(A)
Material price variance = actual quantity purchased x (standard price - actual price)
= 460000 x ($1.70 - $1.90)
= $92000 Unfavorable
(B)
Material quantity variance = standard price x (standard quantity - actual quantity used)
= $1.70 x (452200 - 440930)
= $19159 Favorable
Where,
Standard quantity = actual output x standard quantity per unit of output
= 323000 x 1.40 = 452200
(C)
Labor price variance = actual hours x (standard rate - actual rate)
= 79800 x ($18 - $17.80)
= $15960 Favorable
(D)
Labor efficiency variance = standard rate x (standard hours - actual hours)
= $18 x (80750 - 79800)
= $17100 Favorable
Where,
Standard hours = actual output x standard hours per unit of output
= 323000 x 0.25 = 80750 hours
Question: Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing...
Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Favourable (F)/ Unfavourable (U) Budget 310,000 Actual 323,000 Variance 13,000 п Production in units Production costs: Direct material Direct labour Variable overhead costs Fixed overhead costs Total production costs $742,109 1,395,000 131,750 147,250 $2,416,109 $749,581 1,420,440 135,821 139,870 $2,445,712 $(7,472) (25,440) (4,071) 7,380 $(29,603) псс с The manager immediately called the production supervisor, demanding an explanation for the...
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant
was provided with the following variance analysis report:
Budget
Actual
Variance
Favourable (F)/
Unfavourable (U)
Production in units
332,000
347,000
15,000
F
Production costs:
Direct material
$996,000
$1,017,940
$(21,940)
U
Direct labour
1,411,000
1,442,700
(31,700)
U
Variable overhead costs
166,000
172,957
(6,957)
U
Fixed overhead costs
174,300
168,620
5,680
F
Total production costs
$2,747,300
$2,802,217
$(54,917)
U
The manager immediately called the production supervisor,...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $8.00 per kg $ 32.00 Direct labour: 2 hours at $16 per hour 32.00 Variable overhead: 2 hours at $6 per hour 12.00 Total standard cost per unit $ 76.00 The company planned to produce and sell 32,000 units in March. However, during March the company actually produced and...
ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $9.00 per kg $ 36.00 Direct labour: 3 hours at $12 per hour 36.00 Variable overhead: 3 hours at $8 per hour 24.00 Total standard cost per unit $ 96.00 The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $9.00 per kg Direct labour: 3 hours at $15 per hour Variable overhead: 3 hours at $5 per hour $ 54.00 45.00 15.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...