Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant
was provided with the following variance analysis report:
Budget | Actual | Variance | Favourable (F)/ Unfavourable (U) |
|||||
Production in units | 332,000 | 347,000 | 15,000 | F | ||||
Production costs: | ||||||||
Direct material | $996,000 | $1,017,940 | $(21,940) | U | ||||
Direct labour | 1,411,000 | 1,442,700 | (31,700) | U | ||||
Variable overhead costs | 166,000 | 172,957 | (6,957) | U | ||||
Fixed overhead costs | 174,300 | 168,620 | 5,680 | F | ||||
Total production costs | $2,747,300 | $2,802,217 | $(54,917) | U |
The manager immediately called the production supervisor, demanding
an explanation for the large unfavourable variance for the quarter.
The production supervisor was puzzled. He thought the cost-cutting
measures they had incorporated were beginning to work. He certainly
wasn’t expecting such a large discrepancy.
The standard rates the plant was using with its normal costing
system are summarized below.
Volume | Cost | |||||
Direct material | 1.50 | kg per unit | $2.00 | per kg | ||
Direct labour | 0.25 | hour per unit | $17.00 | per hour | ||
Predetermined overhead rate: | ||||||
Variable | 0.25 | hour per unit | $2.00 | per hour | ||
Fixed | 0.25 | hour per unit | $2.10 | per hour |
Other relevant information:
1. | A total of 528,000 kg of direct materials were purchased during the quarter at a cost of $2.05 per kilogram. | |
2. | A total of 508,970 kg of direct materials were used in production to manufacture 347,000 units. | |
3. | Payroll recorded 85,875 direct labour hours at an average cost of $16.80 per hour. |
Calculate the following production variances.
Material price variance | $ |
Unfavourable / Neither favourable nor unfavourable / Favourable |
|
Material quantity variance | $ |
Unfavourable / Favourable / Neither favourable nor unfavourable |
|
Labour price variance | $ |
Unfavourable / Neither favourable nor unfavourable / Favourable |
|
Labour efficiency variance | $ |
Favourable / Neither favourable nor unfavourable / Unfavourable |
|
Variable overhead variance | $ |
Favourable / Neither favourable nor unfavourable / Unfavourable |
Material price variance = (Standard Price – Actual price)*Actual quantity purchased
= (2-2.05)*528000
= $26,400 Unfavorable
Material Quantity Variance = (Standard Quantity – Actual Quantity Used)*Standard Price
= (347000*1.5 – 508,970)*2
= $23,060 Favorable
Labor price variance = (Standard Rate – Actual Rate)*Actual Hours
= (17-16.80)*85875
= $17,175 Favorable
Labor Efficiency variance = (Standard Hours – Actual Hours)*Standard Rate
= (347000*0.25 – 85875)*17
= $14,875 Favorable
Variable overhead variance = Standard Cost – Actual Cost
= 347000*0.25*2 – 172957
= $543 Favorable
Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant...
Question: Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report: Favourable (F)/ Unfavourable (U) Budget Actual Variance Production in units 310,000 323,000 13,000 Production costs: Direct material $(11,781) (25,440) (4,538) $737,800 $749,581 U Direct labour Variable overhead costs Fixed overhead costs 1,395,000 131,750 147,250 1,420,440 U 136,288 U 139,870 7,380 F Total production costs $(34,379) $2,411,800 $2,446,179 U The manager immediately called the production supervisor,...
Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Favourable (F)/ Unfavourable (U) Budget 310,000 Actual 323,000 Variance 13,000 п Production in units Production costs: Direct material Direct labour Variable overhead costs Fixed overhead costs Total production costs $742,109 1,395,000 131,750 147,250 $2,416,109 $749,581 1,420,440 135,821 139,870 $2,445,712 $(7,472) (25,440) (4,071) 7,380 $(29,603) псс с The manager immediately called the production supervisor, demanding an explanation for the...
Mercuri Company has gathered the following information: Variable manufacturing overhead costs $13,680 Fixed manufacturing overhead costs $10,710 Normal production level in labour hours 9,000 Standard labour hours 9,500 During the year, 3,050 units were produced, 10,900 hours were worked, and the actual manufacturing overhead was $21,800. Actual fixed overhead totalled $10,800. Mercuri applies overhead based on direct labour hours. Calculate the total, fixed, and variable predetermined overhead rates.(Round answers to 2 decimal places, e.g. 15.25.) Fixed predetermined ovehead rate $...
Question 24 Rondell Company uses standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed Actual direct labour hours Fixed overhead Variable overhead 9,070 10,600 $179,000 $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance Calculate the variable overhead spending variance. Variable overhead spending variance $ Calculate the variable overhead efficiency variance. Variable overhead efficiency...
Jay Levitt Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $6 per kilogram) $12.00 Direct labour (2 hours at $12 per hour) 24.00 Variable manufacturing overhead 11.90 Fixed manufacturing overhead 6.25 Total standard cost per unit $54.15 Actual costs for producing 2,740 units were as follows: Direct materials used 5,560 kg Direct materials purchased (6,780 kg) $40,002 Direct labour (6,880 hours) $67,424 Variable manufacturing costs $32,600 Fixed manufacturing costs $17,600 Your...
Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city in which a company has a factory. The company finds that they are able to pay new employees a lower wage per hour than when the unemployment rate was lower a year ago. Which variance is directly impacted? A) Materials price variance B) Materials efficiency variance C) Labour price variance D) Labour efficiency variance 2) Thomas Corporation produces stopwatches. According to company standards, it...
ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...
Muddy Duck Manufacturing (MDM) Inc.’s costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead, both fixed and variable, is allocated to products on the basis of standard direct manufacturing labour hours (DMLH). At the beginning of 2017, MDM adopted the following standards for its manufacturing costs: Input Cost per output unit Direct materials 3kg @ $5 per kg $15 Direct manufacturing labour 5 hours @ $15 per hour 75 Manufacturing overhead: Variable $6 per...
Waterways Continuing Problem 11 a-g Waterways Corporation uses very stringent standard costs in evaluating its manufacturing efficiency. These standards are not “ideal” at this point, but the management is working toward that as a goal. At present, the company uses the following standards. Materials Item Per unit Cost Metal 1 lb. 63¢ per lb. Plastic 12 oz. $1.00 per lb. Rubber 4 oz. 88¢ per lb. Direct labor Item Per unit Cost Labor 15 min. $9.00 per hr. Predetermined overhead...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $8.00 per kg $ 32.00 Direct labour: 2 hours at $16 per hour 32.00 Variable overhead: 2 hours at $6 per hour 12.00 Total standard cost per unit $ 76.00 The company planned to produce and sell 32,000 units in March. However, during March the company actually produced and...