 5,680 F Total production costs $2,747,300 $2,802,217 $(54,917) U The manager immediately called the production supervisor,...

  • The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given...

    The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 5.0   millilitres $ 0.30 per millilitre $ 1.50     Direct labour 0.4   hours $ 12.00 per hour $ 4.80   During the most recent month, the following activity was recorded: 28,000 millilitres of material was purchased at a cost of $0.25 per millilitre. All of the material was used to produce 3,000 bottles...

  • The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given...

    The direct materials and direct labour standards for one bottle of Clean-All spray cleaner are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 7.0   millilitres $ 0.26 per millilitre $ 1.82     Direct labour 0.4   hours $ 12.00 per hour $ 4.80   During the most recent month, the following activity was recorded: 26,000 millilitres of material was purchased at a cost of $0.21 per millilitre. All of the material was used to produce 3,000 bottles...

  • The following data for a pottery company pertain to the production of 2,000 clay pots during...

    The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard cost: $2.00 per kilogram of clay Total actual cost: $10,640 Standard cost allowed for units produced was $12,000 Materials quantity variance was $800 favourable Direct Manufacturing Labour: Standard cost is 2 pots per hour at $24.00 per hour Actual cost per hour was $24.50 Actual labour was 1028 hours show all steps! a. What is...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $180 per ton Standard labor rate $14.50 per hour Standard materials price $182 per ton Quantities Actual hours incurred and used 4,700 hours Actual quantity of materials purchased and used 1,900 tons Standard hours used 4,760 hours Standard quantity of materials used 1,890 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • Mercuri Company has gathered the following information: Variable manufacturing overhead costs $13,680 Fixed manufacturing overhead costs...

    Mercuri Company has gathered the following information: Variable manufacturing overhead costs $13,680 Fixed manufacturing overhead costs $10,710 Normal production level in labour hours 9,000 Standard labour hours 9,500 During the year, 3,050 units were produced, 10,900 hours were worked, and the actual manufacturing overhead was $21,800. Actual fixed overhead totalled $10,800. Mercuri applies overhead based on direct labour hours. Calculate the total, fixed, and variable predetermined overhead rates.(Round answers to 2 decimal places, e.g. 15.25.) Fixed predetermined ovehead rate $...

  • What is the materials price variance? What is the materials quantity variance? What is the labour...

    What is the materials price variance? What is the materials quantity variance? What is the labour price variance? What is the labour quantity variance? Question 25 Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $5 per kilogram) Direct labour (2 hours at $12 per hour) Variable manufacturing overhead Fixed manufacturing overhead Total standard cost per unit $10.00 24.00 10.00 7.70 $51.70 Actual costs for producing 2,700 units were as...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT